FDOT contract T3967 bid tabulation

SR 292 (SORRENTO RD) FROM CR 293 (BAUER RD) TO CR 292A (GULF. Let by Florida DOT on May 28, 2025, Escambia, District 3. 3 bids received; low bid $6,120,821 by Roads, Inc. of NWF.

Owner
Florida DOT
Letting
28 MAY 2025
Pay items
128
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Roads, Inc. of NWF$6,120,821Low
2C.W. Roberts Contracting, Inc.$7,452,206+22%
3Panhandle Grading & Paving, Inc.$8,194,979+34%
FDOT contract T3967: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Roads, Inc. of NWF2. C.W. Roberts Contracting, Inc.3. Panhandle Grading & Paving, Inc.
0005Mobilization (0101-1)LS1$436,537$370,000$464,500
0010Mobilization (0101-1)LS1$163,709$306,543$155,000
0015Maintenance of traffic (0102-1)DA1$186,551$310,000$325,000
0020Maintenance of traffic (0102-1)DA1$100,000$320,000$130,250
0025Traffic control officer (0102-14)HR56$99.00$80.00$105.00
0030Work zone sign (0102-60)ED15,750$0.45$0.45$0.55
0035Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED23,400$0.23$0.20$0.35
0040Portable changeable message sign, temporary (0102-99)ED928$23.12$22.15$38.50
0045Temporary signalization and maintenance, intersection (0102-104)ED450$12.85$12.25$12.50
0050Temporary traffic detection and maintenance, intersection (0102-107-1)ED450$12.85$12.25$12.50
0055Temporary slope drain / runoff control structure (0104-6)LF135$83.83$59.00$105.00
0060Sediment barrier (0104-10-3)LF28,521$2.58$3.05$7.50
0065Inlet protection system (0104-18)EACH3$260.34$1,000.00$750.00
0070Litter removal (0107-1)ACRE449.82$96.38$120.00$85.00
0075Mowing (0107-2)ACRE449.82$83.53$100.00$85.00
0080Clearing & grubbing (0110-1-1)ACRE1$128,322$45,000$50,000
0085Clearing & grubbing (0110-1-1)ACRE1$100,000$160,000$200,000
0090Removal of existing concrete (0110-4-10)SY441$32.79$51.00$55.00
0095Regular excavation (0120-1)CY2,391.40$26.95$96.00$38.56
0100Borrow excavation, truck measure (0120-2-2)CY2,931.50$33.49$46.00$58.56
0105Type B stabilization (0160-4)SY1,279$45.45$81.00$89.50
0110Optional base, base group 02 (0285-702)SY590$50.17$120.00$89.56
0115Optional base, base group 04 (0285-704)SY15,948$47.70$69.00$31.81
0120Optional base, base group 06 (0285-706)SY856$48.95$98.00$32.02
0125Milling existing asphalt pavement, 1" avg depth (0327-70-1)SY17,911$2.42$3.35$5.10
0130Milling existing asphalt pavement, 3" avg depth (0327-70-4)SY1,592$3.37$4.60$7.25
0135Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6)SY38,500$2.60$3.65$4.60
0140Milling existing asphalt pavement, 4" avg depth (0327-70-7)SY16,458$4.20$5.50$7.40
0145Superpave asphaltic conc, traffic B (0334-1-12)TN33.10$523.70$860.00$400.00
0150Superpave asphaltic concrete, traffic C, PG76-22 (0334-1-53)TN2,311.50$168.49$180.00$248.65
0155Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83)TN9,062.70$186.14$170.00$268.65
0160Miscellaneous asphalt (0339-1)TN45.10$385.14$1,820.00$1,200.00
0165Inlets, DT bot, type D, <10' (0425-1541)EACH2$11,040$17,200$19,795
0170Inlets, DT bot, type H, <10' (0425-1581)EACH2$14,045$21,000$26,860
0175Manholes, P-7, <10' (0425-2-41)EACH1$11,147$12,000$31,459
0180Valve boxes, adjust (0425-6)EACH3$1,075.17$960.00$3,500.00
0185Pipe culvert, optional material, round, 18"SD (0430-174118)LF128$169.38$170.00$205.76
0190Pipe culvert, optional material, round, 24"SD (0430-174124)LF16$600.07$260.00$386.88
0195Pipe culvert, optional material, other shape - ellip/arch, 36"SD (0430-174236)LF77$376.71$710.00$915.20
0200Pipe culvert,optional material,round, 18"S/CD (0430-175118)LF349$124.23$160.00$205.76
0205Pipe culvert,optional material,round, 24"S/CD (0430-175124)LF48$197.98$350.00$386.88
0210Pipe culvert,optional material,other shape-elip/arch, 24"S/CD (0430-175224)LF8$1,080.19$660.00$1,500.00
0215Pipe culvert, opt material, shape - elip/arch, 36"S/CD (0430-175236)LF332$371.12$390.00$815.20
0220Mitered end section, optional round, 24" CD (0430-982129)EACH1$4,157.41$6,700.00$9,850.00
0225Mitered end section, optional round, 18" SD (0430-984125)EACH7$3,530.10$4,100.00$6,758.00
0230Mitered end section, optional round, 24" SD (0430-984129)EACH5$4,157.41$4,500.00$9,850.00
0235Mitered end sect, optional - elliptical / arch, 24" SD (0430-984629)EACH1$6,262.59$10,000$10,500
0240Mitered end sect, optional /ellip/arch, 36" SD (0430-984638)EACH3$11,702$11,000$15,650
0245Mitered end sect, replace slab- construction use (0430-991)EACH4$2,404.81$3,600.00$18,550
0250Concrete sidewalk and driveways, 6" thick (0522-2)SY263$127.10$210.00$175.00
0255Concrete ditch pavement, non reinforced, 4" (0524-1-2)SY126$166.22$310.00$225.00
0260Detectable warnings (0527-2)SF89$29.54$28.00$32.50
0265Riprap, rubble, F&I, ditch lining (0530-3-4)TN12$214.88$940.00$550.00
0270Bedding stone (0530-74)TN8.60$232.18$510.00$550.00
0275Guardrail -roadway, general (0536-1-1)LF697$35.97$34.00$43.75
0280Special guardrail post- post for shallow mount (0536-7-3)EACH3$385.36$370.00$312.50
0285Guardrail removal (0536-73)LF549$8.99$8.60$6.25
0290Guardrail end treatment- parallel approach terminal (0536-85-24)EACH4$4,174.69$4,000.00$5,625.00
0295Performance turf, sod (0570-1-2)SY35,426$3.21$6.10$7.50
0300Raised pavement marker, type B (0706-1-3)EACH1,368$5.14$4.90$6.25
0305Painted pavement markings, standard, white, solid, 6" (0710-11101)GM8.41$1,284.52$1,200.00$1,875.00
0310Painted pavement markings, standard, white, solid for interchange and urban island, (0710-11102)GM0.15$1,284.52$1,200.00$2,000.00
0315Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123)LF813$3.85$3.70$2.63
0320Painted pavement markings, standard, white, solid for diagonal or chevron, 18" (0710-11124)LF378$5.14$4.90$2.75
0325Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125)LF960$6.42$6.15$2.94
0330Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131)GM0.00$6,422.61$15,000$56,250
0335Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141)GM0.47$1,284.52$1,200.00$1,250.00
0340Painted pavement markings, standard, white, message or symbol (0710-11160)EACH13$154.14$150.00$68.75
0345Painted pavement markings, standard, white, arrows (0710-11170)EACH70$83.49$80.00$62.50
0350Painted pavement markings, standard, yellow, solid, 6" (0710-11201)GM6.02$1,284.52$1,200.00$1,875.00
0355Painted pavement markings, standard, yellow, solid for diagonal or chevron, 18" (0710-11224)LF757$5.14$4.90$2.69
0360Painted pavement markings, standard, yellow, skip, 6" (0710-11231)GM1.65$1,284.52$1,200.00$1,312.50
0365Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241)GM0.06$6,422.61$6,000.00$6,250.00
0370Initial contingency amount, DO not bid (0999-25)LS1$34,633$34,633$34,633
0375Initial contingency amount, DO not bid (0999-25)LS1$30,194$30,194$30,194
0380Ground-in rumble strips, 8" sinusoidal (0546-72-3)GM7.42$3,606.46$2,500.00$1,875.00
0385Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH20$578.03$550.00$718.75
0390Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112)EACH1$2,055.23$2,000.00$2,500.00
0395Single column ground sign assembly, remove (0700-1600)EACH19$64.23$61.00$62.50
0400Multi-column ground sign assembly, F&I ground mount, 20.0 SF (0700-2112)EACH2$6,422.61$6,100.00$7,312.50
0405Multi-column ground sign assembly, F&I ground mount, 50.0 SF (0700-2114)EACH1$8,991.66$8,600.00$8,125.00
0410Multi-column ground sign assembly, remove (0700-2600)EACH1$1,541.43$1,500.00$1,250.00
0415Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101)EACH2$340.40$320.00$312.50
0420Sign panel, remove, UP to 12 SF (0700-3601)EACH2$192.68$180.00$62.50
0425Object marker, type 1 (0705-10-1)EACH9$340.40$320.00$250.00
0430Raised pavement marker, type B (0706-1-3)EACH1,368$5.14$4.90$6.25
0435Painted pavement markings, surface (0710-90)LS1$40,213$38,000$56,453
0440Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF813$5.14$4.90$5.31
0445Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124)LF378$6.42$6.15$6.44
0450Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF281$10.28$9.80$7.90
0455Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141)GM0.47$4,367.37$4,200.00$5,032.93
0460Thermoplastic, standard, message or symbol (0711-11160)EACH3$256.90$250.00$312.50
0465Thermoplastic, standard, arrow (0711-11170)EACH60$109.18$100.00$93.75
0470Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224)LF757$6.42$6.15$6.31
0475Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241)GM0.06$4,367.37$4,100.00$18,750
0480Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125)LF679$19.27$18.00$15.00
0485Thermoplastic, preformed, white, message (0711-14160)EACH10$192.68$180.00$187.50
0490Thermoplastic, preformed, white, arrow (0711-14170)EACH10$192.68$180.00$156.25
0495Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM8.41$5,394.99$5,100.00$6,375.00
0500Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102)GM0.15$10,276$9,200.00$8,750.00
0505Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131)GM0.00$32,113$77,000$31,250
0510Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM6.02$5,394.99$5,100.00$6,393.75
0515Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231)GM1.65$4,367.37$4,100.00$2,875.00
0520Itsfm location documentation- intersection (0611-2-1)EACH1$3,853.56$3,700.00$3,750.00
0525Conduit, furnish & install, open trench (0630-2-11)LF169$19.27$18.00$18.75
0530Conduit, furnish & install, directional bore (0630-2-12)LF450$51.38$49.00$50.00
0535Signal cable- new or reconstructed intersection, furnish & install (0632-7-1)PI1$12,845$12,000$12,500
0540Signal cable, remove- intersection (0632-7-6)PI1$1,284.52$1,200.00$1,250.00
0545Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH18$2,016.70$1,900.00$1,962.50
0550Electrical power service, F&I, underground, meter by contractor (0639-1122)AS1$3,853.56$3,700.00$3,750.00
0555Electrical service wire, & install (0639-2-1)LF26$12.85$12.00$12.50
0560Prestressed concrete pole, type P-II service pole (0641-2-12)EACH1$3,236.99$3,100.00$3,150.00
0565Prestressed concrete pole, complete pole removal- pedestal/service pole (0641-2-60)EACH1$642.26$610.00$625.00
0570Aluminum signals pole, (0646-1-11)EACH7$4,881.18$4,700.00$4,750.00
0575Aluminum signals pole, furnish install pedestrian detector post (0646-1-12)EACH1$1,926.78$1,800.00$1,875.00
0580Aluminum signals pole, remove (0646-1-60)EACH3$385.36$370.00$375.00
0585Vehicular traffic signal, furnish & install aluminum, 3 section, 1 way (0650-1-14)AS10$3,082.85$2,900.00$3,000.00
0590Vehicular traffic signal, furnish & install aluminum, 5 section straight, 1 way (0650-1-18)AS2$4,052.66$3,900.00$3,943.75
0595Vehicular traffic signal, remove- poles to remain (0650-1-60)AS12$256.90$250.00$250.00
0600Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11)AS6$1,926.78$1,800.00$1,875.00
0605Pedestrian signal, furnish & install LED countdown, 2 ways (0653-1-12)AS1$3,211.30$3,100.00$3,125.00
0610Vehicle detection system- furnish & install cabinet equipment (0660-4-11)EACH1$68,080$65,000$66,250
0615Vehicle detection system- furnish & install above ground equipment (0660-4-12)EACH6$9,377.02$8,900.00$9,125.00
0620Pedestrian detector, furnish & install, standard (0665-1-11)EACH9$1,027.62$980.00$1,000.00
0625Traffic controller assembly, F&I, NEMA (0670-5110)AS1$69,364$66,000$67,500
0630Traffic controller assembly, remove controller with (0670-5600)AS1$1,284.52$1,200.00$1,250.00
0635Uninterruptible power supply, furnish and install, online/double conversion with cabinet (0685-1-14)EACH1$8,349.39$8,000.00$8,125.00
0640Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201)EACH2$1,091.84$1,000.00$1,062.00
FDOT contract T3967: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of May 28, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy