FDOT contract T7559 bid tabulation
SR 400 (I-4) FROM E OF TAMPA BYPASS CANAL TO W OF I-75. Let by Florida DOT on December 3, 2025, Hillsborough, District 7. 5 bids received; low bid $8,564,850 by Watson Civil Construction, Inc..
- Owner
- Florida DOT
- Letting
- 03 DEC 2025
- Pay items
- 153
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Watson Civil Construction, Inc. | $8,564,850 | Low |
| 2 | Preferred Materials Inc. | $8,700,867 | +2.0% |
| 3 | C.W. Roberts Contracting, Inc. | $8,905,115 | +4.0% |
| 4 | De Moya Highway Infrastructure LLC | $9,858,634 | +15% |
| 5 | Ajax Paving Industries of Florida LLC | $11,897,195 | +39% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Watson Civil Construction, Inc. | 2. Preferred Materials Inc. | 3. C.W. Roberts Contracting, Inc. | 4. De Moya Highway Infrastructure LLC | 5. Ajax Paving Industries of Florida LLC |
|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $850,000 | $830,988 | $828,361 | $950,000 | $1,190,000 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $560,000 | $300,154 | $485,150 | $475,000 | $1,190,000 |
| 0015 | Special detour- temporary pavement (0102-2200) | SY | 1 | $326,000 | $216,828 | $328,889 | $750,000 | $400,000 |
| 0020 | Special detour- temporary earthwork/base (0102-2300) | CY | 1 | $210,000 | $249,817 | $290,396 | $200,000 | $515,000 |
| 0025 | Traffic control officer (0102-14) | HR | 862 | $120.00 | $85.16 | $96.87 | $90.00 | $121.07 |
| 0030 | Work zone sign (0102-60) | ED | 16,151 | $0.32 | $0.22 | $0.26 | $0.21 | $0.20 |
| 0035 | Barrier mounted work zone sign- index 700-012 (0102-62-12) | ED | 112 | $31.00 | $12.77 | $14.70 | $12.00 | $23.06 |
| 0040 | Barrier mounted work zone sign- index 700-013 (0102-62-13) | ED | 4,030 | $1.30 | $0.69 | $0.80 | $0.65 | $0.40 |
| 0045 | Temporary barrier, F&I, anchored (0102-71-15) | LF | 6,888 | $36.00 | $59.09 | $44.11 | $37.00 | $40.64 |
| 0050 | Temporary barrier, relocate, anchored (0102-71-25) | LF | 4,988 | $15.00 | $28.10 | $20.27 | $17.00 | $16.72 |
| 0055 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 61,525 | $0.11 | $0.13 | $0.15 | $0.12 | $0.10 |
| 0060 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 490 | $0.06 | $0.05 | $0.06 | $0.05 | $0.03 |
| 0065 | Arrow board / advance warning arrow panel (0102-76) | ED | 396 | $6.00 | $6.39 | $7.35 | $6.00 | $5.77 |
| 0070 | Temporary crash cushion, redirective option (0102-89-1) | LO | 9 | $1,110.00 | $1,277.45 | $1,430.60 | $2,500.00 | $1,124.21 |
| 0075 | Portable changeable message sign, temporary (0102-99) | ED | 2,317 | $12.00 | $10.65 | $12.25 | $10.00 | $10.38 |
| 0080 | Existing ITS maintenance (0102-112) | DA | 300 | $110.00 | $79.84 | $399.44 | $50.00 | $90.80 |
| 0085 | Type III barricade (0102-115) | ED | 140 | $0.34 | $0.37 | $0.43 | $0.35 | $0.27 |
| 0090 | Portable regulatory, sign (0102-150-1) | ED | 1,202 | $5.50 | $6.39 | $7.35 | $6.00 | $4.61 |
| 0095 | Radar speed display unit (0102-150-2) | ED | 1,202 | $5.50 | $6.39 | $7.35 | $6.00 | $5.19 |
| 0100 | Sediment barrier (0104-10-3) | LF | 10,120 | $1.10 | $1.81 | $1.70 | $3.00 | $5.07 |
| 0105 | Staked turbidity barrier- nylon reinforced PVC (0104-12) | LF | 722 | $5.10 | $9.31 | $8.48 | $10.00 | $28.83 |
| 0110 | Soil tracking prevention device (0104-15) | EACH | 3 | $4,800.00 | $1,596.81 | $1,020.89 | $4,500.00 | $7,921.34 |
| 0115 | Inlet protection system (0104-18) | EACH | 12 | $130.00 | $90.49 | $164.10 | $200.00 | $253.67 |
| 0120 | Litter removal (0107-1) | ACRE | 322.71 | $50.00 | $34.98 | $38.92 | $50.00 | $54.19 |
| 0125 | Mowing (0107-2) | ACRE | 316.76 | $65.00 | $50.62 | $56.33 | $50.00 | $50.73 |
| 0130 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $381,000 | $436,774 | $280,682 | $750,000 | $1,100,000 |
| 0135 | Removal of existing concrete (0110-4-10) | SY | 1,891 | $31.00 | $56.54 | $67.78 | $50.00 | $55.35 |
| 0140 | Regular excavation (0120-1) | CY | 7,626.30 | $10.00 | $22.84 | $8.71 | $20.00 | $11.53 |
| 0145 | Subsoil excavation (0120-4) | CY | 1,720.60 | $16.00 | $37.50 | $41.20 | $25.00 | $68.03 |
| 0150 | Embankment (0120-6) | CY | 8,262.70 | $10.00 | $27.24 | $9.98 | $30.00 | $33.44 |
| 0155 | Type B stabilization (0160-4) | SY | 17,334 | $12.00 | $15.80 | $12.51 | $20.00 | $11.53 |
| 0160 | Optional base, base group 08 (0285-708) | SY | 9,113 | $25.00 | $42.31 | $22.65 | $35.00 | $31.13 |
| 0165 | Optional base, base group 12 (0285-712) | SY | 8,225 | $31.00 | $43.33 | $28.18 | $40.00 | $49.58 |
| 0170 | Milling existing asphalt pavement, 1" avg depth (0327-70-1) | SY | 27,338 | $3.55 | $2.30 | $4.31 | $3.40 | $3.99 |
| 0175 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 6,425 | $9.90 | $4.05 | $8.03 | $3.90 | $8.61 |
| 0180 | Milling existing asphalt pavement, 2 1/4" avg depth (0327-70-11) | SY | 5,644 | $11.15 | $6.77 | $9.04 | $8.00 | $9.22 |
| 0185 | Superpave asphaltic conc, traffic E (0334-1-15) | TN | 1,977.80 | $189.00 | $178.08 | $146.07 | $145.00 | $230.23 |
| 0190 | Superpave asphaltic concrete, traffic E, PG76-22 (0334-1-55) | TN | 2,806.20 | $201.00 | $184.16 | $193.27 | $216.00 | $270.68 |
| 0195 | Asphalt concrete friction course, inc bit, FC-5, PG 76-22 (0337-7-25) | TN | 1,980.90 | $269.00 | $219.57 | $250.41 | $280.00 | $313.86 |
| 0200 | Miscellaneous asphalt (0339-1) | TN | 90.50 | $552.00 | $405.31 | $844.53 | $700.00 | $659.22 |
| 0205 | Inlets, DT bot, type B, <10' (0425-1511) | EACH | 3 | $7,600.00 | $10,842 | $12,918 | $10,000 | $10,954 |
| 0210 | Inlets, DT bot, type F, <10' (0425-1561) | EACH | 1 | $7,200.00 | $9,341.32 | $11,129 | $8,000.00 | $9,939.15 |
| 0215 | Inlets, ditch bottom, type F, partial (0425-1565) | EACH | 1 | $6,400.00 | $8,760.81 | $10,438 | $8,000.00 | $10,723 |
| 0220 | Inlets, gutter, type S, <10' (0425-1701) | EACH | 4 | $4,300.00 | $11,321 | $13,488 | $8,000.00 | $7,494.72 |
| 0225 | Manholes, P-8, <10' (0425-2-61) | EACH | 1 | $5,000.00 | $9,075.98 | $10,813 | $8,000.00 | $8,347.96 |
| 0230 | Manholes, J-7, <10' (0425-2-71) | EACH | 1 | $9,400.00 | $13,258 | $15,795 | $13,000 | $12,741 |
| 0235 | Pipe culvert,optional material,round, 18"S/CD (0430-175118) | LF | 525 | $161.00 | $230.56 | $274.69 | $350.00 | $196.02 |
| 0240 | Pipe culvert,optional material,round, 24"S/CD (0430-175124) | LF | 8 | $310.00 | $258.14 | $307.55 | $500.00 | $795.59 |
| 0245 | Pipe culvert, opt material, round, 48"S/CD (0430-175148) | LF | 65 | $479.00 | $591.76 | $705.02 | $500.00 | $668.76 |
| 0250 | Pipe culvert,optional material,other-elip/arch, (0430-175215) | LF | 18 | $183.00 | $229.02 | $272.86 | $500.00 | $184.49 |
| 0255 | Straight concrete endwalls, double, 0 degrees, round (0430-548200) | EACH | 1 | $22,700 | $18,417 | $21,942 | $15,000 | $55,369 |
| 0260 | Mitered end section, optional round, 18" CD (0430-982125) | EACH | 5 | $1,900.00 | $3,750.49 | $4,468.36 | $3,500.00 | $4,854.27 |
| 0265 | Mitered end section, optional - elliptical / arch, 15" CD (0430-982623) | EACH | 2 | $1,900.00 | $3,305.72 | $3,938.46 | $3,000.00 | $4,439.18 |
| 0270 | Shoulder gutter- concrete (0520-6) | LF | 497 | $63.00 | $52.68 | $45.13 | $60.00 | $89.94 |
| 0275 | Concrete ditch pavement, non reinforced, 4" (0524-1-2) | SY | 331 | $177.00 | $105.63 | $116.68 | $150.00 | $161.42 |
| 0280 | Riprap, rubble, F&I, ditch lining (0530-3-4) | TN | 662.30 | $163.00 | $158.84 | $172.78 | $200.00 | $161.42 |
| 0285 | Guardrail -roadway, general (0536-1-1) | LF | 894 | $23.50 | $25.11 | $26.88 | $23.04 | $26.57 |
| 0290 | Guardrail removal (0536-73) | LF | 354 | $2.10 | $1.79 | $1.91 | $2.42 | $2.79 |
| 0295 | Guardrail end treatment- trailing anchorage (0536-85-20) | EACH | 2 | $2,000.00 | $1,698.37 | $1,818.12 | $1,405.00 | $1,616.85 |
| 0300 | Guardrail end treatment- parallel approach terminal (0536-85-24) | EACH | 2 | $3,000.00 | $3,059.22 | $3,274.93 | $3,300.00 | $3,765.65 |
| 0305 | Performance turf, sod (0570-1-2) | SY | 65,986 | $5.10 | $3.26 | $6.26 | $5.00 | $4.96 |
| 0310 | Conduit, furnish & install, open trench (0630-2-11) | LF | 13 | $22.10 | $20.49 | $48.35 | $42.00 | $23.31 |
| 0315 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 96 | $43.00 | $39.81 | $33.38 | $29.00 | $45.28 |
| 0320 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 3 | $1,800.00 | $1,657.49 | $1,368.67 | $1,200.00 | $1,885.04 |
| 0325 | Traffic monitoring site vehicle sensor-non-weight, furnish & install (0695-1-1) | EACH | 5 | $4,400.00 | $4,068.66 | $2,872.03 | $2,500.00 | $4,627.78 |
| 0330 | Traffic monitoring site inductive loop assembly, & install, 2 loops (0695-6-12) | EACH | 5 | $2,560.00 | $2,341.98 | $4,144.00 | $3,600.00 | $2,663.51 |
| 0335 | Traffic monitoring site cabinet, F&I, type 3, 2 pane back, pedestal mount (0695-7162) | EACH | 1 | $8,200.00 | $7,554.59 | $8,176.35 | $7,105.00 | $8,591.74 |
| 0340 | Raised pavement marker, type B (0706-1-3) | EACH | 5,005 | $4.20 | $5.85 | $4.35 | $5.00 | $4.79 |
| 0345 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 7.68 | $1,950.00 | $1,596.83 | $1,858.48 | $1,600.00 | $2,190.76 |
| 0350 | Painted pavement markings, standard, white, solid for interchange and urban island, (0710-11102) | GM | 0.50 | $2,600.00 | $1,594.70 | $2,090.12 | $1,800.00 | $2,921.79 |
| 0355 | Painted pavement markings, standard, white, solid for interchange markings, 12" (0710-11103) | GM | 1.83 | $3,850.00 | $3,192.25 | $2,319.06 | $2,000.00 | $4,381.53 |
| 0360 | Painted pavement markings, standard, white, solid for diagonal or chevron, 18" (0710-11124) | LF | 1,186 | $1.90 | $2.13 | $3.48 | $3.00 | $2.13 |
| 0365 | Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131) | GM | 6.02 | $505.00 | $691.84 | $1,162.53 | $1,000.00 | $576.52 |
| 0370 | Painted pavement marking, standard,white, 3'-9' skip drop line and approach to toll 12" wide, (0710-11133) | GM | 0.39 | $1,050.00 | $1,063.94 | $1,852.51 | $1,600.00 | $1,153.03 |
| 0375 | Painted pavement markings, standard, white, message or symbol (0710-11160) | EACH | 19 | $41.00 | $85.16 | $98.67 | $85.00 | $46.12 |
| 0380 | Painted pavement markings, standard, white, arrows (0710-11170) | EACH | 21 | $41.00 | $42.58 | $52.24 | $45.00 | $46.12 |
| 0385 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 6.11 | $1,950.00 | $1,596.83 | $1,859.10 | $1,600.00 | $2,190.76 |
| 0390 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $98,000 | $98,000 | $98,000 | $98,000 | $98,000 |
| 0395 | Ground-in rumble strips, 16" (0546-72-1) | GM | 1.32 | $8,000.00 | $4,795.24 | $12,282 | $8,000.00 | $4,035.62 |
| 0400 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 6 | $1,975.00 | $2,014.20 | $2,437.81 | $2,100.00 | $605.34 |
| 0405 | Single column ground sign assembly, relocate (0700-1500) | EACH | 8 | $2,050.00 | $2,089.11 | $592.04 | $510.00 | $172.96 |
| 0410 | Single column ground sign assembly, remove (0700-1600) | EACH | 4 | $103.00 | $105.49 | $482.92 | $416.00 | $51.89 |
| 0415 | Multi-column ground sign assembly, F&I ground mount, 50.0 SF (0700-2114) | EACH | 1 | $7,560.00 | $7,793.59 | $7,823.03 | $6,739.00 | $10,954 |
| 0420 | Multi-column ground sign assembly, F&I ground mount, 100.0 SF (0700-2115) | EACH | 1 | $8,900.00 | $9,134.54 | $10,582 | $9,116.00 | $12,683 |
| 0425 | Multi-column ground sign assembly, F&I ground mount, 1-200.0 SF (0700-2116) | EACH | 1 | $15,800 | $16,253 | $20,818 | $17,933 | $34,591 |
| 0430 | Multi-column ground sign assembly, F&I ground mount, 1-400.0 SF (0700-2118) | EACH | 1 | $19,100 | $19,662 | $35,116 | $30,250 | $39,203 |
| 0435 | Multi-column ground sign assembly, relocate (0700-2500) | EACH | 2 | $10,800 | $11,079 | $9,004.79 | $7,757.00 | $3,747.36 |
| 0440 | Multi-column ground sign assembly, remove (0700-2600) | EACH | 1 | $740.00 | $761.89 | $2,263.68 | $1,950.00 | $2,882.58 |
| 0445 | Sign panel, furnish & install overhead mount, 21-30 SF (0700-3203) | EACH | 2 | $1,400.00 | $1,445.59 | $1,788.88 | $1,541.00 | $1,644.05 |
| 0450 | Sign panel, furnish & install overhead mount, 51-100 SF (0700-3205) | EACH | 2 | $3,750.00 | $3,857.92 | $6,080.59 | $5,238.00 | $4,387.56 |
| 0455 | Sign panel, furnish & install overhead mount, 101-200 SF (0700-3206) | EACH | 6 | $5,500.00 | $5,662.18 | $6,779.42 | $5,840.00 | $6,439.53 |
| 0460 | Sign panel, furnish & install overhead mount, 601 SF and greater (0700-3211) | EACH | 2 | $33,400 | $34,429 | $42,822 | $36,888 | $39,156 |
| 0465 | Sign panel, relocate, 12-20 SF (0700-3502) | EACH | 1 | $500.00 | $511.49 | $370.32 | $319.00 | $581.71 |
| 0470 | Sign panel, remove, 21-30 SF (0700-3603) | EACH | 2 | $265.00 | $269.88 | $406.30 | $350.00 | $306.93 |
| 0475 | Sign panel, remove, 51-100 SF (0700-3605) | EACH | 2 | $685.00 | $703.01 | $578.11 | $498.00 | $799.52 |
| 0480 | Sign panel, remove, 101-200 SF with lighting (0700-3626) | EACH | 3 | $1,750.00 | $1,783.77 | $3,879.59 | $3,342.00 | $2,028.66 |
| 0485 | Sign panel, remove panel, SF with lighting (0700-3627) | EACH | 3 | $1,920.00 | $1,977.44 | $3,871.47 | $3,335.00 | $2,248.92 |
| 0490 | Overhead static sign furnish & install, span, 51-100 FT (0700-4125) | EACH | 1 | $204,000 | $189,126 | $220,469 | $200,000 | $215,091 |
| 0495 | Overhead static sign furnish & install, span, 101-150 (0700-4126) | EACH | 2 | $407,000 | $377,770 | $373,734 | $330,000 | $429,669 |
| 0500 | Overhead static sign deep foundation removal, cantilever (0700-4612) | EACH | 2 | $13,800 | $12,759 | $18,468 | $16,000 | $14,510 |
| 0505 | Overhead static sign deep foundation removal, span (0700-4622) | EACH | 1 | $30,500 | $28,212 | $60,467 | $55,000 | $32,085 |
| 0510 | Delineator, non-flexible (0705-11-2) | EACH | 108 | $102.00 | $212.91 | $203.15 | $120.00 | $115.30 |
| 0515 | Raised pavement marker, type B (0706-1-3) | EACH | 905 | $4.20 | $5.85 | $4.35 | $5.00 | $4.79 |
| 0520 | Painted pavement markings, surface (0710-90) | LS | 1 | $22,000 | $18,097 | $19,153 | $20,000 | $27,600 |
| 0525 | Thermoplastic, standard, solid, 12" for interchange markings (0711-11103) | GM | 0.15 | $11,600 | $31,936 | $11,455 | $12,000 | $13,369 |
| 0530 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 1,186 | $6.00 | $10.65 | $5.80 | $7.00 | $6.75 |
| 0535 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 16 | $134.00 | $319.36 | $232.16 | $250.00 | $152.20 |
| 0540 | Thermoplastic, standard, arrow (0711-11170) | EACH | 18 | $79.00 | $106.45 | $116.08 | $125.00 | $89.94 |
| 0545 | Thermoplastic, preformed, white, message (0711-14160) | EACH | 1 | $540.00 | $2,129.08 | $1,741.19 | $1,500.00 | $613.41 |
| 0550 | Thermoplastic, preformed, color route shield (0711-14660) | EACH | 12 | $2,000.00 | $3,193.61 | $3,134.15 | $4,200.00 | $2,269.17 |
| 0555 | Thermoplastic, standard-open graded asphalt surfaces solid, 6" (0711-15101) | GM | 1.73 | $6,800.00 | $8,517.14 | $6,972.83 | $6,500.00 | $7,780.67 |
| 0560 | Thermoplastic, standard-open graded asphalt surfaces, solid, 8" (0711-15102) | GM | 0.50 | $9,050.00 | $10,645 | $8,636.87 | $7,500.00 | $10,374 |
| 0565 | Thermoplastic, standard-open graded asphalt surfaces, skip, 6",10-30 skip or 3-9 lane (0711-15131) | GM | 2.91 | $1,750.00 | $2,661.49 | $3,481.19 | $4,500.00 | $1,945.17 |
| 0570 | Thermoplastic, standard-open graded asphalt surfaces, skip, 12"- approach to toll plaza or 3-9 lane drop (0711-15133) | GM | 0.39 | $3,400.00 | $6,386.83 | $6,946.96 | $8,000.00 | $3,890.34 |
| 0575 | Thermoplastic, standard-open graded asphalt surfaces, yellow, solid, 6" (0711-15201) | GM | 1.73 | $6,250.00 | $8,516.44 | $6,952.71 | $6,500.00 | $7,131.51 |
| 0580 | Conduit, furnish & install, open trench (0630-2-11) | LF | 4,287 | $11.20 | $10.38 | $14.96 | $13.00 | $11.80 |
| 0585 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 156 | $32.00 | $29.56 | $28.78 | $25.00 | $33.62 |
| 0590 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 19 | $1,800.00 | $1,657.49 | $2,417.34 | $2,100.00 | $1,885.04 |
| 0595 | Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12) | LF | 4,868 | $2.90 | $2.66 | $3.17 | $2.75 | $3.03 |
| 0600 | Lighting conductors, F&I, insulated, no 4 to no 2 (0715-1-13) | LF | 13,840 | $4.35 | $3.99 | $3.34 | $2.90 | $4.54 |
| 0605 | Lighting conductors, remove & dispose, contractor owns (0715-1-60) | LF | 17,898 | $0.60 | $0.53 | $1.15 | $1.00 | $0.61 |
| 0610 | Load center, rework, voltage (0715-7-21) | EACH | 1 | $5,400.00 | $5,003.33 | $3,021.67 | $2,625.00 | $5,690.22 |
| 0615 | Itsfm subsurface documentation- project length (0611-1-1) | MI | 0.80 | $4,100.00 | $3,747.18 | $4,620.28 | $4,015.00 | $4,261.61 |
| 0620 | Itsfm location documentation- ITS site (0611-2-2) | EACH | 3 | $2,200.00 | $2,043.38 | $3,687.01 | $3,203.00 | $2,323.91 |
| 0625 | Conduit, furnish & install, open trench (0630-2-11) | LF | 148 | $22.10 | $20.49 | $19.57 | $17.00 | $23.31 |
| 0630 | Fiber optic cable, F&I, underground,2-12 fibers (0633-1121) | LF | 1,205 | $4.65 | $4.28 | $3.80 | $3.30 | $4.87 |
| 0635 | Fiber optic cable, relocate, underground (0633-1420) | LF | 10 | $3.80 | $3.51 | $3.17 | $2.75 | $4.00 |
| 0640 | Fiber optic cable, remove, underground (0633-1620) | LF | 908 | $1.90 | $1.76 | $1.44 | $1.25 | $2.00 |
| 0645 | Fiber optic connection, install, splice (0633-2-31) | EACH | 4 | $57.00 | $52.70 | $73.67 | $64.00 | $59.93 |
| 0650 | Fiber optic connection, install, termination (0633-2-32) | EACH | 12 | $95.00 | $87.82 | $90.94 | $79.00 | $99.88 |
| 0655 | Fiber optic connection hardware, F&I, splice tray (0633-3-12) | EACH | 1 | $63.20 | $58.55 | $102.45 | $89.00 | $66.59 |
| 0660 | Fiber optic connection hardware, F&I, buffer tube fan out kit (0633-3-14) | EACH | 1 | $108.00 | $99.53 | $92.09 | $80.00 | $113.20 |
| 0665 | Fiber optic connection hardware, F&I, patch panel- terminated (0633-3-16) | EACH | 1 | $1,700.00 | $1,551.56 | $1,502.20 | $1,305.00 | $1,764.69 |
| 0670 | Fiber optic cable locator (0633-6) | DA | 300 | $341.00 | $316.17 | $324.61 | $50.00 | $359.57 |
| 0675 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 7 | $1,800.00 | $1,657.49 | $1,365.22 | $1,186.00 | $1,885.04 |
| 0680 | Pull & splice box, F&I, 24" X 36" cover size (0635-2-12) | EACH | 3 | $3,280.00 | $2,998.80 | $3,672.05 | $3,190.00 | $3,410.50 |
| 0685 | Electrical service wire, & install (0639-2-1) | LF | 640 | $15.00 | $13.84 | $3.11 | $2.70 | $15.74 |
| 0690 | Electrical service wire, (0639-2-6) | LF | 674 | $1.15 | $1.06 | $1.15 | $1.00 | $1.21 |
| 0695 | Prestressed concrete pole, type P-III (0641-2-13) | EACH | 2 | $21,300 | $19,705 | $10,957 | $9,519.00 | $22,410 |
| 0700 | Prestressed concrete pole, complete pole removal- pole 30' and greater (0641-2-80) | EACH | 1 | $10,900 | $10,113 | $30,381 | $26,393 | $11,502 |
| 0705 | Concrete CCTV pole, furnish & install with lowering device, (0641-3186) | EACH | 1 | $44,500 | $41,248 | $53,591 | $46,556 | $46,911 |
| 0710 | Steel CCTV pole, remove pole- complete/deep foundation removal, bolt on attachment (0649-2605) | EACH | 1 | $9,800.00 | $9,048.57 | $26,341 | $22,883 | $10,291 |
| 0715 | Vehicle detection system- avi, bluetooth relocate, cabinet equipment (0660-6421) | EACH | 1 | $1,120.00 | $1,024.62 | $1,097.01 | $953.00 | $1,165.28 |
| 0720 | Vehicle detection system- avi, bluetooth relocate, above ground equipment (0660-6422) | EACH | 1 | $1,570.00 | $1,434.46 | $1,720.91 | $1,495.00 | $1,631.40 |
| 0725 | Traffic data detection system- microwave, furnish and install, cabinet equipment (0660-8-11) | EACH | 2 | $9,750.00 | $9,017.22 | $10,245 | $8,900.00 | $10,255 |
| 0730 | Traffic data detection system- microwave, furnish and install, above ground equipment (0660-8-12) | EACH | 2 | $10,900 | $10,043 | $11,626 | $10,100 | $11,422 |
| 0735 | Traffic data detection system- microwave, remove (0660-8-60) | EACH | 2 | $1,750.00 | $1,596.81 | $2,250.43 | $1,955.00 | $1,816.03 |
| 0740 | ITS cabinet, furnish & install, pole mount, 336S, 24" W X 46" H X D (0676-2112) | EACH | 1 | $13,200 | $12,246 | $12,110 | $10,520 | $13,928 |
| 0745 | ITS cabinet- adjust/modify (0676-2500) | EACH | 2 | $3,450.00 | $3,193.62 | $2,095.03 | $1,820.00 | $3,632.06 |
| 0750 | ITS CCTV camera, pressurized, high definition (0682-1163) | EACH | 1 | $7,000.00 | $6,503.62 | $21,238 | $18,450 | $7,396.49 |
| 0755 | Managed field ethernet switch, furnish & install (0684-1-1) | EACH | 1 | $5,100.00 | $4,667.52 | $5,341.16 | $4,640.00 | $5,308.31 |
| 0760 | Uninterruptible power supply, furnish and install, line interactive (0685-1-11) | EACH | 1 | $5,800.00 | $5,333.33 | $5,824.63 | $5,060.00 | $6,065.53 |
| 0765 | Remote power management rpmu, furnish and install (0685-2-1) | EACH | 1 | $1,140.00 | $1,057.68 | $2,164.09 | $1,880.00 | $1,202.89 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of December 3, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.