IDOT contract 62P01 bid tabulation
Section 2021-064-CR. Let by Illinois DOT on February 27, 2026, Will, District 01. 4 bids received; low bid $4,980,727 by Austin Tyler Construction, Inc..
- Owner
- Illinois DOT
- Letting
- 27 FEB 2026
- Pay items
- 131
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Austin Tyler Construction, Inc. | $4,980,727 | Low |
| 2 | D. Construction, Inc. | $5,055,284 | +1.0% |
| 3 | P. T. Ferro Construction Co. | $5,612,641 | +13% |
| 4 | Lorig Construction Company | $6,794,682 | +36% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Austin Tyler Construction, Inc. | 2. D. Construction, Inc. | 3. P. T. Ferro Construction Co. | 4. Lorig Construction Company |
|---|---|---|---|---|---|---|---|
| 1 | Mowing cycles (K1003660) | EACH | 12 | $2,600.00 | $2,860.00 | $8,400.00 | $2,600.00 |
| 2 | Weed CTRL NTV LSCP EN (X0327120) | ACRE | 13 | $900.00 | $990.00 | $1,280.00 | $900.00 |
| 3 | Rem temp LT con N sal (X1400279) | EACH | 2 | $1,000.00 | $1,100.00 | $1,000.00 | $1,000.00 |
| 4 | Tree remov acres SPL (X2010350) | ACRE | 1 | $8,500.00 | $9,350.00 | $8,500.00 | $8,500.00 |
| 5 | Stump removal only (X2010400) | UNIT | 423 | $5.00 | $5.50 | $5.00 | $5.00 |
| 6 | Seeding CL 4 mod (X2501800) | ACRE | 5 | $3,200.00 | $3,520.00 | $1,582.00 | $3,200.00 |
| 7 | Seeding CL 5 mod (X2501820) | ACRE | 5 | $3,500.00 | $3,850.00 | $2,573.00 | $3,500.00 |
| 8 | Mowing SPL (X2503110) | ACRE | 13 | $120.00 | $132.00 | $700.00 | $120.00 |
| 9 | Cofferdam typ 1 IS WW (X5021512) | EACH | 1 | $25,000 | $0.01 | $20,000 | $100.00 |
| 10 | SHT pile removal SP (X5220003) | SF | 1,167 | $15.00 | $12.50 | $1.00 | $1.00 |
| 11 | Memb WTRPRF sys B STR (X5810103) | SY | 298 | $43.00 | $48.00 | $45.00 | $45.00 |
| 12 | Shoulder rum strip RM (X6420100) | SY | 1,170 | $22.00 | $35.00 | $17.00 | $17.00 |
| 13 | Engrs FLD ofc TY A D1 (X6700407) | CAL MO | 12 | $2,500.00 | $5,000.00 | $1,000.00 | $3,800.00 |
| 14 | Traf cont & prot SPL (X7010216) | LS | 1 | $47,000 | $100,750 | $67,000 | $350,000 |
| 15 | Temp info signing (X7200061) | SF | 288 | $35.00 | $35.00 | $35.00 | $16.00 |
| 16 | RRPM reflector removl (X7830050) | EACH | 355 | $10.00 | $10.00 | $10.00 | $6.00 |
| 17 | RRPM reflector replac (X7830052) | EACH | 355 | $15.00 | $16.50 | $15.00 | $12.00 |
| 18 | Elect serv install SPL (X8040102) | EACH | 2 | $5,000.00 | $5,500.00 | $5,000.00 | $5,000.00 |
| 19 | Temp lum LED HGHMST I (X8211016) | EACH | 10 | $4,000.00 | $4,400.00 | $4,000.00 | $4,000.00 |
| 20 | Temp light controller (X8250060) | EACH | 2 | $10,000 | $11,000 | $10,000 | $10,000 |
| 21 | Temp WP 60 CL 4 (X8302161) | EACH | 2 | $4,000.00 | $4,400.00 | $4,000.00 | $4,000.00 |
| 22 | Temp TR signal timing (X8900104) | EACH | 1 | $3,000.00 | $3,300.00 | $3,000.00 | $3,000.00 |
| 23 | Stab constr entrance (Z0013797) | SY | 534 | $0.01 | $0.01 | $0.01 | $5.00 |
| 24 | Construction layout (Z0013798) | LS | 1 | $50,000 | $20,000 | $24,000 | $145,000 |
| 25 | Rock fill - foundatn (Z0054406) | CY | 160 | $80.00 | $60.00 | $150.00 | $180.00 |
| 26 | Temp pavement (Z0062456) | SY | 3,323 | $43.00 | $46.50 | $55.00 | $58.00 |
| 27 | Trainees (Z0076600) | HR | 500 | $0.80 | $0.80 | $0.80 | $0.80 |
| 28 | Trainees TPG (Z0076604) | HR | 500 | $15.00 | $15.00 | $15.00 | $15.00 |
| 29 | Temporary fence (20101000) | LF | 305 | $5.00 | $5.50 | $6.00 | $5.00 |
| 30 | Tree trunk protection (20101100) | EACH | 6 | $135.00 | $220.00 | $135.00 | $135.00 |
| 31 | Earth excavation (20200100) | CY | 25,951 | $21.00 | $28.00 | $33.00 | $32.00 |
| 32 | Furnished excavation (20400800) | CY | 2,137 | $25.00 | $0.01 | $28.00 | $27.00 |
| 33 | Topsoil exc & plac (21101505) | CY | 4,787 | $17.00 | $18.00 | $22.00 | $22.00 |
| 34 | Nitrogen fert nutr (25000400) | LB | 1,988 | $3.00 | $3.30 | $3.00 | $3.00 |
| 35 | Potassium fert nutr (25000600) | LB | 1,988 | $3.00 | $3.30 | $3.00 | $3.00 |
| 36 | Interseed CL 1B (25003115) | ACRE | 9 | $1,600.00 | $1,760.00 | $2,657.00 | $1,600.00 |
| 37 | Interseed CL 2A (25003210) | ACRE | 5 | $1,600.00 | $1,760.00 | $1,858.00 | $1,600.00 |
| 38 | Interseed CL 4A (25003312) | ACRE | 4 | $1,900.00 | $2,090.00 | $1,791.00 | $1,900.00 |
| 39 | Interseed CL 5A (25003322) | ACRE | 4 | $2,400.00 | $2,640.00 | $2,102.00 | $2,400.00 |
| 40 | Erosion contr blanket (25100630) | SY | 61,987 | $1.10 | $1.21 | $1.40 | $1.10 |
| 41 | Wildlife friendly ecb (25100645) | SY | 44,787 | $1.60 | $1.76 | $1.70 | $1.60 |
| 42 | Temp eros contr seed (28000250) | LB | 1,281 | $1.00 | $1.10 | $3.00 | $1.00 |
| 43 | Temp ditch checks (28000305) | LF | 2,460 | $8.00 | $8.80 | $4.00 | $8.00 |
| 44 | Agg ditch checks (28000315) | TON | 9 | $250.00 | $275.00 | $250.00 | $250.00 |
| 45 | Perimeter eros bar (28000400) | LF | 9,613 | $2.50 | $2.75 | $2.00 | $2.50 |
| 46 | Inlet & pipe protect (28000500) | EACH | 10 | $150.00 | $165.00 | $62.00 | $150.00 |
| 47 | Stone riprap CL A4 (28100107) | SY | 2,048 | $46.00 | $75.00 | $90.00 | $161.00 |
| 48 | Stone riprap CL A5 (28100109) | SY | 129 | $110.00 | $85.00 | $130.00 | $225.00 |
| 49 | Filter fabric (28200200) | SY | 2,102 | $2.50 | $5.00 | $4.50 | $3.25 |
| 50 | Agg subgrade improve (30300001) | CY | 100 | $32.00 | $60.00 | $38.00 | $60.00 |
| 51 | Agg subgrade impr 12 (30300112) | SY | 938 | $14.75 | $22.00 | $29.00 | $40.00 |
| 52 | Sub gran mat B 4 (31101200) | SY | 3,323 | $7.25 | $8.00 | $12.50 | $12.00 |
| 53 | Sub gran mat C 4 (31102100) | SY | 158 | $16.00 | $8.00 | $10.50 | $18.00 |
| 54 | Sub gran mat C 6 (31102300) | SY | 57 | $26.00 | $12.00 | $16.00 | $32.00 |
| 55 | HMA base cse 10 (35501324) | SY | 379 | $52.00 | $67.00 | $65.00 | $67.00 |
| 56 | P HMA SC IL-9.5 E N70 (40604172) | TON | 43 | $170.00 | $150.00 | $170.00 | $160.00 |
| 57 | PCC PVT 15 jointed (42000570) | SY | 342 | $170.00 | $180.00 | $135.00 | $260.00 |
| 58 | Pavement rem (44000100) | SY | 4,069 | $12.00 | $15.00 | $13.50 | $13.00 |
| 59 | Conc barrier remov (44001980) | LF | 80 | $8.50 | $50.00 | $22.50 | $20.00 |
| 60 | Paved SHLD removal (44004250) | SY | 252 | $8.00 | $15.00 | $18.00 | $17.00 |
| 61 | Dowel bars 1 1/4 (44201298) | EACH | 48 | $70.00 | $20.00 | $20.00 | $33.00 |
| 62 | Aggregate SHLDS B 6 (48101500) | SY | 576 | $16.00 | $14.00 | $15.00 | $25.00 |
| 63 | HMA shoulders 8 (48203029) | SY | 158 | $54.00 | $55.00 | $75.00 | $75.00 |
| 64 | PCC shoulders 9 (48300400) | SY | 57 | $150.00 | $120.00 | $95.00 | $185.00 |
| 65 | Rem exist struct (50100100) | EACH | 1 | $25,000 | $30,000 | $100,000 | $600,000 |
| 66 | Pipe culvert remov (50105220) | LF | 891 | $30.00 | $20.00 | $25.00 | $28.00 |
| 67 | Structure excavation (50200100) | CY | 29 | $55.00 | $50.00 | $100.00 | $125.00 |
| 68 | Rem/disp uns matl-STR (50200450) | CY | 160 | $55.00 | $40.00 | $50.00 | $135.00 |
| 69 | Conc struct (50300225) | CY | 31.90 | $1,600.00 | $1,000.00 | $2,700.00 | $2,300.00 |
| 70 | Conc sup-STR (50300255) | CY | 65 | $1,250.00 | $1,200.00 | $1,600.00 | $1,300.00 |
| 71 | Protective coat (50300300) | SY | 144 | $3.50 | $2.00 | $5.00 | $5.00 |
| 72 | Stud shear connectors (50500505) | EACH | 105 | $40.00 | $8.00 | $30.00 | $28.00 |
| 73 | Reinf bars, epoxy CTD (50800205) | LB | 92,210 | $1.65 | $2.00 | $1.90 | $1.75 |
| 74 | Bicycle railing (50901720) | LF | 51 | $340.00 | $374.00 | $438.00 | $340.00 |
| 75 | Parapet railing (50901750) | LF | 128 | $110.00 | $121.00 | $178.00 | $110.00 |
| 76 | Name plates (51500100) | EACH | 2 | $800.00 | $1,500.00 | $1,000.00 | $1,100.00 |
| 77 | Temp SHT piling (52200010) | SF | 3,537 | $53.00 | $25.00 | $1.00 | $1.00 |
| 78 | Fur soldier piles WS (52200105) | LF | 550 | $360.00 | $346.88 | $375.00 | $330.00 |
| 79 | Drill set SLD PI soil (52200200) | CF | 4,235 | $28.00 | $35.00 | $40.00 | $35.00 |
| 80 | Untreated timber lag (52200250) | SF | 662.50 | $40.00 | $25.00 | $24.00 | $23.00 |
| 81 | Conc box cul (54003000) | CY | 261.50 | $1,850.00 | $1,200.00 | $2,000.00 | $1,700.00 |
| 82 | PCBC 12X9 (54011209) | LF | 185 | $1,450.00 | $1,875.00 | $1,850.00 | $2,600.00 |
| 83 | P cul CL D 1 15 temp (5421D015) | LF | 891 | $65.00 | $90.00 | $70.00 | $105.00 |
| 84 | PRC flar end sec 15 (54213660) | EACH | 2 | $1,600.00 | $1,200.00 | $1,150.00 | $1,100.00 |
| 85 | Storm sew CL A 2 15 (550A0360) | LF | 12 | $130.00 | $100.00 | $105.00 | $105.00 |
| 86 | Granular backfill STR (58600101) | CY | 33 | $165.00 | $50.00 | $100.00 | $150.00 |
| 87 | Concrete sealer (58700300) | SF | 850 | $1.50 | $2.00 | $6.00 | $6.00 |
| 88 | Geocomposite wall DR (59100100) | SY | 379 | $31.00 | $35.00 | $30.00 | $37.00 |
| 89 | CB TA 4 dia T8G (60200805) | EACH | 2 | $2,900.00 | $4,300.00 | $3,800.00 | $3,600.00 |
| 90 | Remov catch bas (60500050) | EACH | 1 | $1,200.00 | $1,000.00 | $300.00 | $300.00 |
| 91 | SPBGR TY A 6FT posts (63000001) | LF | 775 | $33.00 | $35.75 | $31.00 | $33.00 |
| 92 | Traf bar term T2 (63100045) | EACH | 2 | $1,600.00 | $1,760.00 | $1,980.00 | $1,600.00 |
| 93 | Traf bar term T6B (63100089) | EACH | 2 | $4,800.00 | $5,280.00 | $4,300.00 | $4,800.00 |
| 94 | TR bar TRM T1 SPL tan (63100167) | EACH | 2 | $4,000.00 | $4,400.00 | $3,860.00 | $4,000.00 |
| 95 | Guardrail remov (63200310) | LF | 1,107 | $5.00 | $5.50 | $6.00 | $5.00 |
| 96 | Mod glar SCR sys temp (63800920) | LF | 3,013 | $8.00 | $9.00 | $12.50 | $15.00 |
| 97 | Shoulder rum strip 8 (64200108) | LF | 3,172 | $3.85 | $3.80 | $4.50 | $3.25 |
| 98 | Non SPL waste disposl (66900200) | CY | 6,220 | $64.00 | $65.00 | $70.00 | $70.00 |
| 99 | Soil disposal analy (66900530) | EACH | 3 | $800.00 | $1,815.00 | $1,450.00 | $1,500.00 |
| 100 | Reg sub P-const plan (66901001) | LS | 1 | $5,800.00 | $2,750.00 | $3,100.00 | $3,100.00 |
| 101 | Reg sub F con report (66901003) | LS | 1 | $500.00 | $2,750.00 | $1,200.00 | $1,200.00 |
| 102 | Reg sub mon (66901006) | CAL DAY | 60 | $715.00 | $880.00 | $1.00 | $1,000.00 |
| 103 | Mobilization (67100100) | LS | 1 | $315,000 | $75,001 | $335,000 | $360,000 |
| 104 | Changeable message SN (70107025) | CAL DAY | 568 | $30.00 | $40.00 | $30.00 | $35.00 |
| 105 | SHRT TRM pavt MK rem (70300150) | SF | 15,286 | $1.00 | $3.00 | $1.00 | $0.25 |
| 106 | Temp PVT MK LTR & sym T4 tape (70307100) | SF | 42 | $9.00 | $25.00 | $9.00 | $1.75 |
| 107 | Temp PVT MK L4 T4 tape (70307120) | LF | 42,978 | $1.55 | $3.00 | $0.01 | $1.35 |
| 108 | Temp PVT MK L6 T4 tape (70307130) | LF | 2,121 | $2.00 | $5.00 | $2.00 | $2.00 |
| 109 | Temp conc barrier (70400100) | LF | 3,013 | $27.00 | $25.00 | $25.00 | $26.00 |
| 110 | Rel temp conc barrier (70400200) | LF | 2,963 | $18.00 | $15.00 | $10.50 | $3.25 |
| 111 | Imp attn temp sun TL3 (70600280) | EACH | 3 | $8,500.00 | $10,000 | $5,892.00 | $12,000 |
| 112 | Imp attn rel FRD TL3 (70600330) | EACH | 2 | $2,850.00 | $2,200.00 | $2,730.00 | $3,000.00 |
| 113 | Terminal marker - DA (72501000) | EACH | 2 | $50.00 | $55.00 | $50.00 | $50.00 |
| 114 | THPL PVT MK LTR & sym (78000100) | SF | 182 | $7.00 | $7.70 | $7.00 | $6.00 |
| 115 | THPL PVT MK line 4 (78000200) | LF | 3,452 | $1.25 | $1.38 | $1.25 | $1.00 |
| 116 | THPL PVT MK line 6 (78000400) | LF | 743 | $1.75 | $1.93 | $1.75 | $1.50 |
| 117 | THPL PVT MK line 12 (78000600) | LF | 112 | $3.50 | $3.85 | $3.50 | $3.00 |
| 118 | Mod ureth PM LTR-sym (78009000) | SF | 109 | $5.00 | $5.50 | $5.00 | $9.00 |
| 119 | Mod ureth PM line 4 (78009004) | LF | 29,509 | $0.65 | $0.72 | $0.65 | $0.71 |
| 120 | Mod ureth PM line 6 (78009006) | LF | 516 | $1.00 | $1.10 | $1.00 | $1.80 |
| 121 | Mod ureth PM line 24 (78009024) | LF | 95 | $5.00 | $5.50 | $5.00 | $9.00 |
| 122 | Raised refl pavt MKR (78100100) | EACH | 7 | $315.00 | $346.50 | $315.00 | $500.00 |
| 123 | Grdrail ref type A (78200005) | EACH | 10 | $75.00 | $11.00 | $15.00 | $10.00 |
| 124 | Raised ref PVT MK rem (78300200) | EACH | 7 | $118.00 | $20.00 | $50.00 | $50.00 |
| 125 | PVT MKG rem WTR blast (78300202) | SF | 12,209.50 | $1.00 | $1.10 | $1.00 | $1.35 |
| 126 | Undrgrd C galvs 2 (81028200) | LF | 300 | $45.00 | $49.50 | $45.00 | $45.00 |
| 127 | A CBL 3-1C6 mess wire (81800330) | LF | 1,700 | $20.00 | $22.00 | $20.00 | $20.00 |
| 128 | LT P WD 80 CL3 15MA (83057435) | EACH | 10 | $16,500 | $18,150 | $16,500 | $16,500 |
| 129 | Rem temp light unit (84100110) | EACH | 10 | $3,000.00 | $3,300.00 | $3,000.00 | $3,000.00 |
| 130 | Remov elect serv inst (84500120) | EACH | 2 | $1,000.00 | $1,100.00 | $1,000.00 | $1,000.00 |
| 131 | Elcbl C serv 6 3C (87301815) | LF | 350 | $15.00 | $16.50 | $15.00 | $15.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of February 27, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.