Owners, scope and amount

FieldValueSource
Owner or sponsorChesapeake Bay Bridge and Tunnel District
CategoryTunnels
Bored tunnel length5,700 ftFederal Highway Administration, Center for Innovative Finance Support
New southbound lanes2Chesapeake Bay Bridge and Tunnel District
AmountNot collected yet
Threshold evidenceOnly a financed-scope figure meets the threshold; to reconcile
Sourced facts in the research record

Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.

AmountWhat it isScopeAs ofSource
US$756 MContract valueWhole projectUndatedFederal Highway Administration, Center for Innovative Finance SupportDesign-build cost of the Chesapeake Tunnel Joint Venture contract (FHWA profile: 'Design-build cost - $756 million'); the profile gives the total project cost as $1,074 million. The larger bridge-tunnel system is a different asset.
Financial records, each with its kind and scope

Contracts and teams

CompanyRolePackageSource
Chesapeake Tunnel Joint Venture (Dragados USA, Inc. and Schiavone Construction Co. LLC)design-builderParallel Thimble Shoal TunnelFederal Highway Administration, Center for Innovative Finance Support
Delivery parties, each named by the owner, a government or the company itself

In review: consortium rows from the research workbook. They are not published attributions until each one is matched to an award notice.

CompanyConsortiumPackageWorkbook status
Dragados USAChesapeake Tunnel JVDesign-buildTo verify
Schiavone ConstructionChesapeake Tunnel JVDesign-buildTo verify
Workbook consortium rows, not yet published attributions

About the project

A second, two-lane bored tunnel of the Chesapeake Bay Bridge-Tunnel, from #1 Island under Thimble Shoal Channel to #2 Island. The FHWA project profile gives the new bored tunnel's length and planned southbound use.

Scope notes

Sources

  • Parallel Thimble Shoal Tunnel Project, U.S. Department of Transportation. Bored tunnel length and planned traffic. Consulted 9 Nov 2026.
  • Project Profiles: Parallel Thimble Shoal Tunnel, Federal Highway Administration, Center for Innovative Finance Support. 'Design-builder - Chesapeake Tunnel Joint Venture ... Dragados USA, Inc. ... Schiavone Construction Co. LLC - lead contractor ... Design-build cost - $756 million ... Design-build contractor selected July 2016'. Consulted 18 Nov 2026.
  • Parallel Thimble Shoal Tunnel Project, Chesapeake Bay Bridge and Tunnel District. 'The Parallel Thimble Shoal Tunnel project involves the construction of a two-lane bored tunnel from the CBBT's southernmost island (#1 Island) under Thimble Shoal Channel to #2 Island. When complete, the new tunnel will carry two lanes of traffic southbound and the existing tunnel will carry two lanes of traffic northbound.'. Consulted 19 Nov 2026.

See it on the map. How the atlas qualifies a record.