ARDOT contract 020802 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO IMPROVE THE INTERSECTION AT HIGHWAYS 15 AND 31 WITH CHANNELIZATION IN JEFFERSON COUNTY. THIS PROJECT CONSISTS OF CLEARING AND GRUBBING, REMOVAL AND DISPOSAL ITEMS, FLOWABLE SELECT MATERIAL, EARTHWORK, AGGREGATE BASE COURSE, ACHM BINDER AND SURFACE COURSES, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, MAINTENANCE OF TRAFFIC, MINOR DRAINAGE, EROSION CONTROL, PAVEMENT MARKING, AND MISC. ITEMS. Let by Arkansas DOT on May 20, 2026, Jefferson. 5 bids received; low bid $1,159,310 by 1911 Construction Company, Inc..
- Owner
- Arkansas DOT
- Letting
- 20 MAY 2026
- Pay items
- 52
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | 1911 Construction Company, Inc. | $1,159,310 | Low |
| 2 | D & D Paving, Inc. | $1,374,372 | +19% |
| 3 | Mobley Contractors, Inc. | $1,446,009 | +25% |
| 4 | Central Arkansas Contractors, Inc. | $1,681,906 | +45% |
| 5 | Redstone Construction Group, Inc. | $2,055,243 | +77% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. 1911 Construction Company, Inc. | 2. D & D Paving, Inc. | 3. Mobley Contractors, Inc. | 4. Central Arkansas Contractors, Inc. | 5. Redstone Construction Group, Inc. |
|---|---|---|---|---|---|---|---|---|
| 0001 | Clearing (201011) | STA | 4 | $850.00 | $3,150.00 | $2,425.85 | $3,000.00 | $2,228.50 |
| 0002 | Grubbing (201111) | STA | 4 | $750.00 | $1,800.00 | $2,425.85 | $3,000.00 | $4,530.35 |
| 0003 | Removal and disposal of concrete islands (202047) | SY | 44 | $40.00 | $45.00 | $80.39 | $42.00 | $53.30 |
| 0004 | Removal and disposal of pipe culverts (202096) | EACH | 4 | $500.00 | $840.00 | $1,679.29 | $1,500.00 | $1,850.18 |
| 0005 | Removal and disposal of box culverts (202097) | EACH | 1 | $3,500.00 | $6,400.00 | $17,302 | $10,000 | $14,830 |
| 0006 | Removal and disposal of mailboxes (202200) | EACH | 1 | $25.00 | $50.00 | $209.37 | $250.00 | $322.04 |
| 0007 | Flowable select material (206021) | CY | 28 | $175.00 | $480.00 | $568.55 | $572.00 | $361.45 |
| 0008 | Unclassified excavation (210213) | CY | 1,270 | $15.00 | $12.50 | $35.07 | $25.00 | $81.25 |
| 0009 | Compacted embankment (210611) | CY | 7,254 | $20.00 | $35.00 | $31.60 | $33.00 | $71.85 |
| 0010 | Soil stabilization (210702) | TON | 75 | $100.00 | $735.00 | $262.50 | $400.00 | $529.55 |
| 0011 | Aggregate base course (class 7) (303117) | TON | 5,176 | $40.00 | $51.00 | $52.19 | $62.50 | $54.75 |
| 0012 | Tack coat (401011) | GAL | 818 | $6.25 | $5.75 | $1.05 | $6.00 | $6.00 |
| 0013 | Mineral aggregate in achm binder course (1") (406161) | TON | 364 | $159.00 | $142.25 | $99.75 | $190.00 | $285.00 |
| 0014 | Asphalt binder (PG 64-22) in achm binder course (1") (minimum bid $120.00) (406402) | TON | 19 | $195.00 | $174.00 | $892.50 | $250.00 | $120.00 |
| 0015 | Mineral aggregate in achm surface course (1/2") (407162) | TON | 1,792 | $115.00 | $101.80 | $99.75 | $190.00 | $216.00 |
| 0016 | Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432) | TON | 94 | $1,095.00 | $977.00 | $892.50 | $275.00 | $120.00 |
| 0017 | Cold milling asphalt pavement (412002) | SY | 744 | $45.00 | $27.00 | $12.60 | $35.55 | $15.00 |
| 0018 | Achm patching of existing roadway (415011) | TON | 8 | $448.00 | $250.00 | $1,050.00 | $350.00 | $310.00 |
| 0019 | Maintenance of traffic (603009) | LS | 1 | $38,000 | $46,500 | $134,690 | $45,000 | $119,500 |
| 0020 | Signs (604003) | SF | 392 | $16.80 | $14.60 | $15.75 | $15.50 | $5.78 |
| 0021 | Barricades (604013) | LF | 64 | $28.00 | $22.00 | $26.25 | $75.00 | $24.15 |
| 0022 | Traffic drums (604023) | EACH | 52 | $56.00 | $46.00 | $52.50 | $85.00 | $24.15 |
| 0023 | Furnishing and installing precast concrete barrier (604031) | LF | 519 | $47.60 | $72.00 | $54.60 | $120.00 | $42.50 |
| 0024 | Construction pavement markings (604041) | LF | 23,169 | $1.12 | $0.33 | $1.05 | $1.50 | $0.34 |
| 0025 | Vertical panels (604083) | EACH | 52 | $67.20 | $62.00 | $63.00 | $100.00 | $35.00 |
| 0026 | 18" side drain (606703) | LF | 68 | $105.00 | $145.00 | $101.75 | $120.00 | $214.00 |
| 0027 | Lime (620001) | TON | 4 | $112.00 | $110.00 | $105.00 | $250.00 | $110.00 |
| 0028 | Seeding (620011) | ACRE | 2.07 | $1,625.00 | $1,600.00 | $1,522.50 | $2,000.00 | $1,595.00 |
| 0029 | Mulch cover (620022) | ACRE | 4.14 | $1,120.00 | $1,100.00 | $1,050.00 | $1,500.00 | $1,100.00 |
| 0030 | Water (620030) | MGAL | 254.10 | $10.00 | $10.00 | $10.50 | $13.00 | $10.00 |
| 0031 | Temporary seeding (621001) | ACRE | 2.07 | $896.00 | $880.00 | $840.00 | $1,200.00 | $800.00 |
| 0032 | Silt fence (621021) | LF | 2,620 | $3.65 | $3.50 | $3.41 | $7.00 | $3.58 |
| 0033 | Sediment removal and disposal (621111) | CY | 120 | $6.00 | $65.00 | $21.36 | $15.00 | $20.00 |
| 0034 | Rock ditch checks (621151) | CY | 69 | $125.00 | $115.00 | $76.51 | $150.00 | $140.00 |
| 0035 | Second seeding application (623001) | ACRE | 2.07 | $335.00 | $325.00 | $315.00 | $1,200.00 | $300.00 |
| 0036 | Solid sodding (624001) | SY | 65 | $13.45 | $15.00 | $12.60 | $20.00 | $13.20 |
| 0037 | Roadway construction control (635001) | LS | 1 | $35,000 | $72,500 | $39,058 | $35,000 | $36,750 |
| 0038 | Reflectorized paint pavement marking white (6") (718002) | LF | 3,420 | $2.18 | $1.16 | $2.05 | $4.00 | $1.26 |
| 0039 | Reflectorized paint pavement marking white (12") (718005) | LF | 55 | $11.20 | $22.00 | $10.50 | $20.00 | $23.10 |
| 0040 | Reflectorized paint pavement marking yellow (6") (718102) | LF | 4,046 | $2.18 | $1.16 | $2.05 | $1.50 | $1.26 |
| 0041 | Reflectorized paint pavement marking yellow (12") (718105) | LF | 232 | $11.20 | $22.00 | $10.50 | $5.00 | $23.10 |
| 0042 | Raised pavement markers (type II) (721002) | EACH | 26 | $112.00 | $25.00 | $105.00 | $120.00 | $26.40 |
| 0043 | Temporary impact attenuation barrier (731071) | EACH | 1 | $8,960.00 | $7,500.00 | $12,509 | $10,500 | $16,370 |
| 0044 | Temporary impact attenuation barrier (repair) (731072) | EACH | 1 | $560.00 | $1,000.00 | $525.00 | $2,500.00 | $550.00 |
| 0045 | Unclassified excavation for structures-roadway (801101) | CY | 45 | $175.00 | $150.00 | $55.38 | $250.00 | $255.00 |
| 0046 | Class S concrete-roadway (802012) | CY | 19.90 | $1,500.00 | $1,600.00 | $3,219.81 | $4,500.00 | $4,025.00 |
| 0047 | Reinforcing steel-roadway (grade 60) (804003) | LB | 1,965 | $2.50 | $2.60 | $5.63 | $4.50 | $3.35 |
| 0048 | 24" reinforced concrete pipe culverts (class III) (605606) | LF | 122 | $135.00 | $115.00 | $117.47 | $145.00 | $123.00 |
| 0055 | 36" reinforced concrete pipe culverts (class IV) (605618) | LF | 72 | $245.00 | $220.00 | $217.84 | $225.00 | $300.00 |
| 0062 | 24" flared end sections for reinforced concrete pipe culverts (605858) | EACH | 2 | $1,760.00 | $2,600.00 | $3,565.53 | $2,000.00 | $4,305.00 |
| 0064 | 36" flared end sections for reinforced concrete pipe culverts (605862) | EACH | 2 | $3,100.00 | $2,800.00 | $4,547.33 | $3,500.00 | $5,115.00 |
| 0066 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $52,000 | $50,000 | $49,063 | $75,000 | $92,500 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of May 20, 2026. Compiled by Mirage Metrics.