SCOTTS FERRY RD OVER BEAR CREEK, BRIDGE NO 464419. Let by Florida DOT on February 25, 2026, Bay, District 3. 6 bids received; low bid $5,598,308 by Murphree Bridge Corporation.
- Owner
- Florida DOT
- Letting
- 25 FEB 2026
- Pay items
- 76
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Murphree Bridge Corporation | $5,598,308 | Low |
| 2 | F & W Construction Company, Inc. | $5,769,179 | +3.0% |
| 3 | RJ Gorman Contracting LLC | $6,491,062 | +16% |
| 4 | Superior Construction Company Southeast, LLC | $7,845,936 | +40% |
| 5 | Anderson Columbia Co., Inc. | $8,951,130 | +60% |
| 6 | Southern Road & Bridge, LLC | $10,427,904 | +86% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Murphree Bridge Corporation | 2. F & W Construction Company, Inc. | 3. RJ Gorman Contracting LLC | 4. Superior Construction Company Southeast, LLC | 5. Anderson Columbia Co., Inc. | 6. Southern Road & Bridge, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 0003 | Monitor existing structures- inspection and settlement monitoring (0108-1) | LS | 1 | $7,500.00 | $30,000 | $8,628.27 | $4,750.00 | $46,000 | $20,000 |
| 0005 | Removal of existing structures/bridges (0110-3) | SF | 1 | $50,000 | $457,000 | $41,965 | $300,000 | $700,000 | $95,000 |
| 0010 | Conc class II, bridge superstructure (0400-2-4) | CY | 508.20 | $1,650.00 | $700.00 | $1,830.05 | $1,100.00 | $1,329.70 | $3,100.00 |
| 0015 | Concrete class II, approach slabs (0400-2-10) | CY | 76.80 | $900.00 | $650.00 | $695.43 | $760.00 | $1,115.00 | $2,000.00 |
| 0020 | Concrete class IV, bridge substructure (0400-4-5) | CY | 121.40 | $2,135.00 | $650.00 | $2,896.06 | $2,350.00 | $2,800.00 | $2,800.00 |
| 0025 | Bridge deck grooving (0400-7-1) | SY | 947 | $6.00 | $5.00 | $12.53 | $9.00 | $20.00 | $5.00 |
| 0030 | Bridge deck planing (0400-9-1) | SY | 947 | $22.00 | $8.00 | $12.53 | $9.00 | $20.00 | $8.00 |
| 0035 | Plain neoprene bearing pads (0400-148) | CF | 18 | $1,500.00 | $1,500.00 | $1,311.94 | $1,700.00 | $3,500.00 | $2,000.00 |
| 0040 | Reinforcing steel - bridge superstructure (0415-1-4) | LB | 157,752 | $1.25 | $3.00 | $1.52 | $1.50 | $2.00 | $1.55 |
| 0045 | Reinforcing steel- bridge substructure (0415-1-5) | LB | 19,183 | $1.25 | $3.00 | $1.60 | $1.50 | $4.00 | $1.65 |
| 0050 | Reinforcing steel- approach slabs (0415-1-9) | LB | 14,244 | $1.25 | $3.00 | $1.52 | $1.50 | $2.00 | $1.65 |
| 0055 | Stainless reinforcing steel, substructure (0415-2-5) | LB | 216 | $5.50 | $10.00 | $9.70 | $31.00 | $50.00 | $7.00 |
| 0060 | Pile inspection, driven pile (0455-20-1) | EACH | 36 | $1,200.00 | $5,000.00 | $1,061.94 | $625.00 | $1,000.00 | $1,000.00 |
| 0065 | Prestressed concrete piling, SQ (0455-34-5) | LF | 2,543 | $215.00 | $95.00 | $277.54 | $175.00 | $300.00 | $325.00 |
| 0070 | Pile redrive (0455-115) | EACH | 27 | $150.00 | $2,000.00 | $2,754.56 | $900.00 | $2,500.00 | $3,000.00 |
| 0075 | Load test (dynamic), data collection and analysis (0455-137) | EACH | 36 | $3,470.00 | $6,500.00 | $1,150.45 | $1,350.00 | $3,500.00 | $4,000.00 |
| 0077 | Load test (dynamic), test (0455-137-2) | EACH | 9 | $150.00 | $10,000 | $3,330.17 | $1,300.00 | $6,000.00 | $4,000.00 |
| 0080 | Test piles-prestressed concrete,24" SQ (0455-143-5) | LF | 983 | $275.00 | $200.00 | $329.31 | $280.00 | $450.00 | $365.00 |
| 0085 | Bridge deck expansion joint, construction, F&I poured joint with backer rod (0458-1-11) | LF | 63 | $75.00 | $60.00 | $109.12 | $62.00 | $125.00 | $85.00 |
| 0090 | Concrete traffic railing- 36" single-slope (0521-5-13) | LF | 680 | $100.00 | $100.00 | $166.92 | $149.00 | $200.00 | $175.00 |
| 0095 | Riprap, sand-cement bags (0530-1100) | CY | 23.60 | $1,000.00 | $1,200.00 | $909.95 | $1,175.00 | $2,000.00 | $950.00 |
| 0100 | Riprap- rubble, bank and shore (0530-3-3) | TN | 1,215 | $96.50 | $100.00 | $84.99 | $120.00 | $140.00 | $165.00 |
| 0105 | Bedding stone (0530-74) | TN | 433 | $102.00 | $95.00 | $87.45 | $168.00 | $160.00 | $165.00 |
| 0110 | Conduit, furnish & install, embedded concrete barriers and traffic railings (0630-2-16) | LF | 2,040 | $18.00 | $5.00 | $3.73 | $21.00 | $18.00 | $20.00 |
| 0115 | Junction box, furnish & install, embedded (0635-3-13) | EACH | 4 | $2,750.00 | $500.00 | $161.66 | $1,200.00 | $1,600.00 | $600.00 |
| 0120 | Mobilization (0101-1) | LS | 1 | $559,674 | $444,000 | $440,965 | $784,590 | $1,015,000 | $1,000,000 |
| 0125 | Maintenance of traffic (0102-1) | DA | 1 | $21,500 | $30,000 | $68,255 | $100,000 | $90,000 | $400,000 |
| 0130 | Special detour- temporary pavement (0102-2200) | SY | 1 | $105,000 | $202,767 | $176,573 | $300,000 | $175,000 | $225,000 |
| 0135 | Special detour- temporary earthwork/base (0102-2300) | CY | 1 | $370,000 | $321,667 | $319,121 | $400,000 | $600,000 | $525,000 |
| 0140 | Special detour- temporary bridge (0102-2400) | EACH | 1 | $754,682 | $821,192 | $882,611 | $820,650 | $1,145,000 | $2,000,000 |
| 0145 | Work zone sign (0102-60) | ED | 10,820 | $0.40 | $0.40 | $0.40 | $0.50 | $0.60 | $0.30 |
| 0150 | Temporary barrier, F&I, low profile, concrete (0102-71-13) | LF | 280 | $60.00 | $60.00 | $64.05 | $60.00 | $80.00 | $50.00 |
| 0155 | Temporary guardrail (0102-73) | LF | 3,395 | $25.00 | $25.00 | $21.24 | $25.00 | $35.00 | $30.00 |
| 0160 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 8,480 | $0.12 | $0.12 | $0.14 | $0.20 | $0.20 | $0.30 |
| 0165 | Portable changeable message sign, temporary (0102-99) | ED | 1,220 | $20.00 | $20.00 | $19.21 | $20.00 | $25.00 | $40.00 |
| 0170 | Type III barricade (0102-115) | ED | 2,240 | $1.00 | $1.00 | $0.38 | $1.00 | $1.25 | $0.60 |
| 0175 | Artificial coverings /rolled erosion control products (0104-1) | SY | 142 | $1.55 | $3.18 | $17.26 | $16.00 | $25.00 | $8.00 |
| 0180 | Sediment barrier (0104-10-3) | LF | 3,096 | $4.00 | $4.60 | $3.33 | $20.00 | $10.00 | $3.00 |
| 0185 | Floating turbidity barrier (0104-11) | LF | 224 | $15.00 | $20.00 | $21.34 | $26.50 | $55.00 | $20.00 |
| 0190 | Staked turbidity barrier- nylon reinforced PVC (0104-12) | LF | 1,165 | $4.50 | $34.17 | $11.25 | $24.00 | $23.00 | $8.00 |
| 0195 | Soil tracking prevention device (0104-15) | EACH | 2 | $3,850.00 | $8,455.00 | $4,656.44 | $8,000.00 | $9,500.00 | $5,000.00 |
| 0200 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $45,000 | $91,491 | $83,066 | $1,467,469 | $175,000 | $215,000 |
| 0205 | Removal of existing concrete (0110-4-10) | SY | 575 | $9.00 | $6.91 | $18.88 | $12.05 | $11.00 | $20.00 |
| 0210 | Regular excavation (0120-1) | CY | 6,878.70 | $9.00 | $4.42 | $12.94 | $11.30 | $12.00 | $24.00 |
| 0215 | Embankment (0120-6) | CY | 7,008.60 | $19.50 | $18.36 | $25.67 | $15.00 | $30.00 | $40.00 |
| 0220 | Type B stabilization (0160-4) | SY | 6,667 | $5.00 | $8.63 | $5.95 | $12.30 | $7.00 | $20.00 |
| 0225 | Optional base, base group 01 (0285-701) | SY | 244 | $19.20 | $11.23 | $31.98 | $33.20 | $30.00 | $30.00 |
| 0230 | Optional base, base group 06 (0285-706) | SY | 4,104 | $26.70 | $20.66 | $34.36 | $26.00 | $38.00 | $31.00 |
| 0235 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 815 | $6.00 | $12.66 | $9.14 | $15.20 | $12.00 | $32.00 |
| 0240 | Superpave asphaltic concrete, traffic B, PG76-22 (0334-1-52) | TN | 379.80 | $145.00 | $179.40 | $209.74 | $157.00 | $200.00 | $220.00 |
| 0245 | Asphalt concrete friction course,traffic B, FC-12.5, PG (0337-7-81) | TN | 419.20 | $148.00 | $184.04 | $210.06 | $164.00 | $207.00 | $210.00 |
| 0250 | Miscellaneous asphalt (0339-1) | TN | 30.70 | $250.00 | $195.99 | $331.86 | $840.00 | $321.00 | $500.00 |
| 0255 | Inlets, gutter, type S, <10' (0425-1701) | EACH | 6 | $6,850.00 | $6,949.33 | $9,135.49 | $9,215.00 | $9,500.00 | $8,000.00 |
| 0260 | Pipe culvert,optional material,round, 18"S/CD (0430-175118) | LF | 175 | $99.50 | $95.29 | $169.51 | $230.00 | $129.00 | $150.00 |
| 0265 | U-endwall with baffles, index 261/430-011, 1:3 slope, 18"pipe (0430-611225) | EACH | 1 | $4,900.00 | $6,381.89 | $5,756.27 | $5,520.00 | $6,500.00 | $5,000.00 |
| 0270 | U-endwall with baffles, index 261/430-011, 1:2 slope, 18"pipe (0430-611325) | EACH | 1 | $4,500.00 | $6,323.20 | $5,874.36 | $5,600.00 | $6,500.00 | $5,000.00 |
| 0275 | Shoulder gutter- concrete (0520-6) | LF | 589 | $45.00 | $61.41 | $82.07 | $72.25 | $77.50 | $85.00 |
| 0280 | Riprap, rubble, F&I, ditch lining (0530-3-4) | TN | 28.10 | $200.00 | $115.81 | $156.50 | $125.00 | $500.00 | $145.00 |
| 0285 | Bedding stone (0530-74) | TN | 13.30 | $200.00 | $114.82 | $144.76 | $375.00 | $500.00 | $160.00 |
| 0290 | Guardrail -roadway, general (0536-1-1) | LF | 961 | $27.00 | $27.00 | $37.83 | $27.00 | $35.00 | $27.50 |
| 0295 | Guardrail removal (0536-73) | LF | 112 | $5.00 | $5.00 | $3.98 | $5.00 | $35.00 | $3.00 |
| 0300 | Guardrail end treatment- trailing anchorage (0536-85-20) | EACH | 2 | $2,200.00 | $2,200.00 | $2,389.36 | $2,200.00 | $3,000.00 | $2,250.00 |
| 0305 | Guardrail end treatment- parallel approach terminal (0536-85-24) | EACH | 2 | $3,500.00 | $3,500.00 | $4,645.99 | $3,500.00 | $4,000.00 | $4,500.00 |
| 0310 | Fencing, type B, 7.1-8.0', with barbed wire attachment (0550-10241) | LF | 676 | $42.25 | $30.00 | $53.10 | $55.05 | $80.00 | $60.00 |
| 0315 | Performance turf, sod (0570-1-2) | SY | 26,892 | $3.25 | $4.56 | $7.14 | $5.00 | $5.00 | $6.75 |
| 0320 | Raised pavement marker, type B (0706-1-3) | EACH | 1,215 | $4.50 | $4.50 | $6.64 | $4.50 | $6.00 | $5.50 |
| 0325 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 0.72 | $1,750.00 | $1,750.00 | $4,645.99 | $1,750.00 | $4,200.00 | $4,000.00 |
| 0330 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 0.72 | $1,750.00 | $1,750.00 | $4,645.99 | $1,750.00 | $4,200.00 | $4,000.00 |
| 0335 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 2 | $500.00 | $500.00 | $630.53 | $500.00 | $500.00 | $650.00 |
| 0340 | Single column ground sign assembly, remove (0700-1600) | EACH | 5 | $50.00 | $50.00 | $53.10 | $50.00 | $500.00 | $55.00 |
| 0345 | Raised pavement marker, type B (0706-1-3) | EACH | 112 | $4.50 | $4.50 | $6.64 | $4.50 | $6.00 | $5.50 |
| 0350 | Painted pavement markings, surface (0710-90) | LS | 1 | $2,950.00 | $2,950.00 | $5,110.59 | $2,950.00 | $6,000.00 | $4,500.00 |
| 0355 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 0.74 | $5,500.00 | $5,500.00 | $7,300.85 | $5,500.00 | $5,500.00 | $6,000.00 |
| 0360 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 0.74 | $5,500.00 | $5,500.00 | $7,300.85 | $5,500.00 | $5,500.00 | $6,000.00 |
| 0365 | Permanent tape, white, solid, 6" for concrete bridges (0713-103101) | GM | 0.11 | $35,000 | $35,000 | $59,734 | $35,000 | $55,000 | $50,000 |
| 0370 | Permanent tape, yellow, solid, for concrete bridges (0713-103201) | GM | 0.11 | $35,000 | $35,000 | $59,734 | $35,000 | $55,000 | $50,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of February 25, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.