FDOT contract T3933 bid tabulation
SR 369 (US 319) FROM US 319 NB OFF RAMP TO S OF E IVAN RD. Let by Florida DOT on May 28, 2025, Wakulla, District 3. 5 bids received; low bid $3,627,280 by Peavy & Son Construction Co., Inc..
- Owner
- Florida DOT
- Letting
- 28 MAY 2025
- Pay items
- 101
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Peavy & Son Construction Co., Inc. | $3,627,280 | Low |
| 2 | Pigott Asphalt and Sitework LLC | $3,792,899 | +5.0% |
| 3 | Anderson Columbia Co., Inc. | $3,877,871 | +7.0% |
| 4 | C.W. Roberts Contracting, Inc. | $4,481,995 | +24% |
| 5 | Capital Asphalt Inc | $4,888,892 | +35% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Peavy & Son Construction Co., Inc. | 2. Pigott Asphalt and Sitework LLC | 3. Anderson Columbia Co., Inc. | 4. C.W. Roberts Contracting, Inc. | 5. Capital Asphalt Inc |
|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $135,000 | $259,000 | $378,659 | $329,000 | $450,000 |
| 0010 | Mobilization (0101-1) | LS | 1 | $135,000 | $100,000 | $25,000 | $50,000 | $50,000 |
| 0015 | Maintenance of traffic (0102-1) | DA | 1 | $70,000 | $56,500 | $98,573 | $324,000 | $200,000 |
| 0020 | Maintenance of traffic (0102-1) | DA | 1 | $70,000 | $50,000 | $25,000 | $29,000 | $50,000 |
| 0025 | Commercial material for temporary driveway maintenance (0102-3) | CY | 14.80 | $100.00 | $200.00 | $30.00 | $156.00 | $250.00 |
| 0030 | Traffic control officer (0102-14) | HR | 76 | $100.00 | $100.00 | $100.00 | $91.35 | $125.00 |
| 0035 | Work zone sign (0102-60) | ED | 34,350 | $0.55 | $0.30 | $0.22 | $0.25 | $0.25 |
| 0040 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 154,790 | $0.18 | $0.05 | $0.02 | $0.12 | $0.25 |
| 0045 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 2,150 | $1.00 | $0.50 | $0.11 | $0.12 | $0.25 |
| 0050 | Arrow board / advance warning arrow panel (0102-76) | ED | 390 | $8.50 | $5.00 | $5.61 | $5.70 | $6.00 |
| 0055 | Portable changeable message sign, temporary (0102-99) | ED | 1,024 | $15.00 | $10.00 | $11.22 | $11.40 | $12.00 |
| 0060 | Temporary signalization and maintenance, intersection (0102-104) | ED | 990 | $23.10 | $1.50 | $16.82 | $25.00 | $17.00 |
| 0065 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 990 | $17.85 | $1.50 | $16.82 | $19.40 | $17.00 |
| 0070 | Type III barricade (0102-115) | ED | 2,000 | $11.00 | $0.05 | $0.05 | $0.30 | $0.50 |
| 0075 | Sediment barrier (0104-10-3) | LF | 1,085 | $3.50 | $3.00 | $2.24 | $9.80 | $5.00 |
| 0080 | Inlet protection system (0104-18) | EACH | 7 | $200.00 | $200.00 | $392.57 | $256.00 | $500.00 |
| 0085 | Litter removal (0107-1) | ACRE | 266.29 | $70.00 | $10.00 | $67.29 | $68.50 | $100.00 |
| 0090 | Mowing (0107-2) | ACRE | 215.38 | $70.00 | $10.00 | $56.08 | $57.00 | $120.00 |
| 0095 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $5,000.00 | $15,000 | $6,004.48 | $26,000 | $10,000 |
| 0100 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $5,000.00 | $10,000 | $18,013 | $15,000 | $25,000 |
| 0105 | Removal of existing concrete (0110-4-10) | SY | 58 | $50.00 | $75.00 | $51.76 | $75.00 | $200.00 |
| 0110 | Mailbox, F&I single (0110-7-1) | EACH | 1 | $100.00 | $400.00 | $168.24 | $180.00 | $1,500.00 |
| 0115 | Regular excavation (0120-1) | CY | 654 | $15.00 | $35.00 | $24.32 | $17.40 | $30.00 |
| 0120 | Borrow excavation, truck measure (0120-2-2) | CY | 419.50 | $40.00 | $1.00 | $10.00 | $22.25 | $50.00 |
| 0125 | Regular excavation (3-R projects only) (0120-71) | LS | 1 | $5,000.00 | $12,500 | $7,951.59 | $5,500.00 | $15,000 |
| 0130 | Type B stabilization (0160-4) | SY | 2,122 | $10.00 | $20.00 | $18.10 | $21.00 | $30.00 |
| 0135 | Optional base, base group 06 (0285-706) | SY | 1,777 | $30.00 | $27.50 | $29.05 | $34.00 | $40.00 |
| 0140 | Milling existing asphalt pavement, 2" avg depth (0327-70-5) | SY | 75,466 | $2.00 | $1.85 | $1.50 | $3.05 | $3.50 |
| 0145 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 17,813 | $1.50 | $2.00 | $2.55 | $7.60 | $5.00 |
| 0150 | Superpave asphaltic concrete, traffic C, PG76-22 (0334-1-53) | TN | 144 | $150.00 | $175.00 | $150.00 | $193.40 | $250.00 |
| 0155 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 144 | $140.00 | $175.00 | $150.00 | $220.45 | $250.00 |
| 0160 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 9,771 | $140.00 | $165.00 | $150.00 | $171.00 | $185.00 |
| 0165 | Inlets, DT bot, type C,<10' (0425-1521) | EACH | 3 | $7,000.00 | $6,000.00 | $12,722 | $5,600.00 | $6,800.00 |
| 0170 | Manholes, P-7, <10' (0425-2-41) | EACH | 2 | $10,000 | $7,500.00 | $9,913.96 | $7,200.00 | $12,000 |
| 0175 | Pipe culvert, optional material, round, 18"SD (0430-174118) | LF | 477 | $200.00 | $150.00 | $116.33 | $125.15 | $250.00 |
| 0180 | Pipe culvert, optional material, other shape - ellip/arch, 18"SD (0430-174218) | LF | 333 | $250.00 | $205.00 | $148.27 | $130.00 | $400.00 |
| 0185 | Mitered end section, optional round, 18" SD (0430-984125) | EACH | 4 | $3,000.00 | $3,000.00 | $6,174.72 | $2,600.00 | $3,564.00 |
| 0190 | Mitered end sect, optional - elliptical / arch, 18" SD (0430-984625) | EACH | 2 | $3,600.00 | $4,000.00 | $6,292.87 | $4,000.00 | $4,500.00 |
| 0195 | Concrete curb & gutter, type F (0520-1-10) | LF | 74 | $50.00 | $100.00 | $264.01 | $82.00 | $90.00 |
| 0200 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 160 | $100.00 | $100.00 | $319.68 | $220.00 | $200.00 |
| 0205 | Detectable warnings (0527-2) | SF | 244 | $37.00 | $40.00 | $39.25 | $34.00 | $37.00 |
| 0210 | Performance turf, sod (0570-1-2) | SY | 8,979 | $6.10 | $4.00 | $3.93 | $5.65 | $3.75 |
| 0215 | Raised pavement marker, type B (0706-1-3) | EACH | 2,736 | $4.20 | $5.00 | $4.49 | $4.55 | $4.50 |
| 0220 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 21.04 | $1,575.00 | $1,450.00 | $1,682.41 | $1,700.00 | $1,650.00 |
| 0225 | Painted pavement markings, standard, white, solid for diagonal or chevron, 18" (0710-11124) | LF | 103 | $2.63 | $5.00 | $2.80 | $2.85 | $2.75 |
| 0230 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 327 | $3.15 | $4.00 | $3.36 | $3.40 | $3.50 |
| 0235 | Painted pavement markings, standard, white, arrows (0710-11170) | EACH | 5 | $49.35 | $50.00 | $52.71 | $54.00 | $52.00 |
| 0240 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 21.04 | $1,575.00 | $1,450.00 | $1,682.41 | $1,700.00 | $1,650.00 |
| 0245 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $41,884 | $41,884 | $41,884 | $41,884 | $41,884 |
| 0250 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $8,116.01 | $8,116.01 | $8,116.01 | $8,116.01 | $8,116.01 |
| 0255 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 61 | $488.25 | $400.00 | $476.68 | $490.00 | $468.00 |
| 0260 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 7 | $1,811.25 | $1,300.00 | $1,430.06 | $1,500.00 | $1,400.00 |
| 0265 | Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113) | EACH | 4 | $2,520.00 | $3,000.00 | $2,804.03 | $2,900.00 | $2,750.00 |
| 0270 | Single column ground sign assembly, relocate (0700-1500) | EACH | 1 | $78.75 | $100.00 | $72.90 | $74.00 | $72.00 |
| 0275 | Single column ground sign assembly, remove (0700-1600) | EACH | 45 | $36.75 | $30.00 | $39.25 | $40.00 | $39.00 |
| 0280 | Multi-column ground sign assembly, remove (0700-2600) | EACH | 2 | $357.00 | $500.00 | $1,306.68 | $1,300.00 | $1,281.00 |
| 0285 | Retroreflective sign strip- furnish and install, 5' (0700-13-15) | EACH | 2 | $110.25 | $100.00 | $84.13 | $86.00 | $83.00 |
| 0290 | Object marker, type 1 (0705-10-1) | EACH | 3 | $262.50 | $25.00 | $308.44 | $310.00 | $303.00 |
| 0295 | Object marker, type 2 (0705-10-2) | EACH | 16 | $147.00 | $100.00 | $56.08 | $57.00 | $55.00 |
| 0300 | Raised pavement marker, type B (0706-1-3) | EACH | 1,813 | $4.20 | $4.00 | $4.49 | $4.55 | $5.50 |
| 0305 | Painted pavement markings, surface (0710-90) | LS | 1 | $44,205 | $45,000 | $47,220 | $48,000 | $46,300 |
| 0310 | Thermoplastic, standard, solid, 8" for interchange and urban island (0711-11102) | GM | 0.09 | $11,403 | $10,500 | $12,181 | $11,000 | $12,000 |
| 0315 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 1,388 | $5.25 | $6.00 | $5.61 | $5.70 | $5.50 |
| 0320 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 130 | $6.30 | $6.00 | $6.73 | $6.85 | $7.00 |
| 0325 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 658 | $7.35 | $6.00 | $7.85 | $8.00 | $8.00 |
| 0330 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 0.56 | $4,777.50 | $5,000.00 | $5,103.37 | $5,200.00 | $5,000.00 |
| 0335 | Thermoplastic, standard, arrow (0711-11170) | EACH | 148 | $86.10 | $85.00 | $91.98 | $94.00 | $90.00 |
| 0340 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 821 | $6.30 | $5.50 | $6.73 | $6.85 | $7.00 |
| 0345 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 1,148 | $13.65 | $14.00 | $14.58 | $15.00 | $14.50 |
| 0350 | Thermoplastic, preformed, white, message (0711-14160) | EACH | 18 | $157.50 | $175.00 | $168.24 | $170.00 | $165.00 |
| 0355 | Thermoplastic, preformed, white, arrow (0711-14170) | EACH | 18 | $105.00 | $75.00 | $112.16 | $110.00 | $110.00 |
| 0360 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 6.98 | $6,090.00 | $5,900.00 | $6,505.33 | $6,600.00 | $6,380.00 |
| 0365 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 6.37 | $5,985.00 | $5,900.00 | $6,393.16 | $6,500.00 | $6,270.00 |
| 0370 | Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231) | GM | 4.33 | $2,415.00 | $2,500.00 | $2,579.70 | $2,600.00 | $2,530.00 |
| 0375 | Conduit, furnish & install, open trench (0630-2-11) | LF | 663 | $17.85 | $17.85 | $16.82 | $19.00 | $16.00 |
| 0380 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 627 | $44.10 | $45.00 | $41.50 | $48.00 | $40.00 |
| 0385 | Conduit, furnish & install, aboveground (0630-2-14) | LF | 60 | $36.75 | $39.25 | $22.43 | $40.00 | $22.00 |
| 0390 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 27 | $1,785.00 | $1,800.00 | $1,744.11 | $1,940.00 | $1,650.00 |
| 0395 | Electrical power service, F&I, underground, meter by contractor (0639-1122) | AS | 3 | $4,725.00 | $5,000.00 | $5,608.04 | $5,100.00 | $5,250.00 |
| 0400 | Electrical service wire, & install (0639-2-1) | LF | 200 | $12.60 | $14.00 | $11.22 | $14.00 | $11.00 |
| 0405 | Prestressed concrete pole, type P-II service pole (0641-2-12) | EACH | 3 | $2,310.00 | $2,500.00 | $2,243.22 | $2,500.00 | $2,200.00 |
| 0410 | Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12) | LF | 5,109 | $3.15 | $3.00 | $6.73 | $3.40 | $6.50 |
| 0415 | Load center, F&I, secondary voltage (0715-7-11) | EACH | 3 | $19,425 | $20,000 | $25,797 | $21,000 | $25,000 |
| 0420 | Light pole complete, F&I, standard pole standard foundation, 35' mounting height, 15' arm length (0715-61252) | EACH | 8 | $13,650 | $14,000 | $12,338 | $14,840 | $12,000 |
| 0425 | Light pole complete, F&I, utility conflict pole standard foundation, 35' mounting height, 16' arm length (0715-65266) | EACH | 3 | $14,700 | $15,000 | $14,581 | $16,000 | $14,300 |
| 0430 | Light pole complete, remove pole and foundation (0715-69000) | EACH | 4 | $1,470.00 | $1,500.00 | $2,018.90 | $1,600.00 | $2,000.00 |
| 0435 | Pole cable distribution system, furnish and install, conventional (0715-500-1) | EACH | 11 | $840.00 | $900.00 | $1,009.45 | $910.00 | $1,000.00 |
| 0440 | Conduit, furnish & install, open trench (0630-2-11) | LF | 668 | $17.85 | $17.50 | $22.43 | $19.00 | $22.00 |
| 0445 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 574 | $44.10 | $45.00 | $50.47 | $48.00 | $50.00 |
| 0450 | Signal cable- new or reconstructed intersection, furnish & install (0632-7-1) | PI | 3 | $10,500 | $10,000 | $13,459 | $11,400 | $13,000 |
| 0455 | Signal cable, remove- intersection (0632-7-6) | PI | 3 | $892.50 | $1,000.00 | $1,121.61 | $970.00 | $1,100.00 |
| 0460 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 21 | $1,785.00 | $1,800.00 | $1,744.11 | $1,900.00 | $1,700.00 |
| 0465 | Aluminum signals pole, (0646-1-11) | EACH | 22 | $3,150.00 | $3,000.00 | $3,925.64 | $3,400.00 | $3,750.00 |
| 0470 | Aluminum signals pole, remove (0646-1-60) | EACH | 10 | $525.00 | $750.00 | $560.81 | $570.00 | $550.00 |
| 0475 | Vehicular signal auxiliaries, repair/replace/retrofit- & install, backplate- flexible required (0650-2109) | EACH | 17 | $787.50 | $750.00 | $594.45 | $860.00 | $580.00 |
| 0480 | Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11) | AS | 22 | $1,365.00 | $1,900.00 | $1,682.41 | $1,500.00 | $1,600.00 |
| 0485 | Loop detector, inductive, F&I, type 5, 2CHANNEL, solid state, shelf mounted (0660-1105) | EACH | 12 | $787.50 | $800.00 | $560.81 | $860.00 | $550.00 |
| 0490 | Loop assembly- F&I, type A (0660-2101) | AS | 4 | $1,890.00 | $1,800.00 | $2,355.38 | $2,100.00 | $2,310.00 |
| 0495 | Loop assembly, F&I, type B (0660-2102) | AS | 4 | $1,575.00 | $1,700.00 | $2,804.03 | $1,700.00 | $2,750.00 |
| 0500 | Loop assembly, F&I, type F (0660-2106) | AS | 4 | $1,995.00 | $2,000.00 | $4,486.44 | $2,200.00 | $4,400.00 |
| 0505 | Pedestrian detector, furnish & install, standard (0665-1-11) | EACH | 22 | $472.50 | $500.00 | $1,121.61 | $510.00 | $1,100.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of May 28, 2025. Compiled by Mirage Metrics.