Under construction, as of March 2026 (Diario de Avisos). Tunnel excavation finished in November 2024; in March 2026 the Cabildo-area press reported opening scheduled for the first quarter of 2027.
Status
Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
Research as of

Who, what, how much

FieldValueSource
OwnerGobierno de Canarias, Consejería de Obras Públicas, Vivienda y Movilidad
TypeHighways
Headline amountEUR 21.5 million (EUR), as of January 15, 2026Gobierno de Canarias
What it coversBudget.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

FieldValueScopeSource
Length11.3 kmnew road, about half in tunnelDiario de Avisos
Tunnel length5,095 meach of two tubesDiario de Avisos
Tunnel mined length4,855 mmined excavation, cut-and-cover at both portalsDiario de Avisos
Cross passages19 galleriesevery 250 mDiario de Avisos
Lanes1 lane per directionper the January 2026 reportDiario de Avisos
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

AmountWhat it isScopeAs ofSource
€240 MContract valueaward (IGIC treatment not stated)September 2019Tenerife Weekly
€263 MBudgetcurrent cost after price revisionsNovember 2024Diario de Avisos
€21 MBudgetModification No.2, incl. IGIC (8.9% on current budget), definitively approved January 2026January 15, 2026Gobierno de Canarias
Amounts, each with its kind and scope

Companies and their roles

CompanyRoleNoteSource
Gobierno de Canarias, Consejería de Obras Públicas, Vivienda y MovilidadOwnerDiario de Avisos
FCC Construcción, Syocsa-Inarsa and El Silbo (UTE)General contractorShares not statedDiario de Avisos
Companies and public bodies named by a source, each with its role

Milestones

DateMilestoneSource
September 2019Works awardedTenerife Weekly
November 2019Works beginDiario de Avisos
November 12, 2019Works contract signed (48 months)Gobierno de Canarias
November 2024Erjos tunnel excavation completeDiario de Avisos
January 14, 2026Modification No.2 approved (EUR 21.488M)Gobierno de Canarias
March 2027 (planned)Opening, first quarter 2027Diario de Avisos
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

The Government of the Canary Islands is closing Tenerife's island ring road with 11.3 km of new road between El Tanque and Santiago del Teide, about half of it in the twin-tube Erjos tunnel, 5,095 m per tube, the longest road tunnel in the Canaries. FCC Construcción, Syocsa-Inarsa and El Silbo won the contract in 2019 for EUR 240.4 million and started in November 2019. Excavation finished in November 2024; opening is expected in the first quarter of 2027.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.

Sources

See it on the map. How the map is made.