IDOT contract 61L35 bid tabulation

Hanover Park, section 24-00078-00-BT. Let by Illinois DOT on September 19, 2025, Cook, District 01. 6 bids received; low bid $1,344,596 by A Lamp Concrete Contractors, Inc..

Owner
Illinois DOT
Letting
19 SEP 2025
Pay items
101
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1A Lamp Concrete Contractors, Inc.$1,344,596Low
2Martam Construction Incorporated$1,528,287+14%
3R. W. Dunteman Company$1,595,784+19%
4Copenhaver Construction, Inc.$1,603,598+19%
5PirTano Construction Co., LLC$1,700,000+26%
6Alliance Contractors, Inc.$1,813,621+35%
IDOT contract 61L35: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. A Lamp Concrete Contractors, Inc.2. Martam Construction Incorporated3. R. W. Dunteman Company4. Copenhaver Construction, Inc.5. PirTano Construction Co., LLC6. Alliance Contractors, Inc.
1P PL ornament T gal P (K0012990)UNIT1$2,400.00$3,640.00$3,500.00$2,500.00$3,025.00$3,500.00
2Weed contr pre-EM GRN (K0029634)LB2$50.00$52.00$50.00$300.00$56.00$50.00
3Mulch placement 2 (K0036117)SY20$10.00$10.40$10.00$12.00$11.00$10.00
4Rem&rel GRD elec ser (XX009733)EACH1$3,600.00$3,744.00$3,600.00$4,700.00$1,975.00$3,600.00
5EM veh P S LSC 20 3C (X0324085)LF150$1.30$1.35$1.30$2.00$6.50$1.30
6Washout basin (X0326806)LS1$1,250.00$1,373.95$2,000.00$1,200.00$2,340.00$750.00
7Relocate bench (X0327149)EACH1$675.00$1,956.39$1,800.00$600.00$970.00$4,150.00
8Remove exstng BR pav (X0327989)SF9,133$1.60$3.05$4.10$3.00$3.00$4.00
9Ped signal post 10 FT (X1400367)EACH5$1,576.00$1,639.04$1,576.00$1,900.00$1,580.00$1,576.00
10Ped signal post 5 FT (X1400378)EACH3$1,352.00$1,406.08$1,352.00$1,600.00$1,210.00$1,352.00
11Stamp col PCC SDWLK 5 (X1700067)SF7,870$15.00$23.37$20.35$25.00$26.75$50.00
12Explor trench SPL (X2130010)LF100$10.00$45.09$52.30$20.00$170.00$20.00
13Temp access- com ent (X4022000)EACH2$500.00$985.66$480.00$200.00$2,330.00$1.00
14Sanitary manhole adj (X6026050)EACH1$1,300.00$1,355.96$1,150.00$1,500.00$2,075.00$695.00
15Intercept EX conduit (X8100863)EACH1$715.00$743.60$715.00$900.00$525.00$715.00
16Rebld EX DBL handhole (X8140238)EACH4$4,643.00$4,828.72$4,643.00$5,600.00$4,435.00$4,643.00
17APS ext bracket (X8760002)EACH1$438.00$455.52$438.00$500.00$315.00$438.00
18Accessible ped signal (X8760200)EACH22$2,406.00$2,502.24$2,406.00$2,800.00$2,225.00$2,406.00
19Conc FDN TY A 12D (X8780012)LF36$369.00$383.76$369.00$470.00$325.00$369.00
20Construction layout (Z0013798)LS1$13,900$17,046$13,900$17,000$30,000$13,900
21RE-optimize TR sig sys 1 (Z0033044)EACH5$1,340.00$1,393.60$1,340.00$1,800.00$615.00$1,340.00
22Trainees (Z0076600)HR500$0.80$0.80$0.80$0.80$0.80$0.80
23Trainees TPG (Z0076604)HR500$15.00$15.00$15.00$15.00$15.00$15.00
24Temporary fence (20101000)LF125$6.00$10.40$10.00$6.00$8.00$10.00
25Earth excavation (20200100)CY1,125$58.00$35.94$67.00$45.00$45.00$10.00
26Rem & disp uns matl (20201200)CY1,154$15.00$35.90$67.00$45.00$35.00$10.00
27Furnished excavation (20400800)CY26$1.00$65.43$108.50$10.00$1.00$20.00
28Topsoil F & P 4 (21101615)SY6,992$6.50$0.10$0.10$4.00$10.00$0.10
29Seeding CL 2A (25000210)ACRE1.50$5,500.00$25,168$24,200$6,000.00$3,100.00$24,200
30Nitrogen fert nutr (25000400)LB131$3.00$1.04$1.00$1.00$3.00$1.00
31Potassium fert nutr (25000600)LB131$3.00$1.04$1.00$1.00$3.00$1.00
32Erosion contr blanket (25100630)SY6,992$1.25$1.56$1.50$2.00$1.00$1.50
33Supple watering (25200200)UNIT1$100.00$260.00$250.00$0.01$28.00$250.00
34Temp eros contr seed (28000250)LB145$5.00$0.10$0.10$0.01$7.00$0.10
35Perimeter eros bar (28000400)LF3,092$1.00$2.86$2.75$3.00$2.25$2.75
36Inlet filters (28000510)EACH29$15.00$234.00$185.00$200.00$300.00$25.00
37Agg base cse B 4 (35101600)SY1,874$9.85$6.03$12.75$12.00$12.00$7.20
38Agg base cse B 8 (35102000)SY2,186$20.00$9.81$17.25$16.00$22.00$14.40
39HMA base cse 8 (35501316)SY182$61.00$176.05$80.00$120.00$121.50$100.80
40Preparation of base (35800100)SY4,395$0.01$1.56$1.50$3.00$3.50$1.90
41Bit matls PR CT (40600275)LB9,888$0.01$0.01$0.01$0.01$1.00$0.01
42HMA SC IL-9.5 D N50 (40604060)TON527$130.00$150.28$140.00$160.00$155.00$118.00
43PCC driveway pavt 8 (42300400)SY314$122.00$115.76$86.50$125.00$90.00$116.10
44PC conc sidewalk 5 (42400200)SF8,993$8.50$10.34$8.75$12.00$10.50$20.00
45Detectable warnings (42400800)SF447$35.00$43.12$37.25$35.00$46.00$40.00
46HMA surf rem 2 (44000157)SY2,442$8.50$7.80$13.96$9.00$5.00$20.00
47Drive pavement rem (44000200)SY472$16.50$10.21$27.50$16.00$21.00$20.00
48Comb curb gutter rem (44000500)LF912$8.25$5.18$16.00$8.00$9.00$15.00
49Sidewalk rem (44000600)SF8,785$1.00$1.84$2.50$2.00$4.00$2.00
50CL C patch T2 11 (44201365)SY26$275.00$267.56$345.00$190.00$350.00$260.00
51CL C patch T4 11 (44201371)SY338$140.00$210.69$256.00$155.00$240.00$237.25
52CL D patch T2 11 (44201777)SY10$330.00$250.19$258.00$200.00$775.00$1,100.00
53CL D patch T4 11 (44201783)SY106$125.00$245.19$120.00$190.00$330.00$274.00
54Fire hydnts to BE MVD (56400100)EACH6$6,500.00$5,324.52$9,450.00$5,000.00$6,050.00$8,732.00
55Man adjust (60255500)EACH5$425.00$808.47$550.00$600.00$1,250.00$350.00
56Inlets adj new T1F OL (60260300)EACH2$1,100.00$1,198.08$1,125.00$500.00$1,550.00$350.00
57VV adjust (60265700)EACH6$575.00$808.47$550.00$300.00$1,135.00$350.00
58FR & grates adjust (60300105)EACH3$450.00$808.48$465.00$500.00$1,135.00$350.00
59Conc curb TB (60600605)LF754$38.00$39.71$34.50$45.00$42.00$1.00
60Comb CC&G TB6.12 (60603800)LF274$44.00$56.99$37.00$39.00$45.00$139.75
61Comb CC&G TB6.18 (60604400)LF50$58.00$63.96$60.50$42.00$57.00$144.15
62Comb CC&G TY B-6.24 (60605000)LF537$52.00$67.10$45.00$40.00$52.00$145.80
63BCK SD prot of GRDRL (63000035)LF90$25.34$26.35$55.75$45.00$29.00$25.34
64Non SPL waste disposl (66900200)CY442$85.00$88.82$101.50$90.00$75.00$69.70
65Soil disposal analy (66900530)EACH3$850.00$884.00$850.00$1,600.00$1,000.00$1,500.00
66Reg sub P-const plan (66901001)LS1$5,200.00$5,408.00$5,200.00$4,000.00$1,500.00$4,200.00
67Reg sub F con report (66901003)LS1$500.00$520.00$500.00$2,500.00$1,000.00$500.00
68Reg sub mon (66901006)CAL DAY15$700.00$728.00$700.00$800.00$800.00$1,500.00
69Mobilization (67100100)LS1$80,640$91,697$101,000$103,000$102,000$122,893
70TR cont & prot 701606 (70102625)LS1$80,000$1.04$44,750$49,000$1.00$9,500.00
71TR cont & prot 701601 (70102630)LS1$1.00$75,460$10,460$100.00$28,000$1.00
72TR cont & prot 701701 (70102635)LS1$1.00$1.04$10,460$100.00$1.00$1.00
73TR cont & prot 701801 (70102640)LS1$1.00$1.04$2.05$1,000.00$11,673$1.00
74Mod ureth PM line 6 (78009006)LF2,101$1.90$1.98$1.90$2.00$2.50$1.90
75Mod ureth PM line 12 (78009012)LF2,571$3.30$3.43$3.30$4.00$7.50$3.30
76Mod ureth PM line 24 (78009024)LF22$6.00$6.24$6.00$7.00$14.00$6.00
77PVT MKG rem grinding (78300201)SF55$14.00$14.56$14.00$20.00$2.00$14.00
78Undrgrd C galvs 2 (81028200)LF148$30.60$31.82$30.60$40.00$50.00$30.60
79Undrgrd C galvs 3 (81028220)LF71$64.20$66.77$64.32$80.00$62.00$64.20
80Main EX TR sig instal (85000200)EACH5$4,800.00$4,992.00$4,800.00$6,200.00$6,215.00$4,800.00
81Elcbl C signal 14 2C (87301215)LF3,092$2.00$2.08$2.00$3.00$3.00$2.00
82Elcbl C signal 14 3C (87301225)LF2,505$2.20$2.29$2.20$3.00$3.00$2.20
83Elcbl C signal 14 5C (87301245)LF2,130$2.60$2.70$2.60$3.00$3.50$2.60
84Elcbl C signal 14 7C (87301255)LF219$3.00$3.12$3.00$4.00$4.00$3.00
85Elcbl C serv 6 2C (87301805)LF75$4.20$4.37$4.20$6.00$7.00$4.20
86Elcbl C egrdc 6 1C (87301900)LF457$2.80$2.91$2.80$4.00$4.00$2.80
87TS post 16 (87501200)EACH4$2,514.00$2,614.56$2,514.00$3,000.00$2,875.00$2,514.00
88STL comb maa&P 48 (87702970)EACH1$31,830$33,103$31,830$36,000$31,000$31,830
89Conc FDN TY A (87800100)LF20$322.80$335.71$322.80$400.00$350.00$322.80
90Conc FDN TY E 36D (87800415)LF13$622.50$647.40$622.50$780.00$485.00$622.50
91Drill EX handhole (87900200)EACH14$617.00$641.68$617.00$790.00$770.00$617.00
92Ped SH LED 1F BM CDT (88102717)EACH10$574.00$596.96$574.00$670.00$830.00$574.00
93Reloc EX sig head (89500100)EACH10$917.00$953.68$917.00$1,200.00$985.00$917.00
94Reloc EX ped sig head (89500200)EACH5$617.00$641.68$617.00$800.00$525.00$617.00
95Reloc EX TS post (89501150)EACH1$917.00$953.68$917.00$1,200.00$740.00$917.00
96Rel EM veh PR sys D U (89501400)EACH1$536.00$557.44$536.00$700.00$770.00$536.00
97Mod EX contr (89502200)EACH3$1,782.00$1,853.28$1,782.00$2,300.00$1,115.00$1,782.00
98Rem elcbl FR con (89502300)LF4,747$0.60$0.62$0.60$1.00$2.00$0.60
99Remov EX TS equip (89502375)EACH5$2,400.00$2,496.00$2,400.00$3,100.00$3,450.00$2,400.00
100Rebuild EX handhole (89502376)EACH6$3,493.00$3,632.72$3,493.00$4,400.00$2,935.00$3,493.00
101Remov EX conc FDN (89502385)EACH7$600.00$624.00$600.00$800.00$1,020.00$600.00
IDOT contract 61L35: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of September 19, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy