FDOT contract T2A49 bid tabulation
SR 228 (NORMANDY BLVD) FROM S OF MEMORIAL PARK RD TO SR... Let by Florida DOT on January 28, 2026, Duval, District 2. 5 bids received; low bid $2,497,014 by Preferred Materials Inc..
- Owner
- Florida DOT
- Letting
- 28 JAN 2026
- Pay items
- 73
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Preferred Materials Inc. | $2,497,014 | Low |
| 2 | Duval Asphalt Products, Inc. | $2,725,137 | +9.0% |
| 3 | Hubbard Construction Company | $2,915,281 | +17% |
| 4 | Reeves Construction Company | $2,945,910 | +18% |
| 5 | Anderson Columbia Co., Inc. | $3,291,442 | +32% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Preferred Materials Inc. | 2. Duval Asphalt Products, Inc. | 3. Hubbard Construction Company | 4. Reeves Construction Company | 5. Anderson Columbia Co., Inc. |
|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $107,631 | $250,000 | $189,398 | $354,000 | $335,397 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $145,050 | $190,000 | $369,076 | $81,820 | $220,131 |
| 0015 | Pedestrian or bicycle special detour (0102-4-1) | SY | 1 | $4,048.74 | $1,000.00 | $2,700.24 | $1,610.00 | $3,814.90 |
| 0020 | Traffic control officer (0102-14) | HR | 64 | $100.00 | $110.00 | $93.16 | $95.00 | $152.59 |
| 0025 | Work zone sign (0102-60) | ED | 6,170 | $0.21 | $0.25 | $0.27 | $0.40 | $0.32 |
| 0030 | Business sign (0102-61) | EACH | 38 | $23.00 | $15.00 | $32.40 | $23.00 | $35.10 |
| 0035 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 14,602 | $0.10 | $0.15 | $0.13 | $0.10 | $0.15 |
| 0040 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 9,408 | $0.05 | $0.25 | $0.05 | $0.05 | $0.08 |
| 0045 | Arrow board / advance warning arrow panel (0102-76) | ED | 154 | $5.00 | $6.00 | $5.40 | $5.00 | $7.63 |
| 0050 | Portable changeable message sign, temporary (0102-99) | ED | 628 | $11.00 | $12.50 | $10.80 | $11.00 | $16.79 |
| 0055 | Temporary signalization and maintenance, intersection (0102-104) | ED | 240 | $7.45 | $25.00 | $8.17 | $7.50 | $11.37 |
| 0060 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 240 | $17.39 | $20.00 | $19.07 | $17.50 | $26.54 |
| 0065 | Sediment barrier (0104-10-3) | LF | 956 | $1.84 | $1.50 | $1.06 | $1.00 | $21.64 |
| 0070 | Inlet protection system (0104-18) | EACH | 39 | $125.00 | $175.00 | $108.01 | $105.00 | $305.19 |
| 0075 | Litter removal (0107-1) | ACRE | 18.93 | $179.70 | $250.00 | $216.02 | $150.00 | $228.89 |
| 0080 | Mowing (0107-2) | ACRE | 13.95 | $240.00 | $250.00 | $226.82 | $390.00 | $381.49 |
| 0085 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $12,175 | $25,000 | $7,276.43 | $6,400.00 | $18,496 |
| 0090 | Removal of existing concrete (0110-4-10) | SY | 42 | $65.00 | $95.00 | $73.90 | $71.90 | $176.15 |
| 0095 | Milling existing asphalt pavement, 3 1/2" avg depth (0327-70-2) | SY | 34,838 | $2.74 | $2.00 | $4.25 | $5.00 | $4.47 |
| 0100 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 13,876 | $3.06 | $3.00 | $7.87 | $4.10 | $2.91 |
| 0105 | Superpave asphaltic concrete, traffic C, PG76-22 (0334-1-53) | TN | 3,832.30 | $170.66 | $170.00 | $158.86 | $197.00 | $191.72 |
| 0110 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 4,018.80 | $190.45 | $175.00 | $177.43 | $220.00 | $182.28 |
| 0115 | Manhole, adjust (0425-5) | EACH | 7 | $1,535.54 | $2,000.00 | $2,961.32 | $1,425.00 | $2,288.93 |
| 0120 | Manhole, adjust, utilities (0425-5-1) | EACH | 3 | $1,577.30 | $2,000.00 | $2,961.31 | $1,425.00 | $2,288.93 |
| 0125 | Pipe liner, cured in place, 18" (0431-1118) | LF | 192 | $125.00 | $180.00 | $158.96 | $160.00 | $267.04 |
| 0130 | Pipe liner, cured in place, 24" (0431-1124) | LF | 583 | $155.00 | $215.00 | $194.17 | $195.00 | $305.19 |
| 0135 | Pipe liner, cured in place, 30" (0431-1130) | LF | 155 | $240.00 | $275.00 | $297.08 | $275.00 | $404.37 |
| 0140 | Concrete curb & gutter, type F (0520-1-10) | LF | 12 | $67.50 | $250.00 | $76.74 | $74.50 | $610.38 |
| 0145 | Valley gutter- concrete (0520-3) | LF | 21 | $67.50 | $265.00 | $76.74 | $74.50 | $610.38 |
| 0150 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 43 | $125.00 | $100.00 | $142.12 | $135.00 | $381.48 |
| 0155 | Detectable warnings (0527-2) | SF | 202 | $35.50 | $45.00 | $40.36 | $39.00 | $53.41 |
| 0160 | Performance turf, sod (0570-1-2) | SY | 11 | $215.28 | $150.00 | $325.39 | $27.00 | $137.33 |
| 0165 | Raised pavement marker, type B (0706-1-3) | EACH | 1,022 | $5.00 | $6.00 | $5.49 | $5.25 | $8.24 |
| 0170 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 2.67 | $1,600.00 | $1,400.00 | $1,755.87 | $1,430.00 | $2,746.72 |
| 0175 | Painted pavement markings, standard, white, solid for interchange and urban island, (0710-11102) | GM | 0.06 | $11,000 | $1,700.00 | $1,765.71 | $1,890.00 | $18,312 |
| 0180 | Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123) | LF | 1,458 | $1.75 | $2.25 | $2.20 | $2.20 | $3.05 |
| 0185 | Painted pavement markings, standard, white, solid for diagonal or chevron, 18" (0710-11124) | LF | 2,224 | $2.25 | $2.75 | $3.30 | $2.70 | $3.89 |
| 0190 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 309 | $3.00 | $3.25 | $4.39 | $3.30 | $4.43 |
| 0195 | Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131) | GM | 1.97 | $405.00 | $900.00 | $1,096.98 | $930.00 | $698.89 |
| 0200 | Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141) | GM | 0.39 | $775.00 | $900.00 | $1,081.58 | $940.00 | $1,213.14 |
| 0205 | Painted pavement markings, standard, white, message or symbol (0710-11160) | EACH | 3 | $95.00 | $105.00 | $93.39 | $110.00 | $163.28 |
| 0210 | Painted pavement markings, standard, white, arrows (0710-11170) | EACH | 51 | $50.00 | $55.00 | $49.44 | $55.00 | $80.87 |
| 0215 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 1.96 | $1,600.00 | $1,400.00 | $1,756.95 | $1,430.00 | $2,746.72 |
| 0220 | Painted pavement markings, standard, yellow, solid for diagonal or chevron, 18" (0710-11224) | LF | 41 | $2.25 | $2.75 | $3.30 | $2.70 | $3.66 |
| 0225 | Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241) | GM | 0.30 | $705.00 | $900.00 | $1,094.98 | $930.00 | $1,216.19 |
| 0230 | Two component polyurethane injection (0906-173200) | LB | 16,960 | $11.75 | $12.50 | $11.51 | $6.70 | $13.66 |
| 0235 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 |
| 0240 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 2 | $450.00 | $500.00 | $510.35 | $450.00 | $991.87 |
| 0245 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 4 | $2,400.00 | $2,750.00 | $2,721.84 | $2,400.00 | $3,586.00 |
| 0250 | Sign panel, install, UP to 12 SF (0700-3401) | EACH | 2 | $300.00 | $350.00 | $340.23 | $300.00 | $152.59 |
| 0255 | Sign panel, remove, UP to 12 SF (0700-3601) | EACH | 2 | $50.00 | $55.00 | $56.71 | $50.00 | $76.30 |
| 0260 | Object marker, type 1 (0705-10-1) | EACH | 1 | $375.00 | $420.00 | $425.29 | $375.00 | $412.01 |
| 0265 | Delineator, flexible tubular (0705-11-1) | EACH | 24 | $125.00 | $150.00 | $141.76 | $125.00 | $106.82 |
| 0270 | Raised pavement marker, type B (0706-1-3) | EACH | 1,022 | $5.00 | $6.00 | $5.49 | $5.25 | $8.16 |
| 0275 | Painted pavement markings, standard, yellow, island nose (0710-11290) | SF | 202 | $6.50 | $5.00 | $5.49 | $5.50 | $10.15 |
| 0280 | Painted pavement markings, surface (0710-90) | LS | 1 | $33,000 | $30,000 | $42,680 | $24,000 | $61,038 |
| 0285 | Thermoplastic, standard, solid, 8" for interchange and urban island (0711-11102) | GM | 0.06 | $17,000 | $6,500.00 | $7,356.96 | $6,100.00 | $25,941 |
| 0290 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 1,458 | $4.00 | $7.00 | $4.39 | $6.10 | $6.26 |
| 0295 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 2,224 | $5.00 | $7.50 | $5.49 | $6.60 | $8.01 |
| 0300 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 309 | $8.00 | $9.00 | $6.59 | $8.10 | $12.59 |
| 0305 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 0.39 | $2,500.00 | $2,800.00 | $3,244.74 | $2,425.00 | $3,814.90 |
| 0310 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 3 | $175.00 | $240.00 | $247.20 | $210.00 | $274.67 |
| 0315 | Thermoplastic, standard, arrow (0711-11170) | EACH | 51 | $85.00 | $100.00 | $98.88 | $90.00 | $137.33 |
| 0320 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 41 | $5.20 | $7.50 | $5.49 | $6.75 | $8.01 |
| 0325 | Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241) | GM | 0.30 | $2,500.00 | $2,800.00 | $3,284.98 | $2,400.00 | $3,662.30 |
| 0330 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 768 | $13.25 | $18.00 | $21.97 | $15.50 | $20.60 |
| 0335 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 2.67 | $4,000.00 | $5,500.00 | $5,706.58 | $5,000.00 | $6,714.21 |
| 0340 | Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131) | GM | 1.97 | $1,800.00 | $2,800.00 | $3,290.94 | $2,400.00 | $2,746.72 |
| 0345 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 1.96 | $4,000.00 | $5,500.00 | $5,710.08 | $5,000.00 | $6,714.21 |
| 0350 | Thermoplastic, remove existing thermoplastic pavement markings- surface to remain (0711-17-1) | SF | 490 | $4.00 | $2.75 | $7.97 | $2.35 | $6.33 |
| 0355 | Fiber optic cable locator (0633-6) | DA | 120 | $149.04 | $175.00 | $163.45 | $164.00 | $227.43 |
| 0360 | Loop assembly, F&I, type B (0660-2102) | AS | 18 | $1,297.08 | $1,500.00 | $1,422.45 | $1,430.00 | $1,979.29 |
| 0365 | Loop assembly, F&I, type F (0660-2106) | AS | 9 | $1,621.08 | $1,800.00 | $1,777.76 | $1,790.00 | $2,473.70 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of January 28, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.