F & W Construction Company, Inc.: FDOT bid record

F & W Construction Company, Inc. submitted 18 bids on Florida DOT contracts in the data, from 14 NOV 2018 to 28 OCT 2026, and was the low bidder on 8 of them (44%). When it was not low, its total sat a median +10% above the low bid.

Owner
Florida DOT
Low bid volume
$20,438,137
Latest bid
28 OCT 2026
Data through
28 OCT 2026
18Bids
8Low bids
44Win rate, percent
+10%Median gap to the low bid when not low, 10 bids

By year

YearBidsLow bidsWin rate
20182150%
201922100%
20213267%
2022100%
20232150%
202411100%
2025100%
20266117%
F & W Construction Company, Inc., FDOT: bids and low bids by year of letting

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Bedding stone0530-74TN2619 (73%)$90.00$155.00
Concrete class IV, bridge substructure0400-4-5CY1615 (94%)$850.00$1,700.00
Riprap- rubble, bank and shore0530-3-3TN1914 (74%)$90.00$127.00
Channelizing device- types I, II, VP, drum, or LCD0102-74-1ED1713 (76%)$0.12$0.13
Portable changeable message sign, temporary0102-99ED1713 (76%)$17.00$12.00
Type III barricade0102-115ED1412 (86%)$0.35$0.34
Optional base, base group 060285-706SY1811 (61%)$21.20$31.00
Conduit, furnish & install, embedded concrete barriers and traffic railings0630-2-16LF1511 (73%)$10.00$15.70
Work zone sign0102-60ED1810 (56%)$0.32$0.25
Concrete traffic railing- 36" single-slope0521-5-13LF1710 (59%)$130.00$150.00
Raised pavement marker, type B0706-1-3EACH189 (50%)$5.96$5.00
Regular excavation0120-1CY189 (50%)$15.03$25.47
F & W Construction Company, Inc., FDOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

F & W Construction Company, Inc., FDOT: the firms on the same contracts most often

Latest bids

LetContractDistrictProjectRankIts bidAgainst the low bid
28 OCT 2026T3970District 3HANNA MILL POND RD OVER HANNA POND BRIDGE NO 5040433 of 5$5,870,273+12%
29 APR 2026T3919District 3HUB PRESLEY RD OVER POND CREEK, BRIDGE NO 6041521 of 4$1,664,580Low, 9.0% under the second
25 MAR 2026T3939District 3CR 173 (BETHEL RD) OVER GUM CREEK NO 2, BRIDGE NO 6100262 of 3$1,637,391+33%
25 FEB 2026T3928District 3SCOTTS FERRY RD OVER BEAR CREEK, BRIDGE NO 4644192 of 6$5,769,179+3.0%
28 JAN 2026T3929District 3CR 274 OVER TENMILE CREEK BRIDGE NO. 4700353 of 7$6,596,309+14%
28 JAN 2026T3954District 3KLONDIKE RD OVER UNNAMED BRANCH BRIDGE NO 4840602 of 3$2,706,899+2.0%
30 APR 2025T3879District 3HOWELL WILLIAMS RD OVER TEN MILE CREEK, BRIDGE NO 5241502 of 3$2,415,840+7.0%
31 JAN 2024T3790District 3WOODHAM RD OVER HOLMES CREEK AND RELIEF BRIDGE ...1 of 3$3,547,402Low, 4.0% under the second
13 SEP 2023T3788District 3CR 30A OVER WESTERN LAKE, BRIDGE NO. 600892 of 3$11,994,830+1.0%
26 APR 2023T3792District 3BUDDY RD1 of 3$1,248,264Low, 28% under the second
26 OCT 2022T3774District 3TRAM RD2 of 5$2,616,355+11%
08 DEC 2021T3704District 3PLEASANT RIDGE RD1 of 4$1,462,111Low, 5.0% under the second
28 JUL 2021T3742District 3CR 2731 of 3$3,745,152Low, 16% under the second
09 JUN 2021T3711District 3SR 10 (US 90)4 of 5$11,728,648+43%
04 DEC 2019T3699District 3CR 389 (EAST AVE)1 of 5$2,694,142Low, 14% under the second
30 OCT 2019T3632District 3SR 30 (US 98)1 of 6$4,962,076Low, 10% under the second
05 DEC 2018T3679District 3HICKS RD2 of 3$1,793,531+10%
14 NOV 2018T3619District 3VALEE RD1 of 4$1,114,410Low, 10% under the second
F & W Construction Company, Inc.: latest FDOT bids in the data

How this record was read

FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

  • Every bid counted here matched its published total to within one dollar; FDOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy