Schedule A culvert pipe 12 inch diameter, WSDOT
Low bidders on WSDOT contracts carried a median of $31.00 per LF for this item, from 04 JAN 2001 to 01 FEB 2023, across 78 low bids. Half of all 473 bids fell between $24.00 and $50.00.
- Owner
- Washington State DOT
- Item
- No code published
- Unit
- LF
- Data through
- 07 OCT 2026
WSDOT prints this item as “SCHEDULE A CULV. PIPE 12 IN. DIAM.”.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2001 | 5 | 5 | $14.00 | 23 | $18.00 |
| 2002 | 6 | 6 | $31.75 | 26 | $30.00 |
| 2003 | 2 | 2 | $13.50 | 8 | $14.88 |
| 2004 | 4 | 4 | $18.00 | 14 | $20.00 |
| 2005 | 5 | 5 | $32.00 | 25 | $26.00 |
| 2006 | 4 | 4 | $23.83 | 16 | $25.75 |
| 2007 | 4 | 4 | $30.00 | 24 | $26.00 |
| 2008 | 6 | 6 | $38.50 | 32 | $33.50 |
| 2009 | 6 | 6 | $18.25 | 63 | $25.00 |
| 2010 | 9 | 9 | $34.20 | 62 | $30.00 |
| 2011 | 4 | 4 | $53.00 | 30 | $49.50 |
| 2012 | 3 | 3 | $30.00 | 27 | $40.00 |
| 2013 | 2 | 2 | $35.00 | 15 | $38.00 |
| 2014 | 3 | 3 | $39.20 | 30 | $44.00 |
| 2015 | 1 | 1 | $53.00 | 6 | $54.00 |
| 2016 | 2 | 2 | $52.18 | 8 | $53.50 |
| 2017 | 1 | 1 | $75.00 | 5 | $115.00 |
| 2018 | 4 | 4 | $59.00 | 19 | $40.00 |
| 2019 | 2 | 2 | $117.50 | 11 | $85.00 |
| 2020 | 2 | 2 | $100.00 | 12 | $82.50 |
| 2021 | 2 | 2 | $80.00 | 13 | $49.00 |
| 2023 | 1 | 1 | $89.25 | 4 | $104.62 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| OR region | 17 | $35.05 | 115 | $37.00 |
| SWR region | 14 | $28.00 | 95 | $32.50 |
| SCR region | 11 | $45.00 | 74 | $35.50 |
| NWR region | 12 | $28.85 | 73 | $28.00 |
| NCR region | 16 | $39.25 | 71 | $44.00 |
| ER region | 8 | $28.00 | 45 | $25.00 |
Regions with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 9 to 60 | 19 | $56.00 |
| 60 to 134 | 20 | $40.00 |
| 134 to 398 | 19 | $30.77 |
| 470 to 2,455 | 20 | $18.95 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Wilder Construction Company | 12 | 6 (50%) |
| Tri-State Construction, Inc. | 12 | 4 (33%) |
| Apollo, Inc. | 6 | 4 (67%) |
| Scarsella Bros., Inc. | 25 | 3 (12%) |
| N.A. Degerstrom, Inc. | 8 | 3 (38%) |
| Quigg Bros., Inc. | 13 | 2 (15%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 01 FEB 2023 | 009921 | NCR region | 63 | $89.25 | $104.62 | $60.00 | 4 | Johansen Construction Company, | WSDOT |
| 03 FEB 2021 | 009625 | SCR region | 125 | $45.00 | $42.50 | $70.00 | 8 | Scarsella Bros., Inc. | WSDOT |
| 13 JAN 2021 | 009623 | ER region | 10 | $115.00 | $63.21 | $90.00 | 5 | Max J. Kuney Company | WSDOT |
| 11 MAR 2020 | 009528 | NCR region | 87 | $150.00 | $75.00 | $185.00 | 5 | Coral Construction Company | WSDOT |
| 05 FEB 2020 | 009515 | OR region | 20 | $50.00 | $85.00 | $80.00 | 7 | Northeast Electric, LLC | WSDOT |
| 10 APR 2019 | 009419 | SWR region | 30 | $150.00 | $72.00 | $120.00 | 8 | Farline Bridge, Incorporated | WSDOT |
| 27 MAR 2019 | 009399 | NCR region | 295 | $85.00 | $112.00 | $50.00 | 3 | Strider Construction Co., Inc. | WSDOT |
| 25 APR 2018 | 009258 | ER region | 220 | $31.00 | $35.00 | $35.00 | 2 | CPM Development Corporation | WSDOT |
| 04 APR 2018 | 009238 | SWR region | 71 | $90.00 | $83.00 | $135.00 | 3 | Rognlin'S, Inc. | WSDOT |
| 28 FEB 2018 | 009215 | OR region | 42 | $87.00 | $57.50 | $112.00 | 4 | Interwest Construction, Inc. | WSDOT |
| 07 JAN 2018 | 009197 | SWR region | 263 | $26.00 | $38.90 | $55.00 | 10 | Oregon State Bridge Constructi | WSDOT |
| 15 MAR 2017 | 009040 | NCR region | 36 | $75.00 | $115.00 | $45.00 | 5 | Scarsella Bros., Inc. | WSDOT |
| 02 MAR 2016 | 008843 | SCR region | 60 | $73.59 | $71.80 | $40.00 | 2 | Acme Concrete Paving, Inc. | WSDOT |
| 13 JAN 2016 | 008827 | OR region | 173 | $30.77 | $39.65 | $40.00 | 6 | Port Madison Enterprises | WSDOT |
| 01 APR 2015 | 008715 | SCR region | 21 | $53.00 | $54.00 | $31.00 | 6 | Guy F. Atkinson Construction, | WSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.
How these prices were read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the WSDOT letting of 07 OCT 2026 and was rebuilt on 26 NOV 2026.