FDOT contract T4728 bid tabulation
N 22ND AVE (SW 12TH AVE) FROM SHERIDAN ST TO STIRLING RD. Let by Florida DOT on August 27, 2025, Broward, District 4. 6 bids received; low bid $2,926,112 by The Stout Group LLC.
- Owner
- Florida DOT
- Letting
- 27 AUG 2025
- Pay items
- 66
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | The Stout Group LLC | $2,926,112 | Low |
| 2 | Weekley Asphalt Paving, Inc. | $3,136,623 | +7.0% |
| 3 | Florida Engineering & Development Corp | $3,250,843 | +11% |
| 4 | General Asphalt Company, LLC | $3,492,378 | +19% |
| 5 | Roadway Construction, LLC | $3,596,939 | +23% |
| 6 | Jva Engineering Contractor, Inc | $3,618,112 | +24% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. The Stout Group LLC | 2. Weekley Asphalt Paving, Inc. | 3. Florida Engineering & Development Corp | 4. General Asphalt Company, LLC | 5. Roadway Construction, LLC | 6. Jva Engineering Contractor, Inc |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $210,000 | $164,100 | $324,772 | $400,000 | $359,693 | $311,000 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $210,000 | $262,000 | $314,038 | $465,000 | $461,874 | $221,000 |
| 0015 | Commercial material for temporary driveway maintenance (0102-3) | CY | 80 | $60.00 | $65.00 | $159.03 | $115.00 | $288.41 | $32.00 |
| 0020 | Traffic control officer (0102-14) | HR | 28 | $90.00 | $98.00 | $99.19 | $97.75 | $75.00 | $95.00 |
| 0025 | Work zone sign (0102-60) | ED | 29,817 | $0.19 | $0.19 | $0.21 | $0.22 | $0.20 | $0.25 |
| 0030 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 12,517 | $0.12 | $0.12 | $0.09 | $0.14 | $0.09 | $0.11 |
| 0035 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 10,874 | $0.05 | $0.05 | $0.10 | $0.06 | $0.10 | $0.06 |
| 0040 | Portable changeable message sign, temporary (0102-99) | ED | 860 | $9.00 | $9.00 | $9.27 | $10.35 | $9.00 | $12.70 |
| 0045 | Temporary signalization and maintenance, intersection (0102-104) | ED | 538 | $36.70 | $9.22 | $5.15 | $5.75 | $5.00 | $14.20 |
| 0050 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 538 | $36.70 | $9.22 | $5.15 | $5.75 | $5.00 | $14.20 |
| 0055 | Type III barricade (0102-115) | ED | 336 | $0.33 | $0.33 | $0.26 | $0.38 | $0.25 | $0.30 |
| 0060 | Sediment barrier (0104-10-3) | LF | 8,877 | $6.00 | $2.65 | $3.21 | $3.45 | $5.57 | $4.80 |
| 0065 | Inlet protection system (0104-18) | EACH | 35 | $150.00 | $165.00 | $101.28 | $201.25 | $549.13 | $191.00 |
| 0070 | Monitor existing structures- inspection and settlement monitoring (0108-1) | LS | 1 | $15,000 | $29,335 | $772.50 | $1.15 | $2,400.00 | $5,930.00 |
| 0075 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $75,000 | $127,503 | $137,307 | $17,250 | $103,616 | $16,600 |
| 0080 | Selective clearing and areas with trees to remain (0110-2-2) | ACRE | 0.08 | $100,000 | $98,000 | $297,127 | $23,000 | $35,000 | $23,712 |
| 0085 | Removal of existing concrete (0110-4-10) | SY | 2,478 | $25.00 | $39.70 | $44.88 | $11.50 | $23.77 | $28.50 |
| 0090 | Tree protection barrier (0110-21) | LF | 415 | $15.00 | $9.00 | $8.19 | $11.50 | $12.55 | $3.70 |
| 0095 | Tree root and branch pruning (0110-22) | EACH | 11 | $650.00 | $1,800.00 | $5,150.00 | $1,725.00 | $1,000.00 | $1,420.00 |
| 0100 | Borrow excavation, truck measure (0120-2-2) | CY | 102.40 | $95.00 | $39.00 | $73.47 | $57.50 | $0.01 | $92.15 |
| 0105 | Regular excavation (3-R projects only) (0120-71) | LS | 1 | $25,000 | $25,000 | $22,571 | $21,735 | $35,103 | $34,200 |
| 0110 | Type B stabilization (0160-4) | SY | 242 | $30.00 | $20.00 | $18.83 | $57.50 | $61.21 | $37.50 |
| 0115 | Optional base, base group 15 (0285-715) | SY | 575 | $125.00 | $80.00 | $123.34 | $198.00 | $148.67 | $105.00 |
| 0120 | Milling existing asphalt pavement, 3" avg depth (0327-70-4) | SY | 288 | $15.00 | $3.85 | $4.35 | $25.40 | $3.28 | $7.10 |
| 0125 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 20,199 | $3.50 | $3.00 | $4.01 | $3.35 | $3.28 | $4.35 |
| 0130 | Superpave asphaltic conc, traffic B (0334-1-12) | TN | 288.50 | $230.00 | $275.00 | $213.22 | $295.52 | $194.00 | $201.60 |
| 0135 | Asphalt concrete friction course,traffic B, FC-12.5, PG (0337-7-81) | TN | 1,713.90 | $220.00 | $200.00 | $231.96 | $230.30 | $226.00 | $243.70 |
| 0140 | Inlets, DT bot, type C,<10' (0425-1521) | EACH | 2 | $15,000 | $9,682.00 | $8,049.08 | $10,350 | $11,132 | $7,881.50 |
| 0145 | Manhole, adjust, utilities (0425-5-1) | EACH | 3 | $1,000.00 | $1,200.00 | $987.31 | $1,035.00 | $935.39 | $1,232.80 |
| 0150 | Valve boxes, adjust (0425-6) | EACH | 19 | $900.00 | $750.00 | $888.96 | $862.50 | $935.45 | $885.00 |
| 0155 | Meter boxes, adjust (0425-6-1) | EACH | 3 | $250.00 | $800.00 | $1,086.63 | $862.50 | $669.53 | $920.00 |
| 0160 | Pipe culvert,optional material,round, 15"S/CD (0430-175115) | LF | 8 | $900.00 | $625.00 | $287.06 | $575.00 | $831.25 | $713.40 |
| 0165 | Pipe culvert,optional material,round, 18"S/CD (0430-175118) | LF | 30 | $350.00 | $365.00 | $294.25 | $575.00 | $435.24 | $560.00 |
| 0170 | Pipe handrail - guiderail, aluminum (0515-1-2) | LF | 63 | $110.00 | $140.00 | $103.00 | $115.00 | $100.00 | $130.00 |
| 0175 | Concrete curb & gutter, type F (0520-1-10) | LF | 610 | $35.00 | $50.90 | $71.23 | $80.50 | $76.32 | $48.60 |
| 0180 | Concrete curb, type D (0520-2-4) | LF | 3 | $50.00 | $160.00 | $48.50 | $80.50 | $216.14 | $118.00 |
| 0185 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 2,967 | $90.00 | $69.31 | $84.98 | $115.00 | $161.44 | $83.60 |
| 0190 | Patterned pavement (0523-3) | SY | 158 | $250.00 | $200.00 | $109.35 | $93.15 | $81.00 | $191.80 |
| 0195 | Detectable warnings (0527-2) | SF | 874 | $40.00 | $43.00 | $40.63 | $57.50 | $70.13 | $44.00 |
| 0200 | Performance turf, sod (0570-1-2) | SY | 7,082 | $12.00 | $7.22 | $7.97 | $9.19 | $12.09 | $12.00 |
| 0205 | Partnering, DO not bid (0999-16) | LS | 1 | $6,000.00 | $6,000.00 | $6,000.00 | $6,000.00 | $6,000.00 | $6,000.00 |
| 0210 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 |
| 0215 | Local agency initial amount (DO not bid) (0999-26) | LS | 1 | $1,122.50 | $1,122.50 | $1,122.50 | $1,122.50 | $1,122.50 | $1,122.50 |
| 0220 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 44 | $588.54 | $595.00 | $540.75 | $603.75 | $525.00 | $705.00 |
| 0225 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 5 | $1,845.51 | $2,850.00 | $1,699.50 | $2,070.00 | $1,650.00 | $3,378.00 |
| 0230 | Single column ground sign assembly, relocate (0700-1500) | EACH | 12 | $415.00 | $550.00 | $257.50 | $345.00 | $250.00 | $652.00 |
| 0235 | Single column ground sign assembly, remove (0700-1600) | EACH | 26 | $50.00 | $10.00 | $51.50 | $172.50 | $50.00 | $12.00 |
| 0240 | Enhanced highway sign solar powered, relocate - ground mount (0700-142802) | EACH | 1 | $8,500.00 | $5,434.00 | $4,265.44 | $3,450.00 | $2,500.00 | $2,964.00 |
| 0245 | Raised pavement marker, type B (0706-1-3) | EACH | 450 | $10.00 | $5.00 | $4.12 | $4.60 | $4.00 | $5.90 |
| 0250 | Painted pavement markings, surface (0710-90) | LS | 1 | $20,000 | $11,900 | $10,157 | $11,340 | $9,861.00 | $13,788 |
| 0255 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 546 | $7.00 | $3.00 | $3.23 | $3.61 | $3.14 | $3.60 |
| 0260 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 309 | $12.00 | $5.00 | $6.47 | $7.22 | $6.28 | $9.50 |
| 0265 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 0.05 | $4,500.00 | $2,300.00 | $2,317.56 | $2,587.50 | $2,000.00 | $2,720.00 |
| 0270 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 27 | $300.00 | $120.00 | $109.18 | $121.90 | $106.00 | $142.00 |
| 0275 | Thermoplastic, standard, arrow (0711-11170) | EACH | 14 | $125.00 | $80.00 | $62.83 | $70.15 | $61.00 | $94.80 |
| 0280 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 269 | $10.00 | $3.00 | $4.41 | $4.92 | $4.28 | $4.30 |
| 0285 | Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241) | GM | 0.10 | $4,500.00 | $6,400.00 | $2,317.52 | $2,587.50 | $2,227.72 | $7,500.00 |
| 0290 | Thermoplastic, standard, blue, solid,6" (0711-11421) | LF | 165 | $20.00 | $6.00 | $5.37 | $5.99 | $5.21 | $7.10 |
| 0295 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 40 | $30.00 | $20.00 | $16.02 | $17.88 | $15.55 | $23.70 |
| 0300 | Thermoplastic, preformed, white, message (0711-14160) | EACH | 39 | $450.00 | $260.00 | $307.97 | $343.85 | $299.00 | $308.00 |
| 0305 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 1.71 | $8,500.00 | $6,400.00 | $4,942.97 | $5,518.85 | $4,799.00 | $7,500.00 |
| 0310 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 0.98 | $8,500.00 | $6,400.00 | $4,542.30 | $5,071.50 | $4,378.40 | $7,500.00 |
| 0315 | Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231) | GM | 0.60 | $6,500.00 | $2,300.00 | $1,136.10 | $1,268.45 | $1,093.73 | $2,720.00 |
| 0320 | Light pole complete- special design, F&I, single arm shoulder mount, aluminum, 35' (0715-511135) | EACH | 40 | $21,245 | $30,174 | $23,658 | $25,300 | $23,125 | $37,900 |
| 0325 | Light pole complete- special design, remove (0715-550000) | EACH | 3 | $1,280.00 | $1,153.00 | $1,832.06 | $1,725.00 | $1,500.00 | $1,000.00 |
| 0330 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 1 | $1,495.40 | $1,670.00 | $2,471.28 | $2,300.00 | $2,000.00 | $3,675.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of August 27, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way