| 0005 | Mobilization (0101-1) | LS | 1 | $436,537 | $370,000 | $464,500 |
| 0010 | Mobilization (0101-1) | LS | 1 | $163,709 | $306,543 | $155,000 |
| 0015 | Maintenance of traffic (0102-1) | DA | 1 | $186,551 | $310,000 | $325,000 |
| 0020 | Maintenance of traffic (0102-1) | DA | 1 | $100,000 | $320,000 | $130,250 |
| 0025 | Traffic control officer (0102-14) | HR | 56 | $99.00 | $80.00 | $105.00 |
| 0030 | Work zone sign (0102-60) | ED | 15,750 | $0.45 | $0.45 | $0.55 |
| 0035 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 23,400 | $0.23 | $0.20 | $0.35 |
| 0040 | Portable changeable message sign, temporary (0102-99) | ED | 928 | $23.12 | $22.15 | $38.50 |
| 0045 | Temporary signalization and maintenance, intersection (0102-104) | ED | 450 | $12.85 | $12.25 | $12.50 |
| 0050 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 450 | $12.85 | $12.25 | $12.50 |
| 0055 | Temporary slope drain / runoff control structure (0104-6) | LF | 135 | $83.83 | $59.00 | $105.00 |
| 0060 | Sediment barrier (0104-10-3) | LF | 28,521 | $2.58 | $3.05 | $7.50 |
| 0065 | Inlet protection system (0104-18) | EACH | 3 | $260.34 | $1,000.00 | $750.00 |
| 0070 | Litter removal (0107-1) | ACRE | 449.82 | $96.38 | $120.00 | $85.00 |
| 0075 | Mowing (0107-2) | ACRE | 449.82 | $83.53 | $100.00 | $85.00 |
| 0080 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $128,322 | $45,000 | $50,000 |
| 0085 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $100,000 | $160,000 | $200,000 |
| 0090 | Removal of existing concrete (0110-4-10) | SY | 441 | $32.79 | $51.00 | $55.00 |
| 0095 | Regular excavation (0120-1) | CY | 2,391.40 | $26.95 | $96.00 | $38.56 |
| 0100 | Borrow excavation, truck measure (0120-2-2) | CY | 2,931.50 | $33.49 | $46.00 | $58.56 |
| 0105 | Type B stabilization (0160-4) | SY | 1,279 | $45.45 | $81.00 | $89.50 |
| 0110 | Optional base, base group 02 (0285-702) | SY | 590 | $50.17 | $120.00 | $89.56 |
| 0115 | Optional base, base group 04 (0285-704) | SY | 15,948 | $47.70 | $69.00 | $31.81 |
| 0120 | Optional base, base group 06 (0285-706) | SY | 856 | $48.95 | $98.00 | $32.02 |
| 0125 | Milling existing asphalt pavement, 1" avg depth (0327-70-1) | SY | 17,911 | $2.42 | $3.35 | $5.10 |
| 0130 | Milling existing asphalt pavement, 3" avg depth (0327-70-4) | SY | 1,592 | $3.37 | $4.60 | $7.25 |
| 0135 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 38,500 | $2.60 | $3.65 | $4.60 |
| 0140 | Milling existing asphalt pavement, 4" avg depth (0327-70-7) | SY | 16,458 | $4.20 | $5.50 | $7.40 |
| 0145 | Superpave asphaltic conc, traffic B (0334-1-12) | TN | 33.10 | $523.70 | $860.00 | $400.00 |
| 0150 | Superpave asphaltic concrete, traffic C, PG76-22 (0334-1-53) | TN | 2,311.50 | $168.49 | $180.00 | $248.65 |
| 0155 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 9,062.70 | $186.14 | $170.00 | $268.65 |
| 0160 | Miscellaneous asphalt (0339-1) | TN | 45.10 | $385.14 | $1,820.00 | $1,200.00 |
| 0165 | Inlets, DT bot, type D, <10' (0425-1541) | EACH | 2 | $11,040 | $17,200 | $19,795 |
| 0170 | Inlets, DT bot, type H, <10' (0425-1581) | EACH | 2 | $14,045 | $21,000 | $26,860 |
| 0175 | Manholes, P-7, <10' (0425-2-41) | EACH | 1 | $11,147 | $12,000 | $31,459 |
| 0180 | Valve boxes, adjust (0425-6) | EACH | 3 | $1,075.17 | $960.00 | $3,500.00 |
| 0185 | Pipe culvert, optional material, round, 18"SD (0430-174118) | LF | 128 | $169.38 | $170.00 | $205.76 |
| 0190 | Pipe culvert, optional material, round, 24"SD (0430-174124) | LF | 16 | $600.07 | $260.00 | $386.88 |
| 0195 | Pipe culvert, optional material, other shape - ellip/arch, 36"SD (0430-174236) | LF | 77 | $376.71 | $710.00 | $915.20 |
| 0200 | Pipe culvert,optional material,round, 18"S/CD (0430-175118) | LF | 349 | $124.23 | $160.00 | $205.76 |
| 0205 | Pipe culvert,optional material,round, 24"S/CD (0430-175124) | LF | 48 | $197.98 | $350.00 | $386.88 |
| 0210 | Pipe culvert,optional material,other shape-elip/arch, 24"S/CD (0430-175224) | LF | 8 | $1,080.19 | $660.00 | $1,500.00 |
| 0215 | Pipe culvert, opt material, shape - elip/arch, 36"S/CD (0430-175236) | LF | 332 | $371.12 | $390.00 | $815.20 |
| 0220 | Mitered end section, optional round, 24" CD (0430-982129) | EACH | 1 | $4,157.41 | $6,700.00 | $9,850.00 |
| 0225 | Mitered end section, optional round, 18" SD (0430-984125) | EACH | 7 | $3,530.10 | $4,100.00 | $6,758.00 |
| 0230 | Mitered end section, optional round, 24" SD (0430-984129) | EACH | 5 | $4,157.41 | $4,500.00 | $9,850.00 |
| 0235 | Mitered end sect, optional - elliptical / arch, 24" SD (0430-984629) | EACH | 1 | $6,262.59 | $10,000 | $10,500 |
| 0240 | Mitered end sect, optional /ellip/arch, 36" SD (0430-984638) | EACH | 3 | $11,702 | $11,000 | $15,650 |
| 0245 | Mitered end sect, replace slab- construction use (0430-991) | EACH | 4 | $2,404.81 | $3,600.00 | $18,550 |
| 0250 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 263 | $127.10 | $210.00 | $175.00 |
| 0255 | Concrete ditch pavement, non reinforced, 4" (0524-1-2) | SY | 126 | $166.22 | $310.00 | $225.00 |
| 0260 | Detectable warnings (0527-2) | SF | 89 | $29.54 | $28.00 | $32.50 |
| 0265 | Riprap, rubble, F&I, ditch lining (0530-3-4) | TN | 12 | $214.88 | $940.00 | $550.00 |
| 0270 | Bedding stone (0530-74) | TN | 8.60 | $232.18 | $510.00 | $550.00 |
| 0275 | Guardrail -roadway, general (0536-1-1) | LF | 697 | $35.97 | $34.00 | $43.75 |
| 0280 | Special guardrail post- post for shallow mount (0536-7-3) | EACH | 3 | $385.36 | $370.00 | $312.50 |
| 0285 | Guardrail removal (0536-73) | LF | 549 | $8.99 | $8.60 | $6.25 |
| 0290 | Guardrail end treatment- parallel approach terminal (0536-85-24) | EACH | 4 | $4,174.69 | $4,000.00 | $5,625.00 |
| 0295 | Performance turf, sod (0570-1-2) | SY | 35,426 | $3.21 | $6.10 | $7.50 |
| 0300 | Raised pavement marker, type B (0706-1-3) | EACH | 1,368 | $5.14 | $4.90 | $6.25 |
| 0305 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 8.41 | $1,284.52 | $1,200.00 | $1,875.00 |
| 0310 | Painted pavement markings, standard, white, solid for interchange and urban island, (0710-11102) | GM | 0.15 | $1,284.52 | $1,200.00 | $2,000.00 |
| 0315 | Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123) | LF | 813 | $3.85 | $3.70 | $2.63 |
| 0320 | Painted pavement markings, standard, white, solid for diagonal or chevron, 18" (0710-11124) | LF | 378 | $5.14 | $4.90 | $2.75 |
| 0325 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 960 | $6.42 | $6.15 | $2.94 |
| 0330 | Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131) | GM | 0.00 | $6,422.61 | $15,000 | $56,250 |
| 0335 | Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141) | GM | 0.47 | $1,284.52 | $1,200.00 | $1,250.00 |
| 0340 | Painted pavement markings, standard, white, message or symbol (0710-11160) | EACH | 13 | $154.14 | $150.00 | $68.75 |
| 0345 | Painted pavement markings, standard, white, arrows (0710-11170) | EACH | 70 | $83.49 | $80.00 | $62.50 |
| 0350 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 6.02 | $1,284.52 | $1,200.00 | $1,875.00 |
| 0355 | Painted pavement markings, standard, yellow, solid for diagonal or chevron, 18" (0710-11224) | LF | 757 | $5.14 | $4.90 | $2.69 |
| 0360 | Painted pavement markings, standard, yellow, skip, 6" (0710-11231) | GM | 1.65 | $1,284.52 | $1,200.00 | $1,312.50 |
| 0365 | Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241) | GM | 0.06 | $6,422.61 | $6,000.00 | $6,250.00 |
| 0370 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $34,633 | $34,633 | $34,633 |
| 0375 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $30,194 | $30,194 | $30,194 |
| 0380 | Ground-in rumble strips, 8" sinusoidal (0546-72-3) | GM | 7.42 | $3,606.46 | $2,500.00 | $1,875.00 |
| 0385 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 20 | $578.03 | $550.00 | $718.75 |
| 0390 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 1 | $2,055.23 | $2,000.00 | $2,500.00 |
| 0395 | Single column ground sign assembly, remove (0700-1600) | EACH | 19 | $64.23 | $61.00 | $62.50 |
| 0400 | Multi-column ground sign assembly, F&I ground mount, 20.0 SF (0700-2112) | EACH | 2 | $6,422.61 | $6,100.00 | $7,312.50 |
| 0405 | Multi-column ground sign assembly, F&I ground mount, 50.0 SF (0700-2114) | EACH | 1 | $8,991.66 | $8,600.00 | $8,125.00 |
| 0410 | Multi-column ground sign assembly, remove (0700-2600) | EACH | 1 | $1,541.43 | $1,500.00 | $1,250.00 |
| 0415 | Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101) | EACH | 2 | $340.40 | $320.00 | $312.50 |
| 0420 | Sign panel, remove, UP to 12 SF (0700-3601) | EACH | 2 | $192.68 | $180.00 | $62.50 |
| 0425 | Object marker, type 1 (0705-10-1) | EACH | 9 | $340.40 | $320.00 | $250.00 |
| 0430 | Raised pavement marker, type B (0706-1-3) | EACH | 1,368 | $5.14 | $4.90 | $6.25 |
| 0435 | Painted pavement markings, surface (0710-90) | LS | 1 | $40,213 | $38,000 | $56,453 |
| 0440 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 813 | $5.14 | $4.90 | $5.31 |
| 0445 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 378 | $6.42 | $6.15 | $6.44 |
| 0450 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 281 | $10.28 | $9.80 | $7.90 |
| 0455 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 0.47 | $4,367.37 | $4,200.00 | $5,032.93 |
| 0460 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 3 | $256.90 | $250.00 | $312.50 |
| 0465 | Thermoplastic, standard, arrow (0711-11170) | EACH | 60 | $109.18 | $100.00 | $93.75 |
| 0470 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 757 | $6.42 | $6.15 | $6.31 |
| 0475 | Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241) | GM | 0.06 | $4,367.37 | $4,100.00 | $18,750 |
| 0480 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 679 | $19.27 | $18.00 | $15.00 |
| 0485 | Thermoplastic, preformed, white, message (0711-14160) | EACH | 10 | $192.68 | $180.00 | $187.50 |
| 0490 | Thermoplastic, preformed, white, arrow (0711-14170) | EACH | 10 | $192.68 | $180.00 | $156.25 |
| 0495 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 8.41 | $5,394.99 | $5,100.00 | $6,375.00 |
| 0500 | Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102) | GM | 0.15 | $10,276 | $9,200.00 | $8,750.00 |
| 0505 | Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131) | GM | 0.00 | $32,113 | $77,000 | $31,250 |
| 0510 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 6.02 | $5,394.99 | $5,100.00 | $6,393.75 |
| 0515 | Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231) | GM | 1.65 | $4,367.37 | $4,100.00 | $2,875.00 |
| 0520 | Itsfm location documentation- intersection (0611-2-1) | EACH | 1 | $3,853.56 | $3,700.00 | $3,750.00 |
| 0525 | Conduit, furnish & install, open trench (0630-2-11) | LF | 169 | $19.27 | $18.00 | $18.75 |
| 0530 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 450 | $51.38 | $49.00 | $50.00 |
| 0535 | Signal cable- new or reconstructed intersection, furnish & install (0632-7-1) | PI | 1 | $12,845 | $12,000 | $12,500 |
| 0540 | Signal cable, remove- intersection (0632-7-6) | PI | 1 | $1,284.52 | $1,200.00 | $1,250.00 |
| 0545 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 18 | $2,016.70 | $1,900.00 | $1,962.50 |
| 0550 | Electrical power service, F&I, underground, meter by contractor (0639-1122) | AS | 1 | $3,853.56 | $3,700.00 | $3,750.00 |
| 0555 | Electrical service wire, & install (0639-2-1) | LF | 26 | $12.85 | $12.00 | $12.50 |
| 0560 | Prestressed concrete pole, type P-II service pole (0641-2-12) | EACH | 1 | $3,236.99 | $3,100.00 | $3,150.00 |
| 0565 | Prestressed concrete pole, complete pole removal- pedestal/service pole (0641-2-60) | EACH | 1 | $642.26 | $610.00 | $625.00 |
| 0570 | Aluminum signals pole, (0646-1-11) | EACH | 7 | $4,881.18 | $4,700.00 | $4,750.00 |
| 0575 | Aluminum signals pole, furnish install pedestrian detector post (0646-1-12) | EACH | 1 | $1,926.78 | $1,800.00 | $1,875.00 |
| 0580 | Aluminum signals pole, remove (0646-1-60) | EACH | 3 | $385.36 | $370.00 | $375.00 |
| 0585 | Vehicular traffic signal, furnish & install aluminum, 3 section, 1 way (0650-1-14) | AS | 10 | $3,082.85 | $2,900.00 | $3,000.00 |
| 0590 | Vehicular traffic signal, furnish & install aluminum, 5 section straight, 1 way (0650-1-18) | AS | 2 | $4,052.66 | $3,900.00 | $3,943.75 |
| 0595 | Vehicular traffic signal, remove- poles to remain (0650-1-60) | AS | 12 | $256.90 | $250.00 | $250.00 |
| 0600 | Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11) | AS | 6 | $1,926.78 | $1,800.00 | $1,875.00 |
| 0605 | Pedestrian signal, furnish & install LED countdown, 2 ways (0653-1-12) | AS | 1 | $3,211.30 | $3,100.00 | $3,125.00 |
| 0610 | Vehicle detection system- furnish & install cabinet equipment (0660-4-11) | EACH | 1 | $68,080 | $65,000 | $66,250 |
| 0615 | Vehicle detection system- furnish & install above ground equipment (0660-4-12) | EACH | 6 | $9,377.02 | $8,900.00 | $9,125.00 |
| 0620 | Pedestrian detector, furnish & install, standard (0665-1-11) | EACH | 9 | $1,027.62 | $980.00 | $1,000.00 |
| 0625 | Traffic controller assembly, F&I, NEMA (0670-5110) | AS | 1 | $69,364 | $66,000 | $67,500 |
| 0630 | Traffic controller assembly, remove controller with (0670-5600) | AS | 1 | $1,284.52 | $1,200.00 | $1,250.00 |
| 0635 | Uninterruptible power supply, furnish and install, online/double conversion with cabinet (0685-1-14) | EACH | 1 | $8,349.39 | $8,000.00 | $8,125.00 |
| 0640 | Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201) | EACH | 2 | $1,091.84 | $1,000.00 | $1,062.00 |