FDOT contract T3919 bid tabulation

HUB PRESLEY RD OVER POND CREEK, BRIDGE NO 604152. Let by Florida DOT on April 29, 2026, Walton, District 3. 4 bids received; low bid $1,664,580 by F & W Construction Company, Inc..

Owner
Florida DOT
Letting
29 APR 2026
Pay items
52
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1F & W Construction Company, Inc.$1,664,580Low
2Anderson Columbia Co., Inc.$1,811,532+9.0%
3Murphree Bridge Corporation$1,878,085+13%
4H. G. Harders & Son, Inc.$2,960,925+78%
FDOT contract T3919: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. F & W Construction Company, Inc.2. Anderson Columbia Co., Inc.3. Murphree Bridge Corporation4. H. G. Harders & Son, Inc.
0005Removal of existing structures/bridges (0110-3)SF1$183,500$186,600$90,000$91,611
0010Conc class II, bridge superstructure (0400-2-4)CY129.90$750.00$1,250.00$1,900.00$3,730.00
0015Concrete class II, approach slabs (0400-2-10)CY40.40$650.00$800.00$990.00$2,293.00
0020Concrete class IV, bridge substructure (0400-4-5)CY34.50$800.00$2,650.00$3,400.00$2,677.00
0025Conc class IV, bulkhead (0400-4-8)CY32.60$1,000.00$2,200.00$4,450.00$2,205.50
0030Bridge deck grooving (0400-7-1)SY240$35.00$26.00$20.00$34.00
0035Plain neoprene bearing pads (0400-148)CF3.30$5,000.00$1,950.00$1,850.00$3,650.00
0040Reinforcing steel - bridge superstructure (0415-1-4)LB38,205$2.50$1.50$1.85$2.58
0045Reinforcing steel- bridge substructure (0415-1-5)LB4,754$2.50$2.50$1.85$2.58
0050Reinforcing steel- bulkhead (0415-1-8)LB2,960$2.50$2.50$1.85$2.58
0055Reinforcing steel- approach slabs (0415-1-9)LB8,088$2.50$1.50$1.85$2.58
0065Pile inspection, driven pile (0455-20-1)EACH14$2,500.00$600.00$1,500.00$1,000.00
0070Prestressed concrete piling, SQ (0455-34-5)LF589$85.00$210.00$335.00$850.00
0075Pile redrive (0455-115)EACH4$2,500.00$1,725.00$1,200.00$5,000.00
0080Sheet piling steel, F&I (0455-133-3)SF6,102$90.00$72.00$62.50$85.00
0085Load test (dynamic), data collection and analysis (0455-137)EACH14$1,500.00$1,950.00$1,800.00$1,500.00
0090Load test (dynamic), test (0455-137-2)EACH14$1,000.00$2,350.00$1,800.00$1,500.00
0095Test piles-prestressed concrete,24" SQ (0455-143-5)LF135$300.00$450.00$250.00$1,500.00
0100Bridge deck expansion joint, construction, F&I poured joint with backer rod (0458-1-11)LF54$60.00$85.00$80.00$75.00
0105Concrete traffic railing- 36" single-slope (0521-5-13)LF260$250.00$175.00$150.00$170.00
0110Riprap- rubble, bank and shore (0530-3-3)TN305$90.00$115.00$100.00$304.75
0115Bedding stone (0530-74)TN113.50$85.00$185.00$116.00$270.00
0120Conduit, furnish & install, embedded concrete barriers and traffic railings (0630-2-16)LF260$10.00$22.00$13.00$46.00
0125Junction box, furnish & install, embedded (0635-3-13)EACH4$500.00$800.00$800.00$450.00
0130Mobilization (0101-1)LS1$100,000$180,000$98,242$194,050
0135Maintenance of traffic (0102-1)DA1$7,500.00$4,000.00$25,000$14,000
0140Work zone sign (0102-60)ED17,976$0.35$0.16$0.35$0.28
0145Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED3,648$0.12$0.16$0.12$0.17
0150Portable changeable message sign, temporary (0102-99)ED912$18.00$17.00$18.00$35.00
0155Type III barricade (0102-115)ED1,712$0.35$0.55$0.35$0.58
0160Sediment barrier (0104-10-3)LF869$4.50$6.50$5.00$9.80
0165Floating turbidity barrier (0104-11)LF40$24.25$60.00$25.00$43.10
0170Soil tracking prevention device (0104-15)EACH2$7,200.00$350.00$6,900.00$7,187.50
0175Clearing & grubbing (0110-1-1)ACRE1$15,500$17,000$11,686$26,910
0180Regular excavation (0120-1)CY1,418$12.35$7.75$32.00$24.15
0185Embankment (0120-6)CY659.40$15.62$11.00$19.00$26.50
0190Type B stabilization (0160-4)SY918$16.85$20.00$14.50$12.65
0195Optional base, base group 06 (0285-706)SY718$20.15$30.00$39.00$51.90
0200Superpave asphaltic concrete, traffic B, PG76-22 (0334-1-52)TN49.40$485.00$310.00$327.00$408.60
0205Asphalt concrete friction course,traffic B, FC-12.5, PG (0337-7-81)TN60.90$485.00$285.00$362.00$404.50
0210Shoulder gutter- concrete (0520-6)LF94$74.85$120.00$99.00$74.75
0215Riprap, rubble, F&I, ditch lining (0530-3-4)TN12$205.00$185.00$277.00$328.00
0220Bedding stone (0530-74)TN8.60$195.00$185.00$271.00$305.00
0225Guardrail removal (0536-73)LF307$10.00$13.00$10.00$29.00
0230Performance turf, sod (0570-1-2)SY819$9.15$3.85$4.92$9.80
0235Object marker, type 3 (0705-10-3)EACH4$400.00$200.00$400.00$632.50
0240Raised pavement marker, type B (0706-1-3)EACH18$10.00$10.75$10.00$11.50
0245Painted pavement markings, surface (0710-90)LS1$1,100.00$1,250.00$1,100.00$1,725.00
0250Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM0.10$17,500$20,000$17,500$14,375
0255Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM0.10$17,500$20,000$17,500$14,375
0260Permanent tape, white, solid, 6" for concrete bridges (0713-103101)GM0.03$32,500$35,000$32,500$51,750
0265Permanent tape, yellow, solid, for concrete bridges (0713-103201)GM0.03$32,500$35,000$32,500$51,750
FDOT contract T3919: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of April 29, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy