| 0005 | Removal of existing structures/bridges 44754415201- 860537 (0110-3) | SF | 1 | $65,000 | $25,535 | $123,000 |
| 0010 | Concrete for joint repair (0400-32) | CY | 7 | $12,500 | $3,720.81 | $24,450 |
| 0015 | Cleaning & coating concrete surface, class 5 (0400-143) | SF | 93 | $5.00 | $62.01 | $23.00 |
| 0020 | Restore spalled areas, contractors option (0401-70-5) | CF | 3.40 | $1,879.27 | $2,243.43 | $2,250.00 |
| 0025 | Epoxy concrete overlay for concrete bridge decks (0403-1100) | SY | 1,986 | $199.70 | $256.22 | $289.00 |
| 0030 | Bridge deck expansion joint, rehabilitation, strip seal (0458-1-22) | LF | 82 | $700.00 | $2,991.24 | $1,350.00 |
| 0035 | Mobilization (0101-1) | LS | 1 | $193,000 | $246,690 | $119,800 |
| 0040 | Maintenance of traffic (0102-1) | DA | 1 | $246,934 | $204,333 | $313,333 |
| 0045 | Traffic control officer (0102-14) | HR | 556 | $85.00 | $97.58 | $95.00 |
| 0050 | Work zone sign (0102-60) | ED | 1,548 | $0.47 | $0.27 | $0.22 |
| 0055 | Temporary barrier, F&I, anchored (0102-71-15) | LF | 425 | $51.97 | $19.07 | $50.46 |
| 0060 | Temporary guardrail (0102-73) | LF | 50 | $38.46 | $18.24 | $34.00 |
| 0065 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 9,403 | $0.14 | $0.15 | $0.12 |
| 0070 | Arrow board / advance warning arrow panel (0102-76) | ED | 129 | $6.29 | $6.69 | $5.50 |
| 0075 | Temporary crash cushion, redirective option (0102-89-1) | LO | 1 | $967.10 | $1,027.48 | $4,500.00 |
| 0080 | Portable changeable message sign, temporary (0102-99) | ED | 143 | $0.08 | $12.16 | $10.00 |
| 0085 | Type III barricade (0102-115) | ED | 258 | $0.52 | $0.55 | $0.50 |
| 0090 | Removable tape, white, solid 6" (0102-913-21) | GM | 0.26 | $16,595 | $11,552 | $10,950 |
| 0095 | Removable tape, white, 10'-30', 6'-10', or 2'-4' skip, 6" wide (0102-913-22) | GM | 0.27 | $5,150.25 | $8,025.30 | $2,750.00 |
| 0100 | Removable tape, yellow, solid, (0102-913-31) | GM | 0.27 | $16,595 | $11,552 | $10,650 |
| 0105 | Sediment barrier (0104-10-3) | LF | 346 | $3.44 | $4.91 | $3.50 |
| 0110 | Inlet protection system (0104-18) | EACH | 13 | $115.75 | $155.13 | $220.00 |
| 0115 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $50,000 | $2,711.58 | $29,900 |
| 0120 | Tree root and branch pruning (0110-22) | EACH | 14 | $650.00 | $2,000.00 | $3,600.00 |
| 0125 | Borrow excavation, truck measure (0120-2-2) | CY | 150.60 | $85.00 | $87.66 | $90.00 |
| 0130 | Milling existing asphalt pavement, 2 1/4" avg depth (0327-70-11) | SY | 2,802 | $6.17 | $6.69 | $6.00 |
| 0135 | Milling existing asphalt pavement, 3/4" avg depth (0327-70-19) | SY | 102 | $102.19 | $6.69 | $20.00 |
| 0140 | Superpave asphaltic concrete, traffic E, PG76-22 (0334-1-55) | TN | 231.20 | $413.74 | $303.99 | $300.00 |
| 0145 | Asphalt concrete friction course, inc bit, FC-5, PG 76-22 (0337-7-25) | TN | 115.90 | $515.03 | $303.99 | $325.00 |
| 0150 | Miscellaneous asphalt (0339-1) | TN | 24.40 | $515.03 | $369.14 | $650.00 |
| 0155 | Guardrail -roadway, general (0536-1-1) | LF | 350 | $33.10 | $33.74 | $29.00 |
| 0160 | Guardrail transition to rigid barrier, F&I- index 536- 002, approach TL-3 (0536-8122) | EACH | 1 | $4,470.53 | $3,780.83 | $3,950.00 |
| 0165 | Guardrail removal (0536-73) | LF | 105 | $5.72 | $3.65 | $5.00 |
| 0170 | Guardrail end treatment- parallel approach terminal (0536-85-24) | EACH | 1 | $3,705.89 | $4,001.63 | $3,300.00 |
| 0175 | Performance turf, sod (0570-1-2) | SY | 347 | $5.95 | $12.29 | $15.00 |
| 0180 | Raised pavement marker, type B (0706-1-3) | EACH | 615 | $6.87 | $6.08 | $4.00 |
| 0185 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 0.39 | $7,439.25 | $1,945.54 | $1,200.00 |
| 0190 | Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131) | GM | 0.36 | $6,867.00 | $1,215.94 | $750.00 |
| 0195 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 0.39 | $6,867.00 | $1,945.54 | $1,200.00 |
| 0200 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $50,000 | $50,000 | $50,000 |
| 0205 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 2 | $2,060.10 | $2,675.10 | $3,000.00 |
| 0210 | Single column ground sign assembly, F&I barrier 12.0-20.0 SF (0700-1312) | EACH | 9 | $3,891.30 | $2,918.28 | $5,500.00 |
| 0215 | Sign panel, furnish & install ground mount, 12-20 SF (0700-3102) | EACH | 1 | $1,716.75 | $249.27 | $900.00 |
| 0220 | Sign panel, remove, 12-20 SF (0700-3602) | EACH | 1 | $1,602.30 | $42.56 | $450.00 |
| 0225 | Delineator, flexible tubular (0705-11-1) | EACH | 14 | $120.17 | $109.44 | $130.00 |
| 0230 | Raised pavement marker, type B (0706-1-3) | EACH | 228 | $6.87 | $6.08 | $4.00 |
| 0235 | Painted pavement markings, surface (0710-90) | LS | 1 | $28,613 | $4,863.81 | $2,192.40 |
| 0240 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 85 | $6.29 | $6.08 | $3.33 |
| 0245 | Thermoplastic, standard-open graded asphalt surfaces solid, 6" (0711-15101) | GM | 0.33 | $6,867.00 | $7,903.69 | $4,335.00 |
| 0250 | Thermoplastic, standard-open graded asphalt surfaces, skip, 6",10-30 skip or 3-9 lane (0711-15131) | GM | 0.33 | $3,433.50 | $5,471.80 | $3,400.00 |
| 0255 | Thermoplastic, standard-open graded asphalt surfaces, yellow, solid, 6" (0711-15201) | GM | 0.33 | $6,867.00 | $7,903.67 | $4,335.00 |
| 0260 | Thermoplastic, remove existing thermoplastic pavement markings- surface to remain (0711-17-1) | SF | 127 | $4.58 | $27.77 | $4.20 |
| 0265 | Conduit, furnish & install, open trench (0630-2-11) | LF | 463 | $18.31 | $19.46 | $16.00 |
| 0270 | Conduit, furnish & install, mount (0630-2-15) | LF | 1,206 | $42.35 | $44.99 | $37.00 |
| 0275 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 5 | $1,794.26 | $1,906.27 | $1,567.72 |
| 0280 | Junction box, furnish & install, mounted (0635-3-12) | EACH | 14 | $1,220.05 | $1,296.22 | $1,066.01 |
| 0285 | Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12) | LF | 3,202 | $3.59 | $3.82 | $3.14 |
| 0290 | Lighting conductors, F&I, insulated, no 4 to no 2 (0715-1-13) | LF | 3,000 | $5.44 | $5.78 | $4.75 |
| 0295 | Lighting conductors, remove & dispose, contractor owns (0715-1-60) | LF | 1,353 | $0.48 | $0.51 | $0.42 |
| 0300 | Luminaire, F&I- replace existing luminaire on existing pole/arm, roadway, cobra head (0715-11211) | EACH | 3 | $1,928.28 | $2,048.66 | $1,684.82 |
| 0305 | Lighting-special, light pole comp, F&I, standard pole , 40' mount HGT, 12' arm LGT W/attach BRCK hrdwe bridge mount (0715-52-46) | EACH | 7 | $20,067 | $15,384 | $17,534 |
| 0310 | Light pole complete, F&I, standard pole standard foundation, 40' mounting height, 12' arm length (0715-61342) | EACH | 4 | $12,269 | $13,035 | $10,720 |
| 0315 | Pole cable distribution system, furnish and install, conventional (0715-500-1) | EACH | 5 | $1,088.63 | $1,156.59 | $951.18 |
| 0320 | Pole cable distribution system, wall mount (0715-500-3) | EACH | 10 | $1,088.63 | $1,156.59 | $951.18 |
| 0325 | Fiber optic cable locator (0633-6) | DA | 129 | $259.16 | $275.34 | $226.44 |