FDOT contract T3954 bid tabulation
KLONDIKE RD OVER UNNAMED BRANCH BRIDGE NO 484060. Let by Florida DOT on January 28, 2026, Escambia, District 3. 3 bids received; low bid $2,666,435 by Murphree Bridge Corporation.
- Owner
- Florida DOT
- Letting
- 28 JAN 2026
- Pay items
- 81
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Murphree Bridge Corporation | $2,666,435 | Low |
| 2 | F & W Construction Company, Inc. | $2,706,899 | +2.0% |
| 3 | RJ Gorman Contracting LLC | $3,505,088 | +31% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Murphree Bridge Corporation | 2. F & W Construction Company, Inc. | 3. RJ Gorman Contracting LLC |
|---|---|---|---|---|---|---|
| 0005 | Removal of existing structures/bridges (0110-3) | SF | 1 | $37,000 | $163,000 | $48,000 |
| 0010 | Concrete class II, approach slabs (0400-2-10) | CY | 62.10 | $1,200.00 | $700.00 | $1,000.00 |
| 0015 | Concrete class II, cast-in-place topping with shrinkage admixture (0400-2-47) | CY | 68.40 | $1,800.00 | $850.00 | $1,468.00 |
| 0020 | Concrete class IV, bridge substructure (0400-4-5) | CY | 32.80 | $3,500.00 | $700.00 | $1,610.00 |
| 0025 | Bridge deck grooving (0400-7-1) | SY | 256 | $9.00 | $25.00 | $15.00 |
| 0030 | Plain neoprene bearing pads (0400-148) | CF | 3.30 | $1,800.00 | $5,000.00 | $2,300.00 |
| 0035 | Reinforcing steel - bridge superstructure (0415-1-4) | LB | 15,005 | $1.60 | $2.50 | $1.73 |
| 0040 | Reinforcing steel- bridge substructure (0415-1-5) | LB | 5,396 | $1.60 | $2.50 | $1.73 |
| 0045 | Reinforcing steel- approach slabs (0415-1-9) | LB | 11,358 | $1.60 | $2.50 | $1.73 |
| 0050 | Prestressed beam: florida slab beam, beam depth 18" carbon steel, width 55-57" (0450-8-33) | LF | 469 | $600.00 | $350.00 | $475.00 |
| 0053 | Pile inspection, driven pile (0455-20-1) | EACH | 10 | $650.00 | $10,000 | $950.00 |
| 0055 | Prestressed concrete piling, SQ (0455-34-3) | LF | 456 | $265.00 | $65.00 | $220.00 |
| 0057 | Pile redrive (0455-115) | EACH | 2 | $4,750.00 | $10,000 | $3,700.00 |
| 0058 | Load test (dynamic), data collection and analysis (0455-137) | EACH | 12 | $1,000.00 | $10,000 | $1,250.00 |
| 0059 | Load test (dynamic), test (0455-137-2) | EACH | 2 | $500.00 | $10,000 | $3,800.00 |
| 0060 | Test piles-prestressed concrete,18" SQ (0455-143-3) | LF | 144 | $380.00 | $400.00 | $265.00 |
| 0065 | Bridge deck expansion joint, construction, F&I poured joint with backer rod (0458-1-11) | LF | 78 | $75.00 | $50.00 | $110.00 |
| 0070 | Concrete traffic railing- 36" single-slope (0521-5-13) | LF | 200 | $185.00 | $350.00 | $520.00 |
| 0075 | Riprap, sand-cement bags (0530-1100) | CY | 20 | $1,400.00 | $2,250.00 | $850.00 |
| 0080 | Riprap- rubble, bank and shore (0530-3-3) | TN | 727.40 | $140.00 | $100.00 | $160.00 |
| 0085 | Bedding stone (0530-74) | TN | 259 | $146.00 | $90.00 | $145.00 |
| 0090 | Conduit, furnish & install, embedded concrete barriers and traffic railings (0630-2-16) | LF | 407 | $20.00 | $10.00 | $20.00 |
| 0095 | Junction box, furnish & install, embedded (0635-3-13) | EACH | 8 | $900.00 | $300.00 | $2,000.00 |
| 0100 | Mobilization (0101-1) | LS | 1 | $273,578 | $250,000 | $500,000 |
| 0105 | Maintenance of traffic (0102-1) | DA | 1 | $42,500 | $22,481 | $45,000 |
| 0110 | Special detour- temporary pavement (0102-2200) | SY | 1 | $110,500 | $28,841 | $45,000 |
| 0115 | Special detour- temporary earthwork/base (0102-2300) | CY | 1 | $126,400 | $93,589 | $255,000 |
| 0120 | Special detour- temporary bridge (0102-2400) | EACH | 1 | $401,078 | $550,000 | $670,000 |
| 0125 | Commercial material for temporary driveway maintenance (0102-3) | CY | 27.50 | $147.65 | $126.95 | $320.00 |
| 0130 | Work zone sign (0102-60) | ED | 10,970 | $0.35 | $0.35 | $0.50 |
| 0135 | Temporary barrier, F&I, anchored (0102-71-15) | LF | 590 | $65.00 | $95.53 | $78.00 |
| 0140 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 37,712 | $0.15 | $0.15 | $0.20 |
| 0145 | Temporary crash cushion, redirective option (0102-89-1) | LO | 4 | $3,000.00 | $3,000.00 | $2,000.00 |
| 0150 | Portable changeable message sign, temporary (0102-99) | ED | 1,028 | $25.00 | $25.00 | $25.00 |
| 0155 | Type III barricade (0102-115) | ED | 2,560 | $0.55 | $0.55 | $1.00 |
| 0160 | Artificial coverings /rolled erosion control products (0104-1) | SY | 548 | $16.00 | $4.51 | $14.00 |
| 0165 | Temporary slope drain / runoff control structure (0104-6) | LF | 73 | $135.50 | $68.21 | $75.00 |
| 0170 | Sediment barrier (0104-10-3) | LF | 883 | $9.80 | $7.53 | $3.00 |
| 0175 | Soil tracking prevention device (0104-15) | EACH | 2 | $7,700.00 | $4,365.03 | $8,250.00 |
| 0180 | Monitor existing structures- inspection and settlement monitoring (0108-1) | LS | 1 | $12,500 | $35,000 | $22,000 |
| 0185 | Monitor existing structures- vibration monitoring (0108-2) | LS | 1 | $20,000 | $36,000 | $22,000 |
| 0190 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $25,675 | $73,575 | $50,000 |
| 0195 | Removal of existing concrete (0110-4-10) | SY | 278 | $25.00 | $16.09 | $58.00 |
| 0200 | Mailbox, F&I single (0110-7-1) | EACH | 10 | $900.00 | $277.00 | $350.00 |
| 0205 | Regular excavation (0120-1) | CY | 1,578.10 | $16.00 | $14.76 | $50.00 |
| 0210 | Borrow excavation, truck measure (0120-2-2) | CY | 530.20 | $33.80 | $33.53 | $62.00 |
| 0215 | Type B stabilization (0160-4) | SY | 2,862 | $7.25 | $8.68 | $26.00 |
| 0220 | Optional base, base group 01 (0285-701) | SY | 1,011 | $26.50 | $24.72 | $47.00 |
| 0225 | Optional base, base group 06 (0285-706) | SY | 459 | $51.20 | $54.66 | $72.00 |
| 0230 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 1,365 | $10.00 | $4.35 | $11.00 |
| 0235 | Superpave asphaltic concrete, traffic B, PG76-22 (0334-1-52) | TN | 43.10 | $326.00 | $182.16 | $520.00 |
| 0240 | Asphalt concrete friction course,traffic B, FC-12.5, PG (0337-7-81) | TN | 207 | $255.00 | $201.63 | $345.00 |
| 0245 | Miscellaneous asphalt (0339-1) | TN | 16.80 | $365.00 | $418.32 | $720.00 |
| 0250 | Pipe culvert, optional material, round, 18"SD (0430-174118) | LF | 38 | $161.00 | $144.23 | $430.00 |
| 0255 | Pipe culvert, optional material, other shape - ellip/arch, 15"SD (0430-174215) | LF | 65 | $140.00 | $142.57 | $375.00 |
| 0260 | Mitered end section, optional round, 18" SD (0430-984125) | EACH | 4 | $2,750.00 | $2,671.82 | $3,700.00 |
| 0265 | Mitered end section, optional other - ellip/arch, 15" SD (0430-984623) | EACH | 8 | $2,750.00 | $2,670.36 | $4,090.00 |
| 0270 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 174 | $138.50 | $92.75 | $250.00 |
| 0275 | Concrete ditch pavement, non reinforced, 4" (0524-1-2) | SY | 177 | $127.35 | $180.65 | $175.00 |
| 0280 | Riprap, rubble, F&I, ditch lining (0530-3-4) | TN | 3 | $515.00 | $363.74 | $1,300.00 |
| 0285 | Guardrail -roadway, general/low speed TL-2 (0536-1-0) | LF | 319 | $22.00 | $22.00 | $38.00 |
| 0290 | Guardrail transition to rigid barrier, F&I- index 536- 001, approach TL-2 (0536-8111) | EACH | 2 | $2,200.00 | $2,200.00 | $4,500.00 |
| 0295 | Guardrail transition to rigid barrier, F&I- index 536- 001, trailing (0536-8113) | EACH | 2 | $2,200.00 | $2,200.00 | $4,550.00 |
| 0300 | Guardrail removal (0536-73) | LF | 102 | $2.00 | $2.00 | $3.50 |
| 0305 | Guardrail end treatment- trailing anchorage (0536-85-20) | EACH | 2 | $2,000.00 | $2,000.00 | $1,600.00 |
| 0310 | Guardrail end treatment- parallel approach terminal (0536-85-24) | EACH | 1 | $3,000.00 | $3,000.00 | $4,100.00 |
| 0315 | Guardrail end treatment- type CRT (0536-85-26) | EACH | 1 | $4,500.00 | $4,500.00 | $4,500.00 |
| 0320 | Performance turf, sod (0570-1-2) | SY | 7,464 | $6.25 | $3.07 | $8.00 |
| 0325 | Raised pavement marker, type B (0706-1-3) | EACH | 692 | $5.25 | $10.00 | $6.50 |
| 0330 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 0.33 | $2,625.00 | $8,900.00 | $2,000.00 |
| 0335 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 0.33 | $2,625.00 | $8,900.00 | $2,000.00 |
| 0340 | Single column ground sign assembly, relocate (0700-1500) | EACH | 1 | $105.00 | $180.00 | $300.00 |
| 0345 | Single column ground sign assembly, remove (0700-1600) | EACH | 2 | $63.00 | $100.00 | $250.00 |
| 0350 | Raised pavement marker, type B (0706-1-3) | EACH | 33 | $5.25 | $10.00 | $8.00 |
| 0355 | Painted pavement markings, surface (0710-90) | LS | 1 | $1,575.00 | $5,000.00 | $33,000 |
| 0360 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 0.33 | $5,775.00 | $13,000 | $8,000.00 |
| 0365 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 0.06 | $15,750 | $30,000 | $8,000.00 |
| 0370 | Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231) | GM | 0.17 | $3,675.00 | $11,000 | $3,400.00 |
| 0375 | Permanent tape, white, solid, 6" for concrete bridges (0713-103101) | GM | 0.02 | $47,250 | $85,000 | $44,000 |
| 0380 | Permanent tape, yellow, solid, for concrete bridges (0713-103201) | GM | 0.01 | $57,750 | $140,000 | $45,000 |
| 0385 | Permanent tape, yellow, 10-30 skip, 6" wide, for concrete surfaces (0713-103281) | GM | 0.01 | $26,250 | $120,000 | $45,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of January 28, 2026. Compiled by Mirage Metrics.