FDOT contract T4728 bid tabulation

N 22ND AVE (SW 12TH AVE) FROM SHERIDAN ST TO STIRLING RD. Let by Florida DOT on August 27, 2025, Broward, District 4. 6 bids received; low bid $2,926,112 by The Stout Group LLC.

Owner
Florida DOT
Letting
27 AUG 2025
Pay items
66
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1The Stout Group LLC$2,926,112Low
2Weekley Asphalt Paving, Inc.$3,136,623+7.0%
3Florida Engineering & Development Corp$3,250,843+11%
4General Asphalt Company, LLC$3,492,378+19%
5Roadway Construction, LLC$3,596,939+23%
6Jva Engineering Contractor, Inc$3,618,112+24%
FDOT contract T4728: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. The Stout Group LLC2. Weekley Asphalt Paving, Inc.3. Florida Engineering & Development Corp4. General Asphalt Company, LLC5. Roadway Construction, LLC6. Jva Engineering Contractor, Inc
0005Mobilization (0101-1)LS1$210,000$164,100$324,772$400,000$359,693$311,000
0010Maintenance of traffic (0102-1)DA1$210,000$262,000$314,038$465,000$461,874$221,000
0015Commercial material for temporary driveway maintenance (0102-3)CY80$60.00$65.00$159.03$115.00$288.41$32.00
0020Traffic control officer (0102-14)HR28$90.00$98.00$99.19$97.75$75.00$95.00
0025Work zone sign (0102-60)ED29,817$0.19$0.19$0.21$0.22$0.20$0.25
0030Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED12,517$0.12$0.12$0.09$0.14$0.09$0.11
0035Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD10,874$0.05$0.05$0.10$0.06$0.10$0.06
0040Portable changeable message sign, temporary (0102-99)ED860$9.00$9.00$9.27$10.35$9.00$12.70
0045Temporary signalization and maintenance, intersection (0102-104)ED538$36.70$9.22$5.15$5.75$5.00$14.20
0050Temporary traffic detection and maintenance, intersection (0102-107-1)ED538$36.70$9.22$5.15$5.75$5.00$14.20
0055Type III barricade (0102-115)ED336$0.33$0.33$0.26$0.38$0.25$0.30
0060Sediment barrier (0104-10-3)LF8,877$6.00$2.65$3.21$3.45$5.57$4.80
0065Inlet protection system (0104-18)EACH35$150.00$165.00$101.28$201.25$549.13$191.00
0070Monitor existing structures- inspection and settlement monitoring (0108-1)LS1$15,000$29,335$772.50$1.15$2,400.00$5,930.00
0075Clearing & grubbing (0110-1-1)ACRE1$75,000$127,503$137,307$17,250$103,616$16,600
0080Selective clearing and areas with trees to remain (0110-2-2)ACRE0.08$100,000$98,000$297,127$23,000$35,000$23,712
0085Removal of existing concrete (0110-4-10)SY2,478$25.00$39.70$44.88$11.50$23.77$28.50
0090Tree protection barrier (0110-21)LF415$15.00$9.00$8.19$11.50$12.55$3.70
0095Tree root and branch pruning (0110-22)EACH11$650.00$1,800.00$5,150.00$1,725.00$1,000.00$1,420.00
0100Borrow excavation, truck measure (0120-2-2)CY102.40$95.00$39.00$73.47$57.50$0.01$92.15
0105Regular excavation (3-R projects only) (0120-71)LS1$25,000$25,000$22,571$21,735$35,103$34,200
0110Type B stabilization (0160-4)SY242$30.00$20.00$18.83$57.50$61.21$37.50
0115Optional base, base group 15 (0285-715)SY575$125.00$80.00$123.34$198.00$148.67$105.00
0120Milling existing asphalt pavement, 3" avg depth (0327-70-4)SY288$15.00$3.85$4.35$25.40$3.28$7.10
0125Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6)SY20,199$3.50$3.00$4.01$3.35$3.28$4.35
0130Superpave asphaltic conc, traffic B (0334-1-12)TN288.50$230.00$275.00$213.22$295.52$194.00$201.60
0135Asphalt concrete friction course,traffic B, FC-12.5, PG (0337-7-81)TN1,713.90$220.00$200.00$231.96$230.30$226.00$243.70
0140Inlets, DT bot, type C,<10' (0425-1521)EACH2$15,000$9,682.00$8,049.08$10,350$11,132$7,881.50
0145Manhole, adjust, utilities (0425-5-1)EACH3$1,000.00$1,200.00$987.31$1,035.00$935.39$1,232.80
0150Valve boxes, adjust (0425-6)EACH19$900.00$750.00$888.96$862.50$935.45$885.00
0155Meter boxes, adjust (0425-6-1)EACH3$250.00$800.00$1,086.63$862.50$669.53$920.00
0160Pipe culvert,optional material,round, 15"S/CD (0430-175115)LF8$900.00$625.00$287.06$575.00$831.25$713.40
0165Pipe culvert,optional material,round, 18"S/CD (0430-175118)LF30$350.00$365.00$294.25$575.00$435.24$560.00
0170Pipe handrail - guiderail, aluminum (0515-1-2)LF63$110.00$140.00$103.00$115.00$100.00$130.00
0175Concrete curb & gutter, type F (0520-1-10)LF610$35.00$50.90$71.23$80.50$76.32$48.60
0180Concrete curb, type D (0520-2-4)LF3$50.00$160.00$48.50$80.50$216.14$118.00
0185Concrete sidewalk and driveways, 6" thick (0522-2)SY2,967$90.00$69.31$84.98$115.00$161.44$83.60
0190Patterned pavement (0523-3)SY158$250.00$200.00$109.35$93.15$81.00$191.80
0195Detectable warnings (0527-2)SF874$40.00$43.00$40.63$57.50$70.13$44.00
0200Performance turf, sod (0570-1-2)SY7,082$12.00$7.22$7.97$9.19$12.09$12.00
0205Partnering, DO not bid (0999-16)LS1$6,000.00$6,000.00$6,000.00$6,000.00$6,000.00$6,000.00
0210Initial contingency amount, DO not bid (0999-25)LS1$50,000$50,000$50,000$50,000$50,000$50,000
0215Local agency initial amount (DO not bid) (0999-26)LS1$1,122.50$1,122.50$1,122.50$1,122.50$1,122.50$1,122.50
0220Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH44$588.54$595.00$540.75$603.75$525.00$705.00
0225Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112)EACH5$1,845.51$2,850.00$1,699.50$2,070.00$1,650.00$3,378.00
0230Single column ground sign assembly, relocate (0700-1500)EACH12$415.00$550.00$257.50$345.00$250.00$652.00
0235Single column ground sign assembly, remove (0700-1600)EACH26$50.00$10.00$51.50$172.50$50.00$12.00
0240Enhanced highway sign solar powered, relocate - ground mount (0700-142802)EACH1$8,500.00$5,434.00$4,265.44$3,450.00$2,500.00$2,964.00
0245Raised pavement marker, type B (0706-1-3)EACH450$10.00$5.00$4.12$4.60$4.00$5.90
0250Painted pavement markings, surface (0710-90)LS1$20,000$11,900$10,157$11,340$9,861.00$13,788
0255Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF546$7.00$3.00$3.23$3.61$3.14$3.60
0260Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF309$12.00$5.00$6.47$7.22$6.28$9.50
0265Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141)GM0.05$4,500.00$2,300.00$2,317.56$2,587.50$2,000.00$2,720.00
0270Thermoplastic, standard, message or symbol (0711-11160)EACH27$300.00$120.00$109.18$121.90$106.00$142.00
0275Thermoplastic, standard, arrow (0711-11170)EACH14$125.00$80.00$62.83$70.15$61.00$94.80
0280Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224)LF269$10.00$3.00$4.41$4.92$4.28$4.30
0285Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241)GM0.10$4,500.00$6,400.00$2,317.52$2,587.50$2,227.72$7,500.00
0290Thermoplastic, standard, blue, solid,6" (0711-11421)LF165$20.00$6.00$5.37$5.99$5.21$7.10
0295Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125)LF40$30.00$20.00$16.02$17.88$15.55$23.70
0300Thermoplastic, preformed, white, message (0711-14160)EACH39$450.00$260.00$307.97$343.85$299.00$308.00
0305Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM1.71$8,500.00$6,400.00$4,942.97$5,518.85$4,799.00$7,500.00
0310Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM0.98$8,500.00$6,400.00$4,542.30$5,071.50$4,378.40$7,500.00
0315Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231)GM0.60$6,500.00$2,300.00$1,136.10$1,268.45$1,093.73$2,720.00
0320Light pole complete- special design, F&I, single arm shoulder mount, aluminum, 35' (0715-511135)EACH40$21,245$30,174$23,658$25,300$23,125$37,900
0325Light pole complete- special design, remove (0715-550000)EACH3$1,280.00$1,153.00$1,832.06$1,725.00$1,500.00$1,000.00
0330Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH1$1,495.40$1,670.00$2,471.28$2,300.00$2,000.00$3,675.00
FDOT contract T4728: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of August 27, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way