FDOT contract T3939 bid tabulation

CR 173 (BETHEL RD) OVER GUM CREEK NO 2, BRIDGE NO 610026. Let by Florida DOT on March 25, 2026, Washington, District 3. 3 bids received; low bid $1,234,568 by RJ Gorman Contracting LLC.

Owner
Florida DOT
Letting
25 MAR 2026
Pay items
43
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1RJ Gorman Contracting LLC$1,234,568Low
2F & W Construction Company, Inc.$1,637,391+33%
3Superior Construction Company Southeast, LLC$2,174,836+76%
FDOT contract T3939: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. RJ Gorman Contracting LLC2. F & W Construction Company, Inc.3. Superior Construction Company Southeast, LLC
0005Removal of existing structures/bridges (0110-3)SF1$28,798$406,000$154,365
0010Concrete class IV, culverts (0400-4-1)CY223.80$1,836.73$1,225.00$3,685.00
0015Reinforcing steel- roadway (0415-1-1)LB39,687$1.57$2.00$2.00
0020Concrete barrier, with slab, 36" single slope (0521-8-7)LF98$563.43$200.00$820.00
0025Riprap- rubble, bank and shore (0530-3-3)TN564.50$123.21$100.00$92.00
0030Bedding stone (0530-74)TN210.20$131.95$90.00$112.00
0035Conduit, furnish & install, embedded concrete barriers and traffic railings (0630-2-16)LF196$3.91$50.00$20.80
0040Junction box, furnish & install, embedded (0635-3-13)EACH4$169.67$1,000.00$1,200.00
0045Mobilization (0101-1)LS1$154,159$300,000$217,484
0050Maintenance of traffic (0102-1)DA1$13,361$15,000$38,500
0055Commercial material for temporary driveway maintenance (0102-3)CY25.50$100.74$600.00$55.00
0060Work zone sign (0102-60)ED5,400$0.34$0.35$0.35
0065Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED1,552$0.21$0.05$0.20
0070Portable changeable message sign, temporary (0102-99)ED388$20.68$20.00$25.00
0075Type III barricade (0102-115)ED720$0.41$0.35$0.50
0080Sediment barrier (0104-10-3)LF1,277$1.91$6.00$10.00
0085Floating turbidity barrier (0104-11)LF278$15.11$40.00$30.00
0090Staked turbidity barrier- nylon reinforced PVC (0104-12)LF390$7.63$30.00$20.00
0095Soil tracking prevention device (0104-15)EACH2$1,895.71$5,000.00$4,330.00
0100Clearing & grubbing (0110-1-1)ACRE1$38,663$43,650$278,613
0105Mailbox, F&I single (0110-7-1)EACH1$344.73$240.00$350.00
0110Regular excavation (0120-1)CY1,235.30$25.32$30.00$20.25
0115Borrow excavation, truck measure (0120-2-2)CY1,157.60$15.99$22.00$26.25
0120Excavation for structures (0125-1)CY268.70$4.96$30.00$39.00
0125Type B stabilization (0160-4)SY2,744$6.23$17.00$11.50
0130Optional base, base group 01 (0285-701)SY353$24.01$24.00$24.75
0135Optional base, base group 06 (0285-706)SY1,805$28.45$31.00$34.25
0140Turnout base- optional materials (0286-1)SY67$45.78$47.00$83.25
0145Superpave asphaltic concrete, traffic B, PG76-22 (0334-1-52)TN153.50$310.25$195.00$270.00
0150Asphalt concrete friction course,traffic B, FC-12.5, PG (0337-7-81)TN174.10$310.25$195.00$285.00
0155Miscellaneous asphalt (0339-1)TN42.90$482.61$350.00$471.50
0160Pipe culvert, optional material, other shape - ellip/arch, 24"SD (0430-174224)LF19$178.34$285.00$462.00
0165Mitered end sect, optional - elliptical / arch, 24" SD (0430-984629)EACH2$3,688.39$2,600.00$4,326.75
0170Guardrail -roadway, general (0536-1-1)LF462$27.48$27.00$12.00
0175Guardrail transition to rigid barrier, F&I- index 536- 001, approach TL-3 (0536-8112)EACH4$4,974.63$3,500.00$2,200.00
0180Guardrail removal (0536-73)LF283$3.12$2.00$2.00
0185Guardrail end treatment- trailing anchorage (0536-85-20)EACH2$2,061.00$2,000.00$2,000.00
0190Guardrail end treatment- parallel approach terminal (0536-85-24)EACH2$4,944.11$3,500.00$3,000.00
0195Performance turf, sod (0570-1-2)SY4,243$5.51$6.50$8.00
0200Raised pavement marker, type B (0706-1-3)EACH36$13.79$10.00$5.00
0205Painted pavement markings, surface (0710-90)LS1$2,068.36$765.00$1,201.50
0210Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM0.27$14,478$6,000.00$5,500.00
0215Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM0.27$14,478$6,500.00$5,500.00
FDOT contract T3939: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of March 25, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy