WSDOT contract XE3756 bid tabulation
I-90 Hansen Rd Overpass Emergency Bridge Replacement. Let by Washington State DOT on July 1, 2026, Grant, SCR region. 6 bids received; low bid $5,406,051 by N.A. Degerstrom, Inc., -5.6% against the engineer's estimate of $5,727,319.
- Owner
- Washington State DOT
- Letting
- 01 JUL 2026
- Pay items
- 68
- Data through
- 07 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | N.A. Degerstrom, Inc. | $5,406,051 | Low | -6.0% |
| 2 | Johansen Construction Company, | $5,669,669 | +5.0% | -1.0% |
| 3 | Garco Construction, Inc. | $6,124,999 | +13% | +7.0% |
| 4 | Interwest Construction, Inc. | $6,262,626 | +16% | +9.0% |
| 5 | Granite Construction Company | $7,576,200 | +40% | +32% |
| 6 | Ceccanti, Inc. | $8,339,495 | +54% | +46% |
Engineer's estimate: $5,727,319.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. N.A. Degerstrom, Inc. | 2. Johansen Construction Company, | 3. Garco Construction, Inc. | 4. Interwest Construction, Inc. | 5. Granite Construction Company | 6. Ceccanti, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Mobilization | LS | 1 | $519,758 | $500,000 | $560,750 | $600,000 | $623,069 | $687,000 | $1,650,000 |
| 2 | Removal of structures and obstructions | LS | 1 | $17,850 | $15,500 | $18,070 | $20,000 | $26,000 | $16,900 | $30,000 |
| 3 | Removing shaft obstructions | EST | 1 | $47,500 | $47,500 | $47,500 | $47,500 | $47,500 | $47,500 | $47,500 |
| 4 | Roadway excavation including haul | CY | 1,718 | $75.00 | $30.00 | $58.70 | $60.00 | $58.00 | $62.00 | $100.00 |
| 5 | Common borrow including haul | CY | 936 | $60.00 | $26.00 | $2.20 | $100.00 | $15.00 | $22.00 | $24.00 |
| 6 | Embankment compaction | CY | 851 | $40.00 | $16.00 | $25.20 | $25.00 | $10.00 | $41.00 | $5.00 |
| 7 | Quarry spalls | CY | 12 | $175.00 | $140.00 | $138.00 | $275.00 | $125.00 | $220.00 | $100.00 |
| 8 | Catch basin type 1 | EACH | 4 | $6,000.00 | $4,000.00 | $2,867.00 | $5,500.00 | $2,600.00 | $4,900.00 | $2,000.00 |
| 9 | Schedule A storm sewer pipe 12 inch diameter | LF | 32 | $175.00 | $165.00 | $104.50 | $270.00 | $145.00 | $320.00 | $150.00 |
| 10 | Structure excavation class A including haul | CY | 570 | $200.00 | $30.00 | $46.00 | $65.00 | $25.00 | $57.00 | $80.00 |
| 11 | Shoring or extra excavation class A hansen bridge | LS | 1 | $30,020 | $15,000 | $8,734.00 | $30,000 | $150,000 | $22,100 | $75,000 |
| 12 | Constructing 5 FT. diameter shaft | LF | 300 | $2,000.00 | $2,000.00 | $2,105.00 | $1,900.00 | $1,580.00 | $1,750.00 | $1,400.00 |
| 13 | Constructing 7 FT. diameter shaft | LF | 100 | $3,500.00 | $3,700.00 | $4,368.00 | $3,300.00 | $3,100.00 | $3,420.00 | $2,000.00 |
| 14 | Steel reinf. bar for bridge | LB | 51,495 | $2.00 | $2.00 | $1.95 | $1.55 | $2.25 | $3.00 | $2.00 |
| 15 | QA shaft test | EACH | 8 | $2,700.00 | $2,500.00 | $3,649.00 | $3,500.00 | $6,500.00 | $3,190.00 | $1,600.00 |
| 16 | Concrete class 4000 for bridge | CY | 175 | $1,750.00 | $1,300.00 | $2,484.00 | $2,400.00 | $2,035.00 | $3,490.00 | $4,000.00 |
| 17 | Superstructure BR no 90/216 | LS | 1 | $930,000 | $1,225,000 | $972,654 | $1,349,313 | $1,200,000 | $1,314,000 | $1,500,000 |
| 18 | Bridge railing type BP - superstr. | LF | 530 | $300.00 | $165.00 | $125.50 | $200.00 | $115.00 | $250.00 | $130.00 |
| 19 | Traffic barrier | LF | 530 | $550.00 | $440.00 | $433.50 | $400.00 | $460.00 | $620.00 | $490.00 |
| 20 | Bridge approach slab | SY | 190 | $550.00 | $600.00 | $836.00 | $800.00 | $600.00 | $890.00 | $350.00 |
| 21 | Force account - deck repair | EST | 1 | $200,000 | $200,000 | $200,000 | $200,000 | $200,000 | $200,000 | $200,000 |
| 22 | Permanent debris catchment system | LS | 1 | $160,000 | $160,000 | $226,885 | $150,000 | $150,000 | $576,000 | $670,000 |
| 23 | Crushed surfacing base course | TON | 220 | $75.00 | $90.00 | $43.90 | $90.00 | $42.00 | $170.00 | $100.00 |
| 24 | Hot mix asphalt class 1/2 inch PG 64H-28 | TON | 76 | $500.00 | $820.00 | $874.00 | $900.00 | $875.00 | $640.00 | $800.00 |
| 25 | Job mix compliance price adjustment | CALC | 1 | $1,140.00 | $1,140.00 | $1,140.00 | $1,140.00 | $1,140.00 | $1,140.00 | $1,140.00 |
| 26 | Compaction price adjustment | CALC | 1 | $1,900.00 | $1,900.00 | $1,900.00 | $1,900.00 | $1,900.00 | $1,900.00 | $1,900.00 |
| 27 | Asphalt cost price adjustment | CALC | 1 | $28.00 | $28.00 | $28.00 | $28.00 | $28.00 | $28.00 | $28.00 |
| 28 | Inlet protection | EACH | 6 | $150.00 | $145.00 | $109.50 | $350.00 | $100.00 | $97.00 | $100.00 |
| 29 | Stabilized construction entrance | SY | 450 | $10.00 | $29.00 | $20.50 | $23.00 | $30.00 | $20.00 | $37.00 |
| 30 | Erosion/water pollution control | EST | 1 | $10,000 | $10,000 | $10,000 | $10,000 | $10,000 | $10,000 | $10,000 |
| 31 | Seeding, fertilizing, and mulching | ACRE | 2.30 | $10,000 | $8,000.00 | $8,682.00 | $8,000.00 | $9,000.00 | $7,760.00 | $7,500.00 |
| 32 | Medium compost | ACRE | 2.30 | $25,000 | $29,000 | $31,467 | $30,000 | $37,000 | $32,000 | $7,500.00 |
| 33 | High visibility silt fence | LF | 2,020 | $15.00 | $4.00 | $6.80 | $7.50 | $10.00 | $6.00 | $7.50 |
| 34 | Erosion control blanket | SY | 80 | $100.00 | $6.00 | $2.10 | $24.00 | $13.00 | $5.00 | $17.00 |
| 35 | Beam guardrail transition section type 21 | EACH | 2 | $7,500.00 | $6,000.00 | $6,760.00 | $6,500.00 | $7,500.00 | $7,300.00 | $9,000.00 |
| 36 | Beam guardrail transition section type 24 | EACH | 4 | $7,500.00 | $2,200.00 | $2,447.00 | $2,400.00 | $2,700.00 | $2,640.00 | $3,500.00 |
| 37 | Beam guardrail type 31 non-flared terminal | EACH | 2 | $6,000.00 | $4,300.00 | $4,895.00 | $4,800.00 | $5,400.00 | $5,550.00 | $4,300.00 |
| 38 | Precast concrete barrier type F unanchored | LF | 1,530 | $125.00 | $150.00 | $169.00 | $165.00 | $185.00 | $270.00 | $160.00 |
| 39 | Single slope concrete barrier | LF | 240 | $275.00 | $300.00 | $337.00 | $315.00 | $350.00 | $430.00 | $200.00 |
| 40 | Temporary barrier | LF | 480 | $40.00 | $48.00 | $53.60 | $55.00 | $59.00 | $63.00 | $75.00 |
| 41 | High-tension cable barrier system (4 cable) | LF | 1,250 | $45.00 | $86.00 | $97.90 | $96.00 | $58.00 | $54.00 | $55.00 |
| 42 | Additional high-tension cable barrier components | LS | 1 | $10,000 | $45,000 | $52,444 | $50,000 | $58,000 | $12,700 | $14,000 |
| 43 | Temporary impact attenuator | EACH | 4 | $7,500.00 | $4,500.00 | $5,244.00 | $5,000.00 | $5,800.00 | $6,350.00 | $1,000.00 |
| 44 | Resetting impact attenuator | EACH | 1 | $2,500.00 | $2,800.00 | $3,263.00 | $3,500.00 | $3,700.00 | $3,890.00 | $650.00 |
| 45 | Linear delineation panel for concrete barrier | EACH | 54 | $65.00 | $70.00 | $79.30 | $75.00 | $89.00 | $79.00 | $80.00 |
| 46 | Paint line | LF | 5,350 | $0.50 | $0.23 | $1.15 | $1.25 | $1.25 | $1.00 | $2.00 |
| 47 | Shoulder rumble strip type 2 | MI | 0.69 | $25,000 | $25,000 | $13,985 | $16,000 | $17,000 | $10,000 | $14,000 |
| 48 | Temporary pavement marking-short duration | LF | 5,550 | $1.00 | $0.20 | $1.30 | $4.00 | $3.50 | $3.00 | $3.00 |
| 49 | Bridge mounted sign bracket no. 1 | LS | 1 | $21,000 | $22,000 | $26,360 | $35,000 | $38,000 | $57,000 | $37,000 |
| 50 | Bridge mounted sign bracket no. 2 | LS | 1 | $21,000 | $22,000 | $26,360 | $35,000 | $38,000 | $57,000 | $37,000 |
| 51 | Conduit pipe 2 inch diameter | LF | 1,060 | $120.00 | $85.00 | $78.70 | $72.00 | $75.00 | $65.00 | $92.00 |
| 52 | Portable changeable message sign | HR | 144,000 | $1.00 | $0.25 | $0.25 | $0.01 | $2.00 | $2.00 | $0.50 |
| 53 | Project temporary traffic control | LS | 1 | $412,680 | $300,000 | $220,539 | $400,000 | $500,000 | $625,000 | $950,000 |
| 54 | Work zone safety contingency | EST | 1 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 |
| 55 | Construction signs class A | SF | 364 | $75.00 | $33.00 | $28.20 | $30.00 | $50.00 | $36.00 | $60.00 |
| 56 | WSP reimbursement | CALC | 1 | -$1.00 | -$1.00 | -$1.00 | -$1.00 | -$1.00 | -$1.00 | -$1.00 |
| 57 | Project partnering | CALC | 1 | $10,000 | $10,000 | $10,000 | $10,000 | $10,000 | $10,000 | $10,000 |
| 58 | Structure surveying | LS | 1 | $20,000 | $20,000 | $35,913 | $30,000 | $45,000 | $31,400 | $67,000 |
| 59 | Roadway surveying | LS | 1 | $5,000.00 | $20,000 | $22,161 | $20,000 | $25,000 | $19,400 | $57,000 |
| 60 | Roadside cleanup | EST | 1 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 |
| 61 | Reimbursement for third party damage | EST | 1 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 62 | Minor change | CALC | 1 | -$9.00 | -$9.00 | -$9.00 | -$9.00 | -$9.00 | -$9.00 | -$9.00 |
| 63 | Fuel cost adjustment | CALC | 1 | -$9.00 | -$9.00 | -$9.00 | -$9.00 | -$9.00 | -$9.00 | -$9.00 |
| 64 | Steel cost adjustment | CALC | 1 | -$9.00 | -$9.00 | -$9.00 | -$9.00 | -$9.00 | -$9.00 | -$9.00 |
| 65 | Aggregate compliance price adjustment | CALC | 1 | -$9.00 | -$9.00 | -$9.00 | -$9.00 | -$9.00 | -$9.00 | -$9.00 |
| 66 | Spill prevention, control, and countermeasures plan | LS | 1 | $5,000.00 | $2,500.00 | $3,500.00 | $5,000.00 | $1,500.00 | $5,090.00 | $1,200.00 |
| 67 | Construction geotextile for permanent erosion control | SY | 20 | $25.00 | $20.00 | $3.00 | $23.00 | $60.00 | $20.00 | $10.00 |
| 68 | Superstructure - elastomeric bearing pad | EACH | 10 | $2,000.00 | $1,500.00 | $2,086.00 | $2,000.00 | $2,500.00 | $2,940.00 | $1,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WSDOT's tabulation for this contract. WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
Every contract let that day: WSDOT letting of July 1, 2026. Compiled by Mirage Metrics.