FDOT contract T2A25 bid tabulation
SR A1A FROM GATE 5 NAVAL STATION MAYPORT TO S OF US COAST... Let by Florida DOT on June 11, 2025, Duval, District 2. 5 bids received; low bid $1,482,455 by Coxwell, J.B. Contracting, Inc..
- Owner
- Florida DOT
- Letting
- 11 JUN 2025
- Pay items
- 42
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Coxwell, J.B. Contracting, Inc. | $1,482,455 | Low |
| 2 | Vecellio & Grogan, Inc. | $1,529,811 | +3.0% |
| 3 | Maer Homes, LLC | $1,659,113 | +12% |
| 4 | Superior Construction Company Southeast, LLC | $1,779,332 | +20% |
| 5 | Janus Construction Corp. | $2,223,222 | +50% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Coxwell, J.B. Contracting, Inc. | 2. Vecellio & Grogan, Inc. | 3. Maer Homes, LLC | 4. Superior Construction Company Southeast, LLC | 5. Janus Construction Corp. |
|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $302,000 | $140,000 | $157,641 | $175,000 | $231,933 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $47,800 | $65,000 | $105,000 | $100,000 | $356,388 |
| 0015 | Work zone sign (0102-60) | ED | 1,590 | $0.27 | $0.35 | $1.00 | $0.50 | $0.30 |
| 0017 | Temporary barrier, F&I, low profile, concrete (0102-71-13) | LF | 663 | $52.00 | $60.00 | $75.00 | $40.00 | $45.00 |
| 0020 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 9,314 | $0.16 | $0.25 | $0.65 | $0.25 | $0.20 |
| 0025 | Portable changeable message sign, temporary (0102-99) | ED | 536 | $10.82 | $13.25 | $15.00 | $25.00 | $11.50 |
| 0026 | Temporary traffic signals for lane closures on way roadways (0102-120) | ED | 180 | $205.00 | $95.00 | $200.00 | $125.00 | $220.00 |
| 0027 | Removable tape, white, solid 6" (0102-913-21) | GM | 0.22 | $28,500 | $26,000 | $30,000 | $20,000 | $23,000 |
| 0028 | Removable tape, white, 10'-30', 6'-10', or 2'-4' skip, 6" wide (0102-913-22) | GM | 0.02 | $14,300 | $13,500 | $15,000 | $10,000 | $11,500 |
| 0029 | Removable tape, white, 24" stop bar (0102-913-23) | LF | 75 | $43.00 | $41.00 | $40.00 | $30.00 | $34.50 |
| 0030 | Sediment barrier (0104-10-3) | LF | 174 | $14.50 | $12.00 | $7.00 | $20.00 | $8.65 |
| 0031 | Removable tape, white, symbol or arrow (0102-913-29) | EACH | 2 | $1,425.00 | $1,350.00 | $1,500.00 | $1,000.00 | $1,150.00 |
| 0032 | Removable tape, yellow, solid, (0102-913-31) | GM | 0.07 | $28,460 | $29,100 | $30,000 | $20,000 | $23,000 |
| 0035 | Staked turbidity barrier- nylon reinforced PVC (0104-12) | LF | 338 | $19.00 | $70.00 | $32.00 | $25.00 | $10.35 |
| 0040 | Soil tracking prevention device (0104-15) | EACH | 1 | $4,850.00 | $5,000.00 | $12,500 | $8,000.00 | $2,500.00 |
| 0045 | Litter removal (0107-1) | ACRE | 2.02 | $3,390.00 | $1,000.00 | $1,500.00 | $2,500.00 | $575.00 |
| 0050 | Mowing (0107-2) | ACRE | 0.92 | $3,390.00 | $250.00 | $1,500.00 | $3,600.00 | $1,250.00 |
| 0055 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $6,800.00 | $45,000 | $130,000 | $223,386 | $217,250 |
| 0060 | Regular excavation (0120-1) | CY | 260.30 | $41.00 | $120.00 | $65.00 | $95.00 | $128.25 |
| 0065 | Borrow excavation, truck measure (0120-2-2) | CY | 16.30 | $86.00 | $375.00 | $100.00 | $285.00 | $402.50 |
| 0070 | Type B stabilization (0160-4) | SY | 317 | $19.10 | $110.00 | $75.00 | $65.00 | $55.00 |
| 0075 | Optional base, base group 04 (0285-704) | SY | 496 | $82.43 | $90.00 | $115.00 | $50.00 | $52.00 |
| 0080 | Superpave asphaltic concrete, traffic C, PG76-22 (0334-1-53) | TN | 16.50 | $819.00 | $890.00 | $850.00 | $720.00 | $820.00 |
| 0085 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 40.90 | $436.00 | $475.00 | $950.00 | $400.00 | $448.50 |
| 0090 | Conc class IV, bulkhead (0400-4-8) | CY | 33.30 | $3,225.00 | $2,000.00 | $2,700.00 | $3,000.00 | $2,915.00 |
| 0095 | Fiber reinforced polymer bars, #5 bar (0415-10-5) | LF | 2,903 | $5.80 | $5.75 | $9.00 | $7.25 | $6.60 |
| 0100 | Pipe culvert,optional material,round, 24"S/CD (0430-175124) | LF | 10 | $815.00 | $2,000.00 | $1,200.00 | $8,000.00 | $1,610.00 |
| 0105 | Sheet piling steel, F&I (0455-133-3) | SF | 7,114 | $86.50 | $95.00 | $88.00 | $100.00 | $119.00 |
| 0110 | Riprap- rubble, bank and shore (0530-3-3) | TN | 215.50 | $194.00 | $250.00 | $320.00 | $120.00 | $277.15 |
| 0115 | Bedding stone (0530-74) | TN | 50.80 | $176.00 | $500.00 | $265.00 | $380.00 | $277.15 |
| 0120 | Guardrail -roadway, general (0536-1-1) | LF | 475 | $28.35 | $27.00 | $40.00 | $27.00 | $46.00 |
| 0125 | Special guardrail post- frangible leave-out for mounting through shoulder pavement, square or round (0536-7101) | EACH | 77 | $51.00 | $475.00 | $65.00 | $175.00 | $339.25 |
| 0130 | Guardrail end treatment- parallel approach terminal (0536-85-24) | EACH | 2 | $3,600.00 | $4,600.00 | $4,500.00 | $3,425.00 | $4,600.00 |
| 0133 | Raised pavement marker, type B (0706-1-3) | EACH | 4 | $10.00 | $27.00 | $55.00 | $20.00 | $23.00 |
| 0140 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 |
| 0145 | Single column ground sign assembly, relocate (0700-1500) | EACH | 2 | $305.00 | $1,500.00 | $500.00 | $290.00 | $1,750.00 |
| 0146 | Raised pavement marker, type B (0706-1-3) | EACH | 63 | $10.00 | $27.00 | $55.00 | $20.00 | $23.00 |
| 0150 | Painted pavement markings, surface (0710-90) | LS | 1 | $14,230 | $13,750 | $13,000 | $10,000 | $11,500 |
| 0152 | Thermoplastic, standard, arrow (0711-11170) | EACH | 2 | $145.00 | $137.00 | $150.00 | $43.00 | $1,150.00 |
| 0155 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 0.39 | $19,000 | $18,500 | $22,000 | $15,000 | $17,250 |
| 0156 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 0.34 | $21,215 | $23,000 | $25,000 | $15,000 | $17,250 |
| 0157 | Thermoplastic, remove existing thermoplastic pavement markings- surface to remain (0711-17-1) | SF | 2,055 | $7.10 | $7.00 | $7.00 | $5.00 | $5.75 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of June 11, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.