12 contracts let by Florida DOT on April 24, 2024, $101,863,165 in low bids, a median of 4 bidders per contract.
- Owner
- Florida DOT
- Contracts
- 12
- Low bids, total
- $101,863,165
- Data through
- 28 OCT 2026
Contracts let that day
| Contract | Project | District | Bids | Low bidder | Low bid | Second bid | Gap | Source |
|---|---|---|---|---|---|---|---|---|
| T1894 | SR 25 (US 27) FROM SHORELINE DR TO DAVIS & GAINES RD | District 1 | 4 | C.W. Roberts Contracting, Inc. | $27,819,858 | $28,064,946 | +1.0% | FDOT |
| T7520 | SR 595 (ALT US 19 / PINELLAS AVE) FROM S OF TAMPA RD TO... | District 7 | 4 | Watson Civil Construction, Inc. | $19,767,535 | $21,683,500 | +10% | FDOT |
| T5824 | SR 46 (W 1ST ST) FROM E OF I-4 TO SR 15 (US 17/92) | District 5 | 7 | Masci General Contractors, Inc | $16,711,370 | $17,850,682 | +7.0% | FDOT |
| T3894 | SR 30/30A (US 98/15TH ST) FROM E OF 23RD ST FLYOVER TO JENKS | District 3 | 3 | C.W. Roberts Contracting, Inc. | $10,976,990 | $12,713,979 | +16% | FDOT |
| T6580 | SR 90 (SW 8 ST) AND SW 4 AVE FROM SW 4 AVE TO SW 2 AVE AND.. | District 6 | 6 | H & R Paving, Inc. | $5,947,099 | $6,237,613 | +5.0% | FDOT |
| T1850 | CR 664 (COUNTYLINE RD) OVER PEACE RIVER, BRIDGE NO 160101 | District 1 | 8 | Cone & Graham, Inc. | $5,279,314 | $5,393,000 | +2.0% | FDOT |
| T6577 | SR 934 (NW 74 ST / W-E 21 ST) FROM E OF W 4 AVE TO E 4 AVE | District 6 | 4 | H & R Paving, Inc. | $4,280,927 | $5,066,418 | +18% | FDOT |
| T4686 | SW 45TH ST/ORANGE DR AND TAFT ST FROM FLORIDA'S TURNPIKE... | District 4 | 2 | The Stout Group LLC | $3,298,227 | $4,519,353 | +37% | FDOT |
| T2982 | DISTRICT WIDE RUMBLE STRIPS AT VARIOUS LOCATIONS AS SHOWN... | District 2 | 4 | Emerald Coast Striping, LLC. | $3,046,700 | $3,648,202 | +20% | FDOT |
| T3893 | CR 389 (E 12TH ST) FROM SR 390 TO PENNSYLVANIA AVE | District 3 | 4 | American Sand & X-Cavation, Inc. DBA American Sand & Asphalt | $2,076,217 | $2,222,222 | +7.0% | FDOT |
| T2988 | SR 10 (US 90/ATLANTIC BLVD) AND SR 104 (DUNN AVE)... | District 2 | 3 | De Moya Highway Infrastructure LLC | $1,562,105 | $1,635,948 | +5.0% | FDOT |
| T6583 | SR 94 (KENDALL DR), SR 90 (TAMIAMI TR), SR 997 (KROME AVE).. | District 6 | 2 | Alexander Design + Build, LLC | $1,096,822 | $1,796,694 | +64% | FDOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than FDOT received, the others did not match their published totals and are left out.