Common borrow including haul, WSDOT
Low bidders on WSDOT contracts carried a median of $24.50 per CY for this item, over the 24 months to 07 OCT 2026, across 2 low bids. Half of all 10 bids fell between $16.75 and $62.75.
- Owner
- Washington State DOT
- Item
- No code published
- Unit
- CY
- Data through
- 07 OCT 2026
WSDOT prints this item as “COMMON BORROW INCL. HAUL”.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2000 | 1 | 0 | n/a | 8 | $6.55 |
| 2002 | 4 | 4 | $21.00 | 18 | $12.30 |
| 2003 | 3 | 3 | $10.00 | 12 | $17.75 |
| 2004 | 4 | 4 | $14.50 | 17 | $18.00 |
| 2005 | 5 | 4 | $25.00 | 21 | $15.00 |
| 2006 | 7 | 7 | $12.00 | 27 | $15.00 |
| 2007 | 5 | 5 | $4.29 | 22 | $6.25 |
| 2008 | 3 | 3 | $15.00 | 15 | $8.50 |
| 2009 | 10 | 9 | $21.00 | 70 | $15.00 |
| 2010 | 9 | 9 | $12.00 | 53 | $12.00 |
| 2011 | 3 | 2 | $39.62 | 34 | $19.05 |
| 2012 | 4 | 4 | $15.88 | 34 | $19.00 |
| 2013 | 2 | 2 | $76.00 | 10 | $42.50 |
| 2015 | 3 | 3 | $15.00 | 15 | $35.00 |
| 2016 | 3 | 3 | $10.00 | 16 | $18.18 |
| 2017 | 4 | 4 | $21.50 | 19 | $22.00 |
| 2018 | 2 | 1 | $17.00 | 11 | $16.96 |
| 2019 | 6 | 6 | $22.00 | 23 | $35.00 |
| 2020 | 2 | 2 | $43.00 | 7 | $46.00 |
| 2021 | 7 | 7 | $29.49 | 23 | $25.00 |
| 2022 | 6 | 6 | $35.00 | 13 | $42.41 |
| 2023 | 4 | 4 | $51.60 | 13 | $43.20 |
| 2026 | 2 | 2 | $24.50 | 10 | $23.50 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| SCR region | 28 | $20.00 | 169 | $17.00 |
| ER region | 26 | $13.50 | 97 | $15.00 |
| NWR region | 12 | $23.66 | 83 | $18.00 |
| OR region | 12 | $42.60 | 66 | $43.80 |
| NCR region | 9 | $10.00 | 40 | $10.88 |
| SWR region | 6 | $15.50 | 21 | $16.00 |
Regions with at least three low bids, over all lettings.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 5 to 160 | 23 | $40.00 |
| 176 to 700 | 24 | $20.50 |
| 720 to 3,000 | 23 | $18.88 |
| 3,180 to 379,580 | 24 | $8.25 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Tri-State Construction, Inc. | 10 | 7 (70%) |
| Granite Construction Company | 14 | 5 (36%) |
| Central Washington Asphalt, I | 10 | 4 (40%) |
| Max J. Kuney Company | 13 | 3 (23%) |
| Apollo, Inc. | 10 | 3 (30%) |
| Midmountain Contractors, Inc. | 9 | 3 (33%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 08 JUL 2026 | XE3751 | SCR region | 176 | $23.00 | $49.00 | $40.00 | 4 | Tapani, Inc. | WSDOT |
| 01 JUL 2026 | XE3756 | SCR region | 936 | $26.00 | $23.00 | $60.00 | 6 | N.A. Degerstrom, Inc. | WSDOT |
| 19 APR 2023 | 009952 | SCR region | 700 | $65.00 | $60.50 | $25.00 | 4 | Interstate Concrete & Asphalt | WSDOT |
| 12 APR 2023 | 009945 | SCR region | 13 | $60.00 | $60.00 | $40.00 | 3 | Kraemer North America, LLC. | WSDOT |
| 23 FEB 2023 | 009925 | ER region | 27,860 | $12.00 | $16.00 | $13.00 | 2 | Max J. Kuney Company | WSDOT |
| 01 FEB 2023 | 009921 | NCR region | 8,880 | $43.20 | $37.50 | $30.00 | 4 | Johansen Construction Company, | WSDOT |
| 13 APR 2022 | 009796 | NWR region | 280 | $22.32 | $76.16 | $21.20 | 2 | Granite Construction Company | WSDOT |
| 06 APR 2022 | 009789 | OR region | 362 | $35.00 | $42.41 | $55.00 | 3 | Interwest Construction, Inc. | WSDOT |
| 23 MAR 2022 | 009784 | ER region | 5 | $425.00 | $425.00 | $25.00 | 1 | Central Washington Asphalt, In | WSDOT |
| 16 MAR 2022 | 00000 | NWR region | 64 | $27.00 | $27.00 | $30.00 | 1 | Skycorp, LTD | WSDOT |
| 16 MAR 2022 | 009794 | OR region | 1,040 | $45.20 | $46.22 | $20.00 | 4 | Scarsella Bros., Inc. | WSDOT |
| 24 FEB 2022 | 009767 | NCR region | 100 | $35.00 | $30.00 | $44.00 | 2 | Granite Construction Company | WSDOT |
| 24 MAR 2021 | 009636 | OR region | 6,435 | $47.00 | $52.50 | $20.00 | 4 | Graham Contracting, LTD. | WSDOT |
| 24 MAR 2021 | 009664 | SWR region | 1,081 | $40.00 | $60.00 | $30.00 | 3 | McDonald Excavating, Inc. | WSDOT |
| 24 MAR 2021 | 009656 | NWR region | 3,180 | $30.00 | $21.50 | $15.00 | 4 | Marshbank Construction, Inc. | WSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.
How these prices were read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the WSDOT letting of 07 OCT 2026 and was rebuilt on 26 NOV 2026.