Reviewed record
Tenerife island ring road closure: El Tanque to Santiago del Teide (Erjos tunnel)
- Location
- El Tanque, Erjos and Santiago del Teide, Tenerife, Canary Islands, Spain. See it on the map, in 3D
- Stage
- Under construction, as of March 2026 (Diario de Avisos). Tunnel excavation finished in November 2024; in March 2026 the Cabildo-area press reported opening scheduled for the first quarter of 2027.
- Status
- Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owner | Gobierno de Canarias, Consejería de Obras Públicas, Vivienda y Movilidad | |
| Type | Highways | |
| Headline amount | EUR 21.5 million (EUR), as of January 15, 2026 | Gobierno de Canarias |
| What it covers | Budget. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Length | 11.3 km | new road, about half in tunnel | Diario de Avisos |
| Tunnel length | 5,095 m | each of two tubes | Diario de Avisos |
| Tunnel mined length | 4,855 m | mined excavation, cut-and-cover at both portals | Diario de Avisos |
| Cross passages | 19 galleries | every 250 m | Diario de Avisos |
| Lanes | 1 lane per direction | per the January 2026 report | Diario de Avisos |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| €240 M | Contract value | award (IGIC treatment not stated) | September 2019 | Tenerife Weekly |
| €263 M | Budget | current cost after price revisions | November 2024 | Diario de Avisos |
| €21 M | Budget | Modification No.2, incl. IGIC (8.9% on current budget), definitively approved January 2026 | January 15, 2026 | Gobierno de Canarias |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Gobierno de Canarias, Consejería de Obras Públicas, Vivienda y Movilidad | Owner | Diario de Avisos | |
| FCC Construcción, Syocsa-Inarsa and El Silbo (UTE) | General contractor | Shares not stated | Diario de Avisos |
Milestones
| Date | Milestone | Source |
|---|---|---|
| September 2019 | Works awarded | Tenerife Weekly |
| November 2019 | Works begin | Diario de Avisos |
| November 12, 2019 | Works contract signed (48 months) | Gobierno de Canarias |
| November 2024 | Erjos tunnel excavation complete | Diario de Avisos |
| January 14, 2026 | Modification No.2 approved (EUR 21.488M) | Gobierno de Canarias |
| March 2027 (planned) | Opening, first quarter 2027 | Diario de Avisos |
About the project
The Government of the Canary Islands is closing Tenerife's island ring road with 11.3 km of new road between El Tanque and Santiago del Teide, about half of it in the twin-tube Erjos tunnel, 5,095 m per tube, the longest road tunnel in the Canaries. FCC Construcción, Syocsa-Inarsa and El Silbo won the contract in 2019 for EUR 240.4 million and started in November 2019. Excavation finished in November 2024; opening is expected in the first quarter of 2027.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Anillo Insular de Tenerife: aprobada la modificación nº 2, Diario de Avisos (press), 15 Jan 2026. Consulted 26 Nov 2026.
- Concluye en Erjos la excavación del mayor túnel de Canarias, Diario de Avisos (press), Nov 2024. Consulted 26 Nov 2026.
- El Anillo Insular: el mayor proyecto vial de la Isla, accidentes mortales y un corredor que se quedó corto, Diario de Avisos (press), Mar 2026. Consulted 26 Nov 2026.
- Tenerife island ring project (Anillo Insular), Tenerife Weekly (press), 9 Apr 2024. Consulted 26 Nov 2026.
- Obras Públicas firma el contrato para la ejecución de las obras del cierre del Anillo Insular de Tenerife, Gobierno de Canarias (government), 12 Nov 2019. Consulted 27 Nov 2026.
- El Ejecutivo aprueba técnicamente el modificado2 del cierre del Anillo Insular entre El Tanque y Santiago del Teide, Gobierno de Canarias (government), 8 Sep 2025. Consulted 27 Nov 2026.
- El Ejecutivo aprueba definitivamente el modificado 2 del cierre del Anillo Insular de Tenerife, Gobierno de Canarias (government), 14 Jan 2026. Consulted 27 Nov 2026.
- El TSJC convalida el acuerdo entre la Consejería y OHL para cumplir la sentencia del Anillo Insular de Tenerife, Gobierno de Canarias (government), 2 Dec 2024. Consulted 27 Nov 2026.