Sumit Construction Co., Inc.: IDOT bid record

Sumit Construction Co., Inc. submitted 23 bids on Illinois DOT contracts in the data, from 15 JAN 2021 to 20 SEP 2024, and was the low bidder on 0 of them (0%). When it was not low, its total sat a median +25% above the low bid.

Owner
Illinois DOT
Low bid volume
$0
Latest bid
20 SEP 2024
Data through
18 SEP 2026
23Bids
0Low bids
0Win rate, percent
+25%Median gap to the low bid when not low, 23 bids

By year

YearBidsLow bidsWin rate
20211200%
2022500%
2023100%
2024500%
Sumit Construction Co., Inc., IDOT: bids and low bids by year of letting

By district

DistrictBidsLow bidsWin rate
District 012200%
District 04100%
Sumit Construction Co., Inc., IDOT: bids and low bids by district

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Trainees TPGZ0076604HR1111 (100%)$15.00$15.00
TraineesZ0076600HR1010 (100%)$0.80$0.80
Comb curb gutter rem44000500LF115 (45%)$10.00$11.61
Temp info signingZ0030850SF174 (24%)$18.50$18.00
THPL PVT MK line 1278000600LF123 (25%)$4.50$3.10
Pavmt MRKG rem WTR BL78300202SF83 (38%)$3.60$2.10
Raised ref PVT MK rem78300200EACH53 (60%)$12.00$15.00
Non SPL waste disposl66900200CY102 (20%)$82.50$92.99
PC conc sidewalk 542400200SF102 (20%)$12.00$10.00
HMA SC IL-9.5 D N7040604062TON82 (25%)$262.50$108.16
Main EX TR sig instal85000200EACH82 (25%)$3,475.00$2,600.00
Temp TR signal timingZ0073510EACH62 (33%)$1,425.00$925.00
Sumit Construction Co., Inc., IDOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

Sumit Construction Co., Inc., IDOT: the firms on the same contracts most often

Latest bids

LetContractDistrictProjectRankIts bidAgainst the low bid
20 SEP 202461J74District 01Niles, section 18-00131-00-SW3 of 3$5,571,764+22%
20 SEP 202462P38District 01Section 2021-125-SW5 of 5$1,248,952+18%
20 SEP 202462P40District 01Section 2021-123-SW2 of 3$932,134+5.0%
26 APR 202461K13District 01Addison, section 23-00110-00-SW8 of 8$839,265+54%
26 APR 202461K31District 01Alsip, section 23-00103-00-SW5 of 6$498,515+86%
28 APR 202361H93District 01Evanston, section 19-00283-00-PV2 of 3$6,719,029+1.0%
11 MAR 202262M51District 01Section 2020-165-BR5 of 5$2,099,295+44%
11 MAR 202262M64District 01Section 2020-191-BR8 of 8$1,060,046+23%
11 MAR 202262P80District 01Section 2021-158-BDR&BJR6 of 7$278,448+38%
21 JAN 202261F88District 01Woodridge, section 17-00077-00-SW6 of 7$407,874+33%
21 JAN 202262P48District 01Section 2021-115-B-R4 of 4$686,320+35%
30 JUL 202162J25District 01Section 2019-048-I8 of 8$1,774,514+89%
11 JUN 202162M41District 01Section 2020-153-BR5 of 5$5,444,939+63%
23 APR 202161G99District 01Park Forest, section 19-00105-00-SW8 of 8$330,735+36%
23 APR 202161H06District 01Bellwood, section 18-00146-00-LS7 of 11$1,130,207+17%
23 APR 202162M36District 01Section 2020-181-BR3 of 10$814,291+10%
23 APR 202162M40District 01Section 2020-159-BR8 of 9$640,231+25%
23 APR 202162N30District 01Section 2020-259-BR4 of 6$936,193+13%
05 MAR 202162M29District 01Section 2020-169-BR4 of 6$1,754,077+11%
15 JAN 202162L50District 01Section 2020-072-PP&SW6 of 7$1,080,577+20%
15 JAN 202162M22District 01Section 2020-149-BR8 of 11$771,601+26%
15 JAN 202162M49District 01Section 2020-161-BR8 of 9$1,767,159+51%
15 JAN 202168F99District 04Section (21-HB-2)BRR-12 of 5$248,981+21%
Sumit Construction Co., Inc.: latest IDOT bids in the data

How this record was read

IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

  • Every bid counted here matched its published total to within one dollar; IDOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way