FDOT contract T4741 bid tabulation

SR 814 (ATLANTIC BLVD) AT LYONS RD. Let by Florida DOT on September 24, 2025, Broward, District 4. 5 bids received; low bid $1,013,087 by Jva Engineering Contractor, Inc.

Owner
Florida DOT
Letting
24 SEP 2025
Pay items
58
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Jva Engineering Contractor, Inc$1,013,087Low
2Weekley Asphalt Paving, Inc.$1,053,257+4.0%
3Florida Engineering & Development Corp$1,103,721+9.0%
4R & D Paving LLC$1,146,946+13%
5General Asphalt Company, LLC$1,242,838+23%
FDOT contract T4741: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Jva Engineering Contractor, Inc2. Weekley Asphalt Paving, Inc.3. Florida Engineering & Development Corp4. R & D Paving LLC5. General Asphalt Company, LLC
0005Mobilization (0101-1)LS1$120,000$71,240$96,103$110,000$100,000
0010Maintenance of traffic (0102-1)DA1$120,000$177,570$91,512$77,700$275,000
0015Work zone sign (0102-60)ED5,453$0.27$0.23$0.21$0.25$0.23
0020Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED19,950$0.13$0.11$0.10$0.15$0.11
0025Arrow board / advance warning arrow panel (0102-76)ED266$6.60$6.00$4.46$6.60$4.80
0030Portable changeable message sign, temporary (0102-99)ED294$11.90$12.00$10.04$13.20$10.80
0035Sediment barrier (0104-10-3)LF2,743$4.45$2.70$3.12$2.85$3.60
0040Inlet protection system (0104-18)EACH12$210.00$165.00$103.04$315.00$198.00
0045Clearing & grubbing (0110-1-1)ACRE1$12,390$56,840$41,397$70,000$18,240
0050Removal of existing concrete (0110-4-10)SY470$57.15$39.00$49.13$47.90$29.40
0055Tree protection barrier (0110-21)LF60$6.05$17.00$7.71$3.85$9.60
0060Tree root and branch pruning (0110-22)EACH2$3,000.00$1,667.00$5,575.00$5,500.00$1,800.00
0065Regular excavation (0120-1)CY616$33.45$40.00$75.68$46.00$78.00
0070Embankment (0120-6)CY0.60$371.70$500.00$317.90$8,750.00$1,200.00
0075Type B stabilization (0160-4)SY780$17.95$20.00$15.50$31.80$6.00
0080Optional base, base group 11 (0285-711)SY780$44.60$43.00$36.74$58.00$62.40
0085Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6)SY2,189$7.00$3.50$8.59$5.70$7.61
0090Superpave asphaltic conc, traffic C (0334-1-13)TN323.10$214.00$250.00$257.75$240.00$239.19
0095Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83)TN284.30$290.00$265.00$233.58$257.00$294.27
0100Inlets, curb, type P-2, <10' (0425-1321)EACH1$12,700$17,210$12,697$16,500$18,976
0105Inlets, curb, type P-5, modify (0425-1359)EACH1$10,000$8,940.00$12,995$11,550$11,819
0110Inlets, curb, type 8, <10' (0425-1481)EACH1$11,300$12,000$10,737$8,250.00$9,000.00
0115Manholes, P-7, <10' (0425-2-41)EACH1$8,800.00$12,000$10,140$7,700.00$9,000.00
0120Manhole, adjust (0425-5)EACH1$1,100.00$1,200.00$1,985.96$935.00$1,020.00
0125Pipe culvert,optional material,round, 15"S/CD (0430-175115)LF5$545.00$510.00$624.07$715.00$768.00
0130Pipe culvert,optional material,round, 18"S/CD (0430-175118)LF148$167.00$233.00$138.63$192.50$195.60
0135Pipe culvert, opt material, round, 30"S/CD (0430-175130)LF49$300.00$615.00$884.87$522.50$600.00
0140Concrete curb & gutter, type F (0520-1-10)LF534$84.00$53.74$61.41$75.00$53.70
0145Traffic separator concrete- type I, 4' wide (0520-5-11)LF247$57.50$84.73$111.91$74.00$78.00
0150Concrete sidewalk and driveways, 4" thick (0522-1)SY168$95.70$84.73$85.94$116.15$52.80
0155Performance turf, sod (0570-1-2)SY331$13.20$6.50$11.10$25.50$19.20
0160Irrigation system- modify existing system (0590-70-5)LS1$14,800$33,350$22,322$22,022$48,000
0165Initial contingency amount, DO not bid (0999-25)LS1$48,941$48,941$48,941$48,941$48,941
0170Prestressed concrete pole, complete pole removal- pole 30' and greater (0641-2-80)EACH2$4,330.00$16,120$6,831.81$7,000.00$3,600.00
0175Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH4$737.00$595.00$663.43$1,100.00$600.00
0180Single column ground sign assembly, remove (0700-1600)EACH3$12.40$10.00$11.15$82.50$180.00
0185Sign panel, remove, UP to 12 SF (0700-3601)EACH5$87.00$70.00$78.05$82.50$180.00
0190Raised pavement marker, type B (0706-1-3)EACH76$6.20$5.00$5.58$7.70$4.80
0195Painted pavement markings, surface (0710-90)LS1$3,600.00$2,905.00$6,806.07$5,500.00$1,800.00
0200Thermoplastic, standard, solid, 8" for interchange and urban island (0711-11102)GM0.05$8,180.00$6,600.00$7,358.89$10,450$2,760.00
0205Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141)GM0.09$2,850.00$2,300.00$2,564.53$4,950.00$1,140.00
0210Thermoplastic, preformed, white, message (0711-14160)EACH1$322.00$200.00$289.90$330.00$420.00
0215Thermoplastic, preformed, white, arrow (0711-14170)EACH10$185.00$150.00$167.25$770.00$420.00
0220Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM0.34$7,850.00$6,400.00$7,064.66$9,350.00$5,202.00
0225Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131)GM0.29$2,850.00$2,300.00$2,564.50$4,950.00$1,320.00
0230Thermoplastic, standard other surfaces, white, 6", 6-10 dotted managed lane marking (0711-16171)GM0.02$2,850.00$2,300.00$2,564.71$4,950.00$1,320.00
0235Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM0.12$7,850.00$6,400.00$7,064.53$9,350.00$5,202.00
0240Conduit, furnish & install, open trench (0630-2-11)LF778$24.80$19.00$22.48$22.20$28.80
0245Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH6$2,040.00$1,400.00$1,933.42$1,908.00$2,160.00
0250Electrical power service, F&I, underground, meter by contractor (0639-1122)AS1$8,670.00$5,375.00$7,421.72$7,322.00$6,480.00
0255Electrical service wire, & install (0639-2-1)LF13$16.10$12.00$17.35$17.15$12.00
0260Prestressed concrete pole, type P-II service pole (0641-2-12)EACH1$2,600.00$1,700.00$4,647.19$4,585.00$3,420.00
0265Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12)LF2,800$3.70$2.00$4.19$4.15$9.60
0270Luminaire, F&I- replace existing luminaire on existing pole/arm, roadway, cobra head (0715-11211)EACH37$2,230.00$1,245.00$1,546.24$1,526.00$1,710.00
0275Light pole complete, F&I, standard pole standard foundation, 40' mounting height, 8' arm length (0715-61311)EACH5$10,530$10,200$13,636$13,453$14,700
0280Pole cable distribution system, furnish and install, conventional (0715-500-1)EACH5$930.00$675.00$1,216.42$1,201.00$1,260.00
0285Relocate trees and palms, less than or equal to 3.0" DBH (0581-1300)EACH3$3,700.00$1,667.00$13,938$13,750$1,800.00
0290Relocate trees and palms, 16.1" or greater DBH (0581-1360)EACH1$9,900.00$16,700$44,600$44,000$18,000
FDOT contract T4741: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of September 24, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy