Emerald Coast Striping, LLC.: FDOT bid record
Emerald Coast Striping, LLC. submitted 20 bids on Florida DOT contracts in the data, from 30 OCT 2019 to 27 AUG 2025, and was the low bidder on 7 of them (35%). When it was not low, its total sat a median +17% above the low bid.
- Owner
- Florida DOT
- Low bid volume
- $9,258,204
- Latest bid
- 27 AUG 2025
- Data through
- 28 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2019 | 1 | 1 | 100% |
| 2020 | 4 | 2 | 50% |
| 2021 | 1 | 0 | 0% |
| 2022 | 2 | 0 | 0% |
| 2023 | 6 | 3 | 50% |
| 2024 | 4 | 1 | 25% |
| 2025 | 2 | 0 | 0% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| District 3 | 11 | 6 | 55% |
| District 2 | 5 | 1 | 20% |
| StateWide | 2 | 0 | 0% |
| District 5 | 2 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Ground-in rumble strips, 8" sinusoidal | 0546-72-3 | GM | 10 | 7 (70%) | $1,850.00 | $2,367.50 |
| Raised pavement marker, type B | 0706-1-3 | EACH | 11 | 6 (55%) | $4.50 | $5.00 |
| Work zone sign | 0102-60 | ED | 18 | 5 (28%) | $1.00 | $0.25 |
| Painted pavement markings, standard, white, solid, 6" | 0710-11101 | GM | 7 | 3 (43%) | $900.00 | $1,350.00 |
| Painted pavement markings, standard, yellow, solid, 6" | 0710-11201 | GM | 7 | 3 (43%) | $879.79 | $1,350.00 |
| Thermoplastic, remove existing thermoplastic pavement markings- surface to remain | 0711-17-1 | SF | 7 | 3 (43%) | $3.00 | $4.50 |
| Single post sign, F&I ground mount, UP to 12 SF | 0700-1-11 | AS | 6 | 3 (50%) | $425.00 | $406.23 |
| Sign panel, remove, UP to 12 SF | 0700-3601 | EACH | 5 | 3 (60%) | $100.00 | $65.00 |
| Channelizing device- types I, II, VP, drum, or LCD | 0102-74-1 | ED | 13 | 2 (15%) | $0.50 | $0.13 |
| Thermoplastic, refurbishment, yellow, solid, 6" | 0711-12201 | GM | 9 | 2 (22%) | $3,300.00 | $3,400.00 |
| Portable changeable message sign, temporary | 0102-99 | ED | 7 | 2 (29%) | $60.00 | $12.00 |
| Traffic control officer | 0102-14 | HR | 7 | 2 (29%) | $100.00 | $80.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Acme Barricades LC | 16 | 6 of 16 |
| TRP Construction Group, LLC | 11 | 8 of 11 |
| Oglesby Construction, Inc. | 7 | 5 of 7 |
| Akca, LLC | 6 | 1 of 6 |
| McShea Contracting, LLC | 2 | 0 of 2 |
| Alexander Design + Build, LLC | 2 | 0 of 2 |
| Weekley Asphalt Paving, Inc. | 1 | 0 of 1 |
| Chinchor Electric Inc. | 1 | 0 of 1 |
| Hinson, James D., Electrical Contracting Company, Inc. | 1 | 0 of 1 |
| Powercore, Inc. | 1 | 0 of 1 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 27 AUG 2025 | T3986 | District 3 | SR 10 (US 90) FROM W OF BYRD RD TO OPPORTUNITY LN | 2 of 3 | $124,513 | +17% |
| 29 JAN 2025 | T3974 | District 3 | SR 30 (US 98), SR 10 (US 90), SR 12, SR 61 (US 319), SR 369 | 2 of 4 | $670,616 | +1.0% |
| 13 NOV 2024 | T3936 | District 3 | SR 20, SR 73, SR 30 (US 98), SR 30A, SR 73 AND SR 69 AT VAR | 2 of 3 | $1,156,645 | +16% |
| 25 SEP 2024 | T9043 | StateWide | SR 10 (US 90) AT PENSACOLA WEIGH STATION | 2 of 2 | $319,377 | +68% |
| 24 APR 2024 | T2982 | District 2 | DISTRICT WIDE RUMBLE STRIPS AT VARIOUS LOCATIONS AS SHOWN... | 1 of 4 | $3,046,700 | Low, 20% under the second |
| 31 JAN 2024 | T2981 | District 2 | SR 222/26, SR 20/25, SR 45, SR 20, SR 200, SR 26/24/20 ... | 3 of 4 | $3,514,286 | +21% |
| 06 DEC 2023 | T5820 | District 5 | SR A1A, SR 5, SR 44, SR 11, SR 415 AND SR 5A | 3 of 6 | $689,669 | +14% |
| 06 DEC 2023 | T5821 | District 5 | SR 35, SR 25, SR 45, SR 500, SR 19 AND SR 200 | 4 of 6 | $939,291 | +11% |
| 25 OCT 2023 | T2980 | District 2 | SR 20, SR 21, SR 26, SR 100, SR A1A, SR 312, SR 207, SR 16, | 3 of 5 | $1,765,197 | +48% |
| 25 OCT 2023 | T3889 | District 3 | VARIOUS LOCATIONS AS SHOWN IN THE PLANS | 1 of 4 | $1,570,117 | Low, 10% under the second |
| 13 SEP 2023 | T3886 | District 3 | DISTRICT WIDE AT VARIOUS LOCATIONS AS SHOWN IN THE PLANS | 1 of 4 | $1,444,661 | Low, 24% under the second |
| 24 MAY 2023 | T3860 | District 3 | DISTRICT WIDE RURAL CURVE INITIATIVE | 1 of 2 | $2,392,127 | Low, 13% under the second |
| 27 APR 2022 | T2852 | District 2 | DISTRICTWIDE SAFETY PUSH BUTTON, ON SYSTEM (2ND) | 4 of 5 | $1,219,400 | +151% |
| 26 JAN 2022 | T3811 | District 3 | DISTRICT 3 SCHOOL ZONE IMPLEMENTATION PLAN | 2 of 2 | $2,186,622 | +65% |
| 27 OCT 2021 | T9027 | StateWide | SR 8 (I-10) | 2 of 3 | $652,184 | +15% |
| 29 APR 2020 | T2762 | District 2 | DISTRICT WIDE SCHOOL ZONE IMPROVEMENTS | 2 of 5 | $1,744,550 | +9.0% |
| 29 APR 2020 | T3748 | District 3 | SAFETY PROJECT | 2 of 2 | $905,334 | +51% |
| 25 MAR 2020 | T3734 | District 3 | SR 377 (US 319) (SOPCHOPPY HWY) | 1 of 1 | $161,220 | Low |
| 26 FEB 2020 | T3743 | District 3 | SR 71 | 1 of 1 | $187,229 | Low |
| 30 OCT 2019 | T9020 | District 3 | SNEADS WEIGH STATION | 1 of 2 | $456,152 | Low, 7.0% under the second |
How this record was read
FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
- Every bid counted here matched its published total to within one dollar; FDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.