FDOT contract T7574 bid tabulation
SR 93 (I-75), 93A (I-275) and SR 400 (I-4) FROM MANATEE/PI.. Let by Florida DOT on July 30, 2025, Hillsborough,, District 7. 6 bids received; low bid $4,370,000 by Traffic Management Solutions, LLC.
- Owner
- Florida DOT
- Letting
- 30 JUL 2025
- Pay items
- 68
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Traffic Management Solutions, LLC | $4,370,000 | Low |
| 2 | Sice Inc | $4,701,504 | +8.0% |
| 3 | Transportation Systems Inc. | $4,900,042 | +12% |
| 4 | Chinchor Electric Inc. | $5,082,251 | +16% |
| 5 | Traffic Control Devices, Inc. | $5,127,127 | +17% |
| 6 | Sun Civil LLC | $5,779,441 | +32% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Traffic Management Solutions, LLC | 2. Sice Inc | 3. Transportation Systems Inc. | 4. Chinchor Electric Inc. | 5. Traffic Control Devices, Inc. | 6. Sun Civil LLC |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $132,713 | $157,387 | $25,000 | $126,608 | $125,000 | $193,268 |
| 0010 | Mobilization (0101-1) | LS | 1 | $44,292 | $78,693 | $125,000 | $125,003 | $60,500 | $107,668 |
| 0015 | Mobilization (0101-1) | LS | 1 | $181,195 | $183,618 | $75,000 | $125,819 | $113,300 | $187,486 |
| 0020 | Mobilization (0101-1) | LS | 1 | $44,292 | $52,462 | $25,000 | $125,819 | $50,500 | $68,674 |
| 0025 | Maintenance of traffic (0102-1) | DA | 1 | $87,713 | $42,780 | $20,000 | $76,948 | $44,835 | $95,428 |
| 0030 | Maintenance of traffic (0102-1) | DA | 1 | $29,238 | $29,763 | $75,000 | $76,948 | $25,900 | $47,714 |
| 0035 | Maintenance of traffic (0102-1) | DA | 1 | $119,608 | $58,927 | $35,000 | $76,948 | $59,930 | $111,566 |
| 0040 | Maintenance of traffic (0102-1) | DA | 1 | $29,238 | $16,089 | $20,000 | $76,948 | $9,701.20 | $30,878 |
| 0045 | Traffic control officer (0102-14) | HR | 296 | $112.52 | $115.93 | $103.00 | $123.05 | $157.00 | $111.02 |
| 0050 | Work zone sign (0102-60) | ED | 1,204 | $0.67 | $1.08 | $0.60 | $0.54 | $1.00 | $0.37 |
| 0055 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 889 | $0.12 | $0.58 | $0.50 | $0.10 | $0.20 | $0.20 |
| 0060 | Arrow board / advance warning arrow panel (0102-76) | ED | 7 | $20.15 | $57.97 | $22.00 | $16.05 | $26.00 | $19.59 |
| 0065 | Portable changeable message sign, temporary (0102-99) | ED | 160 | $33.59 | $57.97 | $22.00 | $26.75 | $48.00 | $19.59 |
| 0070 | Existing ITS maintenance (0102-112) | DA | 290 | $310.51 | $106.00 | $475.00 | $294.25 | $237.00 | $236.46 |
| 0075 | Type III barricade (0102-115) | ED | 130 | $0.67 | $1.35 | $0.70 | $0.54 | $1.00 | $0.46 |
| 0080 | Removal of existing concrete (0110-4-10) | SY | 85 | $201.53 | $154.58 | $140.00 | $187.25 | $106.00 | $55.80 |
| 0085 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 85 | $235.11 | $257.63 | $460.00 | $518.95 | $335.00 | $210.40 |
| 0090 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $14,000 | $14,000 | $14,000 | $14,000 | $14,000 | $14,000 |
| 0095 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $15,000 | $15,000 | $15,000 | $15,000 | $15,000 | $15,000 |
| 0100 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $15,000 | $15,000 | $15,000 | $15,000 | $15,000 | $15,000 |
| 0105 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $8,000.00 | $8,000.00 | $8,000.00 | $8,000.00 | $8,000.00 | $8,000.00 |
| 0110 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 17 | $932.21 | $1,118.44 | $995.00 | $615.25 | $724.00 | $979.62 |
| 0115 | Single column ground sign assembly, F&I barrier less than 12 SF (0700-1311) | EACH | 5 | $1,749.06 | $6,807.91 | $4,525.00 | $3,132.45 | $3,930.00 | $4,571.58 |
| 0120 | Single column ground sign assembly, relocate (0700-1500) | EACH | 22 | $1,547.10 | $243.14 | $675.00 | $476.15 | $157.00 | $653.08 |
| 0125 | Single column ground sign assembly, remove (0700-1600) | EACH | 13 | $155.89 | $126.43 | $215.00 | $42.80 | $82.00 | $130.62 |
| 0130 | Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101) | EACH | 1 | $383.10 | $612.71 | $2,220.00 | $343.74 | $396.00 | $587.77 |
| 0135 | Sign panel, remove, UP to 12 SF (0700-3601) | EACH | 3 | $91.90 | $97.26 | $660.00 | $101.65 | $63.00 | $130.62 |
| 0140 | Retroreflective sign strip- furnish and install, 2' (0700-13-12) | EACH | 22 | $94.52 | $136.16 | $175.00 | $101.65 | $88.00 | $163.27 |
| 0145 | Retroreflective sign strip- furnish and install, 5' (0700-13-15) | EACH | 60 | $147.17 | $194.51 | $200.00 | $160.50 | $126.00 | $228.58 |
| 0150 | Enhanced highway sign AC powered, F&I ground mount, highlighted sign <12 SF (0700-141140) | EACH | 58 | $5,672.95 | $8,977.06 | $8,000.00 | $7,164.55 | $7,495.00 | $9,980.51 |
| 0155 | Enhanced highway sign AC powered, F&I overhead highlighted sign <12 SF (0700-141340) | EACH | 2 | $3,606.87 | $8,772.99 | $5,000.00 | $6,592.10 | $2,915.00 | $8,281.57 |
| 0160 | Enhanced highway sign AC powered, F&I barrier side mount, highlighted sign <12 SF (0700-141440) | EACH | 3 | $5,862.77 | $8,840.42 | $7,000.00 | $9,415.42 | $14,090 | $13,920 |
| 0165 | Enhanced highway sign solar powered, F&I ground mount, highlighted sign <12 SF (0700-142140) | EACH | 2 | $6,228.53 | $9,245.33 | $7,500.00 | $11,081 | $7,493.00 | $10,172 |
| 0170 | Raised pavement marker, type B (0706-1-3) | EACH | 646 | $13.43 | $23.70 | $15.00 | $10.70 | $12.60 | $13.06 |
| 0175 | Thermoplastic, standard, arrow (0711-11170) | EACH | 24 | $503.81 | $888.83 | $300.00 | $401.25 | $471.00 | $261.23 |
| 0180 | Thermoplastic, preformed, white with black contrast, arrow on concrete surface (0711-14570) | EACH | 12 | $2,015.23 | $3,555.31 | $1,935.00 | $1,605.00 | $1,885.00 | $1,959.25 |
| 0185 | Thermoplastic, remove existing thermoplastic pavement markings- surface to remain (0711-17-1) | SF | 689 | $13.44 | $23.70 | $65.00 | $10.70 | $12.60 | $65.31 |
| 0190 | Itsfm subsurface documentation- project length (0611-1-1) | MI | 4.10 | $3,828.94 | $3,832.78 | $4,400.00 | $3,049.50 | $3,585.00 | $3,720.76 |
| 0195 | Itsfm location documentation- ITS site (0611-2-2) | EACH | 18 | $2,451.86 | $2,454.32 | $2,340.00 | $1,952.75 | $2,331.00 | $2,383.75 |
| 0200 | Conduit, furnish & install, open trench (0630-2-11) | LF | 16,430 | $14.02 | $16.28 | $20.00 | $16.62 | $27.60 | $29.77 |
| 0205 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 10,272 | $34.25 | $27.59 | $30.00 | $27.32 | $37.65 | $35.12 |
| 0210 | Conduit, furnish & install, aboveground (0630-2-14) | LF | 620 | $44.11 | $64.41 | $54.00 | $51.13 | $46.60 | $61.13 |
| 0215 | Conduit, furnish & install, mount (0630-2-15) | LF | 3,582 | $45.16 | $82.33 | $50.00 | $60.24 | $47.10 | $84.32 |
| 0220 | Fiber optic cable, F&I, underground,2-12 fibers (0633-1121) | LF | 24,085 | $5.04 | $3.75 | $4.50 | $4.58 | $4.70 | $4.90 |
| 0225 | Fiber optic connection, install, splice (0633-2-31) | EACH | 52 | $60.46 | $60.52 | $60.00 | $48.15 | $57.00 | $58.78 |
| 0230 | Fiber optic connection, install, termination (0633-2-32) | EACH | 204 | $114.20 | $114.31 | $105.00 | $90.95 | $107.00 | $111.02 |
| 0235 | Fiber optic connection hardware, F&I, buffer tube fan out kit (0633-3-14) | EACH | 17 | $114.20 | $114.31 | $115.00 | $90.95 | $107.00 | $111.02 |
| 0240 | Fiber optic connection hardware, F&I, patch panel- terminated (0633-3-16) | EACH | 16 | $1,538.30 | $1,539.84 | $1,400.00 | $1,225.15 | $1,440.00 | $1,495.56 |
| 0245 | Fiber optic connection hardware, F&I, connector panel (0633-3-17) | EACH | 1 | $134.35 | $134.48 | $405.00 | $107.00 | $125.53 | $130.62 |
| 0250 | Fiber optic connection hardware, adjust/modify splice enclosure (0633-3-51) | EACH | 10 | $1,068.07 | $1,069.14 | $970.00 | $850.65 | $1,000.00 | $1,038.40 |
| 0255 | Fiber optic cable locator (0633-6) | DA | 290 | $166.32 | $278.24 | $330.00 | $294.25 | $228.00 | $359.20 |
| 0260 | Multi-conductor cable, furnish & install, cat 6 (0633-8-11) | LF | 70 | $3.03 | $9.47 | $10.00 | $6.97 | $2.80 | $13.62 |
| 0265 | Multi-conductor cable, furnish & install, composite (0633-8-12) | LF | 6,062 | $8.20 | $6.44 | $20.00 | $10.18 | $3.85 | $13.62 |
| 0270 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 149 | $1,353.30 | $1,384.77 | $2,500.00 | $1,579.08 | $1,200.00 | $1,439.13 |
| 0275 | Pull & splice box, F&I, 24" X 36" cover size (0635-2-12) | EACH | 41 | $2,788.42 | $2,447.50 | $3,000.00 | $2,406.74 | $3,265.00 | $2,682.86 |
| 0280 | Junction box, furnish & install, mounted (0635-3-12) | EACH | 16 | $996.29 | $450.85 | $715.00 | $1,905.63 | $525.00 | $1,320.47 |
| 0285 | Electrical service wire, & install (0639-2-1) | LF | 31,383 | $10.39 | $7.87 | $12.00 | $8.93 | $9.20 | $8.70 |
| 0290 | Electrical service disconnect, F&I, pole mount (0639-3-11) | EACH | 26 | $3,215.55 | $2,464.89 | $3,225.00 | $2,425.75 | $3,175.00 | $4,660.40 |
| 0295 | Electrical service disconnect, remove- pole or cabinet to remain (0639-3-60) | EACH | 10 | $602.52 | $741.98 | $975.00 | $728.67 | $500.00 | $481.97 |
| 0300 | Electrical power service- transformer, F&I, 5-10 kva, phase, copper windings (0639-6121) | EACH | 17 | $2,733.59 | $2,327.05 | $4,625.00 | $2,773.98 | $3,045.00 | $2,389.63 |
| 0305 | Prestressed concrete pole, type P-II service pole (0641-2-12) | EACH | 16 | $1,583.55 | $3,017.96 | $2,875.00 | $2,104.04 | $2,562.00 | $2,710.95 |
| 0310 | Aluminum pole- index 695-001, furnish & install, 12' (0646-2112) | EACH | 1 | $2,746.67 | $4,746.71 | $6,400.00 | $4,497.73 | $7,377.00 | $13,458 |
| 0315 | Vehicle detection system- wrong way for exit ramp, 1 or 2 lanes, AC powered (0660-7-21) | EACH | 11 | $42,461 | $50,190 | $35,000 | $52,843 | $56,175 | $60,569 |
| 0320 | Vehicle detection system- wrong way for exit ramp, 3 or more lanes, AC powered (0660-7-22) | EACH | 7 | $42,461 | $50,190 | $40,000 | $52,843 | $56,175 | $70,979 |
| 0325 | ITS cabinet, furnish & install, pole mount with sunshield, 24" W X 46" H X 22" D (0676-2122) | EACH | 16 | $8,084.25 | $9,986.35 | $12,500 | $12,058 | $11,350 | $8,385.58 |
| 0330 | Managed field ethernet switch, furnish & install (0684-1-1) | EACH | 16 | $4,589.26 | $4,586.83 | $9,500.00 | $13,081 | $12,490 | $3,815.44 |
| 0335 | Uninterruptible power supply, furnish and install, line interactive (0685-1-11) | EACH | 16 | $4,605.71 | $4,013.52 | $6,500.00 | $7,964.83 | $15,520 | $7,113.38 |
| 0340 | Remote power management rpmu, furnish and install (0685-2-1) | EACH | 17 | $741.67 | $1,032.59 | $1,650.00 | $1,267.58 | $1,930.00 | $719.70 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of July 30, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.