Cobb Site Development, Inc: FDOT bid record
Cobb Site Development, Inc submitted 18 bids on Florida DOT contracts in the data, from 13 JUN 2018 to 27 APR 2022, and was the low bidder on 3 of them (17%). When it was not low, its total sat a median +9.0% above the low bid.
- Owner
- Florida DOT
- Low bid volume
- $3,829,427
- Latest bid
- 27 APR 2022
- Data through
- 28 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2018 | 3 | 0 | 0% |
| 2019 | 3 | 0 | 0% |
| 2020 | 2 | 0 | 0% |
| 2021 | 7 | 3 | 43% |
| 2022 | 3 | 0 | 0% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| District 1 | 17 | 3 | 18% |
| District 7 | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Removal of existing concrete | 0110-4-10 | SY | 12 | 5 (42%) | $17.94 | $33.96 |
| Pipe culvert,optional material,round, 18"S/CD | 0430-175118 | LF | 9 | 5 (56%) | $58.78 | $154.00 |
| Concrete sidewalk and driveways, 6" thick | 0522-2 | SY | 12 | 4 (33%) | $54.67 | $86.00 |
| Conduit, furnish & install, open trench | 0630-2-11 | LF | 22 | 3 (14%) | $13.79 | $16.54 |
| Single post sign, remove | 0700-1-60 | AS | 12 | 3 (25%) | $39.32 | $31.94 |
| Concrete curb & gutter, type E | 0520-1-7 | LF | 9 | 3 (33%) | $21.61 | $43.11 |
| Optional base, base group 01 | 0285-701 | SY | 8 | 3 (38%) | $17.81 | $24.00 |
| Pipe culvert, opt material, round, 30"S/CD | 0430-175130 | LF | 7 | 3 (43%) | $285.08 | $224.50 |
| Turnout base- optional materials | 0286-1 | SY | 7 | 3 (43%) | $32.69 | $41.74 |
| Inlets, DT bot, type D, <10' | 0425-1541 | EACH | 6 | 3 (50%) | $3,920.48 | $6,300.00 |
| Conduit, furnish & install, directional bore | 0630-2-12 | LF | 18 | 2 (11%) | $35.66 | $30.82 |
| Regular excavation | 0120-1 | CY | 13 | 2 (15%) | $10.08 | $25.47 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Ajax Paving Industries of Florida LLC | 11 | 4 of 11 |
| Gosalia Concrete Constructors, Inc. | 6 | 1 of 6 |
| C.W. Roberts Contracting, Inc. | 6 | 1 of 6 |
| Russell Engineering, Inc. | 5 | 2 of 5 |
| Watson Civil Construction, Inc. | 5 | 2 of 5 |
| V & H Construction, Inc. | 3 | 3 of 3 |
| Blacktip Services Incorporated | 3 | 1 of 3 |
| Wright Construction Group, Inc. | 3 | 2 of 3 |
| The Stout Group LLC | 2 | 0 of 2 |
| Ohl USA Inc | 2 | 0 of 2 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 27 APR 2022 | T1787 | District 1 | SR 45 (US BUS 41) | 4 of 4 | $7,009,334 | +14% |
| 23 FEB 2022 | T1844 | District 1 | SR 555 (US 17) | 2 of 6 | $10,061,294 | +7.0% |
| 26 JAN 2022 | T1811 | District 1 | SR 555 (US 17) | 3 of 5 | $3,160,845 | +15% |
| 27 OCT 2021 | T1808 | District 1 | SR 600 (US 17-92) | 1 of 6 | $1,139,701 | Low, 20% under the second |
| 25 AUG 2021 | T1771 | District 1 | EDGEWOOD DR N | 2 of 6 | $935,383 | +6.0% |
| 25 AUG 2021 | T1824 | District 1 | SR 700 (US 98) | 1 of 5 | $889,742 | Low, 13% under the second |
| 25 AUG 2021 | T1825 | District 1 | SR 25 AND SR 70 | 2 of 5 | $8,281,065 | 0.0% |
| 28 JUL 2021 | T1799 | District 1 | SR 25 (US 27) | 1 of 3 | $1,799,984 | Low, 4.0% under the second |
| 09 JUN 2021 | T1761 | District 1 | SR 80 | 4 of 6 | $4,426,768 | +8.0% |
| 27 JAN 2021 | T1794 | District 1 | SR 37 | 2 of 5 | $3,078,604 | +4.0% |
| 18 NOV 2020 | T7449 | District 7 | MORRIS BRIDGE - BIKE PATH/TRAIL | 7 of 12 | $4,970,623 | +11% |
| 29 JUL 2020 | T1789 | District 1 | SR 45 (US 41) | 4 of 5 | $2,650,135 | +12% |
| 25 SEP 2019 | T1756 | District 1 | BONITA SPRINGS ELEMENTARY (SRTS) SIDEWALK | 2 of 5 | $1,131,335 | +9.0% |
| 25 SEP 2019 | T1766 | District 1 | WEST HICKORY ST | 2 of 6 | $334,271 | +10% |
| 27 FEB 2019 | T1743 | District 1 | NORTH HICKORY ST | 2 of 3 | $196,223 | +42% |
| 26 SEP 2018 | T1735 | District 1 | SR 45 (US 41) | 3 of 5 | $441,320 | +8.0% |
| 13 JUN 2018 | T1715 | District 1 | SR 700 | 2 of 2 | $1,045,982 | +3.0% |
| 13 JUN 2018 | T1726 | District 1 | MARINER MIDDLE SCHOOL | 4 of 5 | $297,255 | +17% |
How this record was read
FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
- Every bid counted here matched its published total to within one dollar; FDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.