WSDOT contract XE3751 bid tabulation
Us 395 Kartchner St I/C Nb Ramp Terminal Improvements. Let by Washington State DOT on July 8, 2026, Franklin, SCR region. 4 bids received; low bid $1,093,111 by Tapani, Inc., +3.8% against the engineer's estimate of $1,053,188.
- Owner
- Washington State DOT
- Letting
- 08 JUL 2026
- Pay items
- 54
- Data through
- 07 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Tapani, Inc. | $1,093,111 | Low | +4.0% |
| 2 | Culbert Construction, Inc. | $1,115,000 | +2.0% | +6.0% |
| 3 | Granite Construction Company | $1,161,539 | +6.0% | +10% |
| 4 | Apollo, Inc. | $1,220,000 | +12% | +16% |
Engineer's estimate: $1,053,188.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Tapani, Inc. | 2. Culbert Construction, Inc. | 3. Granite Construction Company | 4. Apollo, Inc. |
|---|---|---|---|---|---|---|---|---|
| 1 | Mobilization | LS | 1 | $94,821 | $100,000 | $120,699 | $115,000 | $118,373 |
| 2 | Clearing and grubbing | ACRE | 0.14 | $55,000 | $16,000 | $41,389 | $25,000 | $3,800.00 |
| 3 | Removing miscellaneous traffic item | LS | 1 | $10,120 | $34,000 | $76,993 | $20,000 | $25,000 |
| 4 | Roadway excavation including haul | CY | 393 | $40.00 | $288.00 | $161.95 | $167.00 | $341.00 |
| 5 | Common borrow including haul | CY | 176 | $40.00 | $23.00 | $92.05 | $75.00 | $15.00 |
| 6 | Embankment compaction | CY | 553 | $30.00 | $20.00 | $32.86 | $31.00 | $23.00 |
| 7 | Quarry spalls | TON | 8 | $120.00 | $74.00 | $172.96 | $235.00 | $171.50 |
| 8 | Catch basin type 1 | EACH | 1 | $3,000.00 | $6,000.00 | $4,044.83 | $4,500.00 | $5,900.00 |
| 9 | Schedule A storm sewer pipe 12 inch diameter | LF | 27 | $120.00 | $130.00 | $71.80 | $196.00 | $123.00 |
| 10 | Crushed surfacing base course | TON | 420 | $55.00 | $67.00 | $81.17 | $175.00 | $40.00 |
| 11 | Textured and pigmented cement concrete pavement | SY | 850 | $130.00 | $142.00 | $98.60 | $108.00 | $107.00 |
| 12 | Cement concrete pavement | CY | 155 | $450.00 | $620.00 | $514.54 | $500.00 | $907.50 |
| 13 | Sealing cement concrete pavement to hot mix asphalt longit joints | LF | 316 | $30.00 | $12.00 | $11.28 | $31.00 | $49.00 |
| 14 | Hot mix asphalt class 1/2 inch PG 64H-28 | TON | 120 | $400.00 | $365.00 | $330.82 | $500.00 | $368.00 |
| 15 | Job mix compliance price adjustment | CALC | 1 | $900.00 | $900.00 | $900.00 | $900.00 | $900.00 |
| 16 | Compaction price adjustment | CALC | 1 | $1,500.00 | $1,500.00 | $1,500.00 | $1,500.00 | $1,500.00 |
| 17 | Asphalt cost price adjustment | CALC | 1 | $65.00 | $65.00 | $65.00 | $65.00 | $65.00 |
| 18 | Erosion control and water pollution prevention | LS | 1 | $5,000.00 | $24,107 | $716.94 | $22,225 | $1,710.00 |
| 19 | Seeding, fertilizing, and mulching | ACRE | 0.42 | $10,000 | $9,000.00 | $9,225.11 | $9,150.00 | $11,100 |
| 20 | Medium compost | ACRE | 0.42 | $25,000 | $7,800.00 | $7,687.59 | $7,600.00 | $9,242.00 |
| 21 | High visibility fence | LF | 960 | $8.00 | $8.00 | $9.03 | $11.50 | $5.75 |
| 22 | Roundabout splitter island nosing curb | EACH | 5 | $1,000.00 | $950.00 | $788.43 | $285.00 | $320.00 |
| 23 | Roundabout cement concrete curb and gutter | LF | 1,877 | $45.00 | $51.00 | $56.15 | $55.00 | $50.00 |
| 24 | Cement concrete traffic curb and gutter | LF | 108 | $60.00 | $41.00 | $50.64 | $44.00 | $34.00 |
| 25 | Roundabout truck apron cem. concrete curb and gutter | LF | 373 | $70.00 | $52.00 | $52.53 | $55.00 | $50.00 |
| 26 | Cement concrete pedestrian curb | LF | 60 | $50.00 | $44.00 | $48.88 | $47.75 | $32.00 |
| 27 | Flexible guide post | EACH | 5 | $150.00 | $110.00 | $102.50 | $100.00 | $200.00 |
| 28 | Plastic line | LF | 3,640 | $3.00 | $6.00 | $5.38 | $5.35 | $1.55 |
| 29 | Plastic crosswalk line | SF | 240 | $10.00 | $13.50 | $12.30 | $12.20 | $11.70 |
| 30 | Plastic traffic arrow | EACH | 1 | $800.00 | $510.00 | $461.26 | $455.00 | $707.00 |
| 31 | Plastic traffic letter | EACH | 4 | $220.00 | $255.00 | $230.63 | $230.00 | $370.00 |
| 32 | Permanent signing | LS | 1 | $11,500 | $30,000 | $27,675 | $27,500 | $34,300 |
| 33 | Illumination system kartchner ST | LS | 1 | $82,000 | $87,000 | $80,928 | $64,000 | $91,000 |
| 34 | Project temporary traffic control | LS | 1 | $250,800 | $65,000 | $158,877 | $181,000 | $187,500 |
| 35 | Work zone safety contingency | EST | 1 | $25,000 | $25,000 | $25,000 | $25,000 | $25,000 |
| 36 | Construction signs class A | SF | 96 | $40.00 | $35.00 | $24.60 | $28.00 | $312.50 |
| 37 | Plastic crosshatch marking | LF | 300 | $10.00 | $11.25 | $10.25 | $10.00 | $3.00 |
| 38 | Plastic wide line | LF | 640 | $5.00 | $11.00 | $10.76 | $10.50 | $5.00 |
| 39 | Structure excavation class B including haul | CY | 20 | $140.00 | $31.00 | $20.77 | $76.00 | $100.00 |
| 40 | Roadway surveying | LS | 1 | $20,000 | $42,000 | $19,707 | $11,000 | $12,000 |
| 41 | ADA features surveying | LS | 1 | $5,000.00 | $9,000.00 | $1,210.99 | $3,500.00 | $3,900.00 |
| 42 | Cement concrete sidewalk | SY | 344 | $80.00 | $99.00 | $104.50 | $82.00 | $83.50 |
| 43 | Cement concrete curb ramp type parallel A | EACH | 1 | $3,000.00 | $2,700.00 | $2,582.30 | $7,400.00 | $2,225.00 |
| 44 | Cement concrete curb ramp type parallel B | EACH | 2 | $3,000.00 | $2,700.00 | $2,561.80 | $7,400.00 | $2,200.00 |
| 45 | Cement concrete curb ramp type perpendicular A | EACH | 1 | $3,000.00 | $2,500.00 | $2,458.28 | $7,400.00 | $2,087.00 |
| 46 | Detectable warning surface | SF | 51 | $40.00 | $31.00 | $29.73 | $30.00 | $33.10 |
| 47 | Roadside cleanup | EST | 1 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 |
| 48 | Reimbursement for third party damage | EST | 1 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 49 | Minor change | CALC | 1 | -$4.00 | -$4.00 | -$4.00 | -$4.00 | -$4.00 |
| 50 | Aggregate compliance price adjustment | CALC | 1 | -$4.00 | -$4.00 | -$4.00 | -$4.00 | -$4.00 |
| 51 | Spill prevention, control, and countermeasures plan | LS | 1 | $500.00 | $2,500.00 | $151.37 | $500.00 | $1,200.00 |
| 52 | Construction geotextile for permanent erosion control | SY | 12 | $30.00 | $11.00 | $77.62 | $55.00 | $10.10 |
| 53 | Pavement repair excavation including haul | SY | 59 | $40.00 | $25.00 | $33.93 | $60.00 | $246.50 |
| 54 | Hot mix asphalt for pavement repair class 1/2 inch PG 64H-28 | TON | 8 | $700.00 | $350.00 | $330.82 | $1,000.00 | $1,090.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WSDOT's tabulation for this contract. WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
Every contract let that day: WSDOT letting of July 8, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.