De Moya Highway Infrastructure LLC: FDOT bid record
De Moya Highway Infrastructure LLC submitted 29 bids on Florida DOT contracts in the data, from 29 MAR 2023 to 03 DEC 2025, and was the low bidder on 4 of them (14%). When it was not low, its total sat a median +21% above the low bid.
- Owner
- Florida DOT
- Low bid volume
- $58,851,235
- Latest bid
- 03 DEC 2025
- Data through
- 28 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2023 | 12 | 1 | 8% |
| 2024 | 16 | 3 | 19% |
| 2025 | 1 | 0 | 0% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| District 7 | 14 | 1 | 7% |
| District 1 | 8 | 0 | 0% |
| District 2 | 5 | 2 | 40% |
| District 6 | 1 | 1 | 100% |
| StateWide | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Raised pavement marker, type B | 0706-1-3 | EACH | 49 | 33 (67%) | $5.00 | $5.00 |
| Conduit, furnish & install, directional bore | 0630-2-12 | LF | 47 | 26 (55%) | $35.00 | $30.82 |
| Work zone sign | 0102-60 | ED | 28 | 19 (68%) | $0.20 | $0.25 |
| Pull & splice box, F&I, 13" X 24" cover size | 0635-2-11 | EACH | 42 | 18 (43%) | $1,470.00 | $1,150.00 |
| Portable changeable message sign, temporary | 0102-99 | ED | 26 | 18 (69%) | $10.00 | $12.00 |
| Type III barricade | 0102-115 | ED | 26 | 18 (69%) | $0.25 | $0.34 |
| Channelizing device- types I, II, VP, drum, or LCD | 0102-74-1 | ED | 29 | 17 (59%) | $0.10 | $0.13 |
| Traffic control officer | 0102-14 | HR | 25 | 17 (68%) | $90.00 | $80.00 |
| Retroreflective sign strip- furnish and install, 5' | 0700-13-15 | EACH | 18 | 17 (94%) | $72.50 | $108.20 |
| Arrow board / advance warning arrow panel | 0102-76 | ED | 25 | 16 (64%) | $5.00 | $5.90 |
| Litter removal | 0107-1 | ACRE | 28 | 15 (54%) | $50.00 | $52.98 |
| Thermoplastic, standard, solid, 18" for diagonals and chevrons | 0711-11124 | LF | 27 | 15 (56%) | $5.50 | $4.58 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Ajax Paving Industries of Florida LLC | 14 | 6 of 14 |
| Watson Civil Construction, Inc. | 14 | 11 of 14 |
| Preferred Materials Inc. | 12 | 7 of 12 |
| Gosalia Concrete Constructors, Inc. | 7 | 7 of 7 |
| C.W. Roberts Contracting, Inc. | 7 | 7 of 7 |
| Webber, LLC | 4 | 2 of 4 |
| Russell Engineering, Inc. | 3 | 2 of 3 |
| Hubbard Construction Company | 3 | 1 of 3 |
| Prince Contracting, LLC. | 2 | 0 of 2 |
| Superior Construction Company Southeast, LLC | 2 | 1 of 2 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 03 DEC 2025 | T7559 | District 7 | SR 400 (I-4) FROM E OF TAMPA BYPASS CANAL TO W OF I-75 | 4 of 5 | $9,858,634 | +15% |
| 13 NOV 2024 | T7541 | District 7 | SR 586 (CURLEW RD) FROM E OF LANDMARK DR TO SR 584 (TAMPA RD | 3 of 4 | $13,679,351 | +27% |
| 28 AUG 2024 | T7546 | District 7 | SR 594 (I-75) FROM 16TH ST S TO 4TH ST | 3 of 3 | $6,470,148 | +21% |
| 28 AUG 2024 | T9040 | StateWide | SR 93 (I-75) AT PUNTA GORDA NB AND SB WEIGH STATIONS | 4 of 6 | $15,039,176 | +8.0% |
| 31 JUL 2024 | T2946 | District 2 | SR 9 (I-95) FROM FOREST ST BRIDGE TO RAILROAD BRIDGE AND... | 3 of 4 | $8,437,471 | +29% |
| 12 JUN 2024 | T1870 | District 1 | SR 700/35 (US 98) FROM S OF GRIFFIN RD TO SHARON DR | 3 of 4 | $13,570,387 | +9.0% |
| 22 MAY 2024 | T2979 | District 2 | SR 13 FROM S OF I-295 TO N OF SUNBEAM RD | 3 of 5 | $17,460,146 | +4.0% |
| 22 MAY 2024 | T7530 | District 7 | SR 580 (SKINNER BLVD) FROM ALT US 19 (BROADWAY) TO MAIN ST | 1 of 3 | $9,184,009 | Low, 1.0% under the second |
| 22 MAY 2024 | T7549 | District 7 | OLA AVE (N RIVER BLVD / N HIGHLAND AVE / DARTMOUTH AVE) FROM | 4 of 5 | $6,192,674 | +23% |
| 24 APR 2024 | T2988 | District 2 | SR 10 (US 90/ATLANTIC BLVD) AND SR 104 (DUNN AVE)... | 1 of 3 | $1,562,105 | Low, 5.0% under the second |
| 24 APR 2024 | T7520 | District 7 | SR 595 (ALT US 19 / PINELLAS AVE) FROM S OF TAMPA RD TO... | 4 of 4 | $24,989,695 | +26% |
| 17 APR 2024 | T7535 | District 7 | SR 400 (I-4) AT SEFFNER EB AND WB WEIGH STATIONS | 3 of 3 | $767,596 | +23% |
| 27 MAR 2024 | T1857 | District 1 | SR 35 (US 17) and SR 45 (TAMIAMI TR/US 41) FROM SR 45... | 5 of 5 | $29,718,011 | +22% |
| 27 MAR 2024 | T1878 | District 1 | SR 25 (US 27) AT SR 78 | 2 of 3 | $9,979,523 | +18% |
| 27 MAR 2024 | T2972 | District 2 | SR 211 FROM SR 128 (SAN JUAN AVE) TO I-95 | 2 of 2 | $11,870,826 | +6.0% |
| 28 FEB 2024 | T7519 | District 7 | SR 400 (I-4) FROM PARK RD WB EXIT RAMP INTERSECTION TO E OF | 4 of 5 | $23,366,273 | +24% |
| 31 JAN 2024 | T2964 | District 2 | SR 228A (EMERSON ST EXPRESSWAY) AND SR 126 (EMERSON ST EXT) | 1 of 3 | $10,386,249 | Low, 13% under the second |
| 06 DEC 2023 | T1887 | District 1 | SR 865 (SAN CARLOS BLVD), FROM N OF CRESCENT ST TO N OF... | 2 of 4 | $15,218,429 | +15% |
| 06 DEC 2023 | T7527 | District 7 | SR 93A (I-75) FROM S OF PROGRESS BLVD TO N OF WOODBERRY RD | 3 of 4 | $28,883,379 | +28% |
| 15 NOV 2023 | T1866 | District 1 | SR 15 (US 98) AND SR 15/SR 700, From SW 23RD ST TO SW 14 ... | 4 of 5 | $5,852,340 | +48% |
| 25 OCT 2023 | T6596 | District 6 | SR 90 (US 41 / SW 8 ST), OVER SR 90 (US 41 / SW 8 ST) AND .. | 1 of 3 | $37,718,871 | Low, 1.0% under the second |
| 14 JUN 2023 | T1861 | District 1 | LEGACY TRAIL | 5 of 6 | $15,274,451 | +19% |
| 14 JUN 2023 | T7515 | District 7 | SR 595 (ALT US 19) (5TH AVE N) | 3 of 3 | $15,748,531 | +20% |
| 24 MAY 2023 | T1856 | District 1 | SR 400 (I-4) | 2 of 2 | $8,958,282 | +2.0% |
| 24 MAY 2023 | T7462 | District 7 | SR 45 (US 41) | 3 of 3 | $23,584,837 | +9.0% |
How this record was read
FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
- Every bid counted here matched its published total to within one dollar; FDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.