WSDOT contract XE3756 bid tabulation

I-90 Hansen Rd Overpass Emergency Bridge Replacement. Let by Washington State DOT on July 1, 2026, Grant, SCR region. 6 bids received; low bid $5,406,051 by N.A. Degerstrom, Inc., -5.6% against the engineer's estimate of $5,727,319.

Owner
Washington State DOT
Letting
01 JUL 2026
Pay items
68
Data through
07 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1N.A. Degerstrom, Inc.$5,406,051Low-6.0%
2Johansen Construction Company,$5,669,669+5.0%-1.0%
3Garco Construction, Inc.$6,124,999+13%+7.0%
4Interwest Construction, Inc.$6,262,626+16%+9.0%
5Granite Construction Company$7,576,200+40%+32%
6Ceccanti, Inc.$8,339,495+54%+46%
WSDOT contract XE3756: bids by rank

Engineer's estimate: $5,727,319.

Bid tabulation

LinePay itemUnitQuantityEstimate1. N.A. Degerstrom, Inc.2. Johansen Construction Company,3. Garco Construction, Inc.4. Interwest Construction, Inc.5. Granite Construction Company6. Ceccanti, Inc.
1MobilizationLS1$519,758$500,000$560,750$600,000$623,069$687,000$1,650,000
2Removal of structures and obstructionsLS1$17,850$15,500$18,070$20,000$26,000$16,900$30,000
3Removing shaft obstructionsEST1$47,500$47,500$47,500$47,500$47,500$47,500$47,500
4Roadway excavation including haulCY1,718$75.00$30.00$58.70$60.00$58.00$62.00$100.00
5Common borrow including haulCY936$60.00$26.00$2.20$100.00$15.00$22.00$24.00
6Embankment compactionCY851$40.00$16.00$25.20$25.00$10.00$41.00$5.00
7Quarry spallsCY12$175.00$140.00$138.00$275.00$125.00$220.00$100.00
8Catch basin type 1EACH4$6,000.00$4,000.00$2,867.00$5,500.00$2,600.00$4,900.00$2,000.00
9Schedule A storm sewer pipe 12 inch diameterLF32$175.00$165.00$104.50$270.00$145.00$320.00$150.00
10Structure excavation class A including haulCY570$200.00$30.00$46.00$65.00$25.00$57.00$80.00
11Shoring or extra excavation class A hansen bridgeLS1$30,020$15,000$8,734.00$30,000$150,000$22,100$75,000
12Constructing 5 FT. diameter shaftLF300$2,000.00$2,000.00$2,105.00$1,900.00$1,580.00$1,750.00$1,400.00
13Constructing 7 FT. diameter shaftLF100$3,500.00$3,700.00$4,368.00$3,300.00$3,100.00$3,420.00$2,000.00
14Steel reinf. bar for bridgeLB51,495$2.00$2.00$1.95$1.55$2.25$3.00$2.00
15QA shaft testEACH8$2,700.00$2,500.00$3,649.00$3,500.00$6,500.00$3,190.00$1,600.00
16Concrete class 4000 for bridgeCY175$1,750.00$1,300.00$2,484.00$2,400.00$2,035.00$3,490.00$4,000.00
17Superstructure BR no 90/216LS1$930,000$1,225,000$972,654$1,349,313$1,200,000$1,314,000$1,500,000
18Bridge railing type BP - superstr.LF530$300.00$165.00$125.50$200.00$115.00$250.00$130.00
19Traffic barrierLF530$550.00$440.00$433.50$400.00$460.00$620.00$490.00
20Bridge approach slabSY190$550.00$600.00$836.00$800.00$600.00$890.00$350.00
21Force account - deck repairEST1$200,000$200,000$200,000$200,000$200,000$200,000$200,000
22Permanent debris catchment systemLS1$160,000$160,000$226,885$150,000$150,000$576,000$670,000
23Crushed surfacing base courseTON220$75.00$90.00$43.90$90.00$42.00$170.00$100.00
24Hot mix asphalt class 1/2 inch PG 64H-28TON76$500.00$820.00$874.00$900.00$875.00$640.00$800.00
25Job mix compliance price adjustmentCALC1$1,140.00$1,140.00$1,140.00$1,140.00$1,140.00$1,140.00$1,140.00
26Compaction price adjustmentCALC1$1,900.00$1,900.00$1,900.00$1,900.00$1,900.00$1,900.00$1,900.00
27Asphalt cost price adjustmentCALC1$28.00$28.00$28.00$28.00$28.00$28.00$28.00
28Inlet protectionEACH6$150.00$145.00$109.50$350.00$100.00$97.00$100.00
29Stabilized construction entranceSY450$10.00$29.00$20.50$23.00$30.00$20.00$37.00
30Erosion/water pollution controlEST1$10,000$10,000$10,000$10,000$10,000$10,000$10,000
31Seeding, fertilizing, and mulchingACRE2.30$10,000$8,000.00$8,682.00$8,000.00$9,000.00$7,760.00$7,500.00
32Medium compostACRE2.30$25,000$29,000$31,467$30,000$37,000$32,000$7,500.00
33High visibility silt fenceLF2,020$15.00$4.00$6.80$7.50$10.00$6.00$7.50
34Erosion control blanketSY80$100.00$6.00$2.10$24.00$13.00$5.00$17.00
35Beam guardrail transition section type 21EACH2$7,500.00$6,000.00$6,760.00$6,500.00$7,500.00$7,300.00$9,000.00
36Beam guardrail transition section type 24EACH4$7,500.00$2,200.00$2,447.00$2,400.00$2,700.00$2,640.00$3,500.00
37Beam guardrail type 31 non-flared terminalEACH2$6,000.00$4,300.00$4,895.00$4,800.00$5,400.00$5,550.00$4,300.00
38Precast concrete barrier type F unanchoredLF1,530$125.00$150.00$169.00$165.00$185.00$270.00$160.00
39Single slope concrete barrierLF240$275.00$300.00$337.00$315.00$350.00$430.00$200.00
40Temporary barrierLF480$40.00$48.00$53.60$55.00$59.00$63.00$75.00
41High-tension cable barrier system (4 cable)LF1,250$45.00$86.00$97.90$96.00$58.00$54.00$55.00
42Additional high-tension cable barrier componentsLS1$10,000$45,000$52,444$50,000$58,000$12,700$14,000
43Temporary impact attenuatorEACH4$7,500.00$4,500.00$5,244.00$5,000.00$5,800.00$6,350.00$1,000.00
44Resetting impact attenuatorEACH1$2,500.00$2,800.00$3,263.00$3,500.00$3,700.00$3,890.00$650.00
45Linear delineation panel for concrete barrierEACH54$65.00$70.00$79.30$75.00$89.00$79.00$80.00
46Paint lineLF5,350$0.50$0.23$1.15$1.25$1.25$1.00$2.00
47Shoulder rumble strip type 2MI0.69$25,000$25,000$13,985$16,000$17,000$10,000$14,000
48Temporary pavement marking-short durationLF5,550$1.00$0.20$1.30$4.00$3.50$3.00$3.00
49Bridge mounted sign bracket no. 1LS1$21,000$22,000$26,360$35,000$38,000$57,000$37,000
50Bridge mounted sign bracket no. 2LS1$21,000$22,000$26,360$35,000$38,000$57,000$37,000
51Conduit pipe 2 inch diameterLF1,060$120.00$85.00$78.70$72.00$75.00$65.00$92.00
52Portable changeable message signHR144,000$1.00$0.25$0.25$0.01$2.00$2.00$0.50
53Project temporary traffic controlLS1$412,680$300,000$220,539$400,000$500,000$625,000$950,000
54Work zone safety contingencyEST1$50,000$50,000$50,000$50,000$50,000$50,000$50,000
55Construction signs class ASF364$75.00$33.00$28.20$30.00$50.00$36.00$60.00
56WSP reimbursementCALC1-$1.00-$1.00-$1.00-$1.00-$1.00-$1.00-$1.00
57Project partneringCALC1$10,000$10,000$10,000$10,000$10,000$10,000$10,000
58Structure surveyingLS1$20,000$20,000$35,913$30,000$45,000$31,400$67,000
59Roadway surveyingLS1$5,000.00$20,000$22,161$20,000$25,000$19,400$57,000
60Roadside cleanupEST1$5,000.00$5,000.00$5,000.00$5,000.00$5,000.00$5,000.00$5,000.00
61Reimbursement for third party damageEST1$5.00$5.00$5.00$5.00$5.00$5.00$5.00
62Minor changeCALC1-$9.00-$9.00-$9.00-$9.00-$9.00-$9.00-$9.00
63Fuel cost adjustmentCALC1-$9.00-$9.00-$9.00-$9.00-$9.00-$9.00-$9.00
64Steel cost adjustmentCALC1-$9.00-$9.00-$9.00-$9.00-$9.00-$9.00-$9.00
65Aggregate compliance price adjustmentCALC1-$9.00-$9.00-$9.00-$9.00-$9.00-$9.00-$9.00
66Spill prevention, control, and countermeasures planLS1$5,000.00$2,500.00$3,500.00$5,000.00$1,500.00$5,090.00$1,200.00
67Construction geotextile for permanent erosion controlSY20$25.00$20.00$3.00$23.00$60.00$20.00$10.00
68Superstructure - elastomeric bearing padEACH10$2,000.00$1,500.00$2,086.00$2,000.00$2,500.00$2,940.00$1,000.00
WSDOT contract XE3756: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WSDOT's tabulation for this contract. WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.

Every contract let that day: WSDOT letting of July 1, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy