INDOT contract B-44359-A bid tabulation

BRIDGE REPLACEMENT. Let by Indiana DOT on February 12, 2025, Shelby, Greenfield. 9 bids received; low bid $2,552,348 by His Constructors Inc.

Owner
Indiana DOT
Letting
12 FEB 2025
Pay items
108
Data through
05 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1His Constructors Inc$2,552,348Low
2Duncan Robertson Inc$2,777,663+9.0%
3Force Construction Co Inc$2,780,113+9.0%
4Rieth-Riley Construction Co., Inc.$2,808,740+10%
5Milestone Contractors LP$2,869,000+12%
6Paul H Rohe Company Inc$2,958,945+16%
7Dave Omara Contractor Inc$3,040,805+19%
8Beaty Construction Inc$3,274,566+28%
9E & B Paving LLC$3,545,000+39%
INDOT contract B-44359-A: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. His Constructors Inc2. Duncan Robertson Inc3. Force Construction Co Inc4. Rieth-Riley Construction Co., Inc.5. Milestone Contractors LP6. Paul H Rohe Company Inc
0001Construction engineering (105-06845)LS1$23,979$20,000$18,730$17,500$18,200$19,300
0002Liquidated damages (109-08359)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0003Contract liens (109-08360)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0004Quality adjustments, HMA (109-08440)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0005Quality adjustments, temporary traffic control devices (109-08443)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0006Quality adjustments, failed materials (109-08444)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0007Payment adjustment, PG asphalt binder (109-09489)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0008Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0009Mobilization and demobilization (110-01001)LS1$113,846$130,000$138,000$224,699$144,000$147,930
0010Clearing right-of-way (201-52370)LS1$44,900$80,000$21,730$84,262$85,000$19,320
0011Pavement removal (202-02240)SYS789$31.35$50.00$26.00$18.52$30.00$24.00
0012Present structure, remove, structure no. 1 (202-51330)LS1$176,110$250,000$144,280$275,771$311,539$104,745
0013Pipe, remove (202-96133)LFT132$44.19$40.00$57.00$26.52$36.00$46.00
0014Fence, farm field, remove (202-99187)LFT98$3.73$3.30$4.10$11.49$3.00$10.00
0015Excavation, common (203-02000)CYS670$32.11$35.00$51.00$66.77$45.00$100.00
0016Borrow (203-02070)CYS375$60.96$1.00$36.00$0.01$1.00$94.00
0017Excavation, waterway (203-51223)CYS400$60.47$65.00$48.00$60.34$49.00$50.00
0018Stormwater management budget (205-12108)DOL15,700$1.00$1.00$1.00$1.00$1.00$1.00
0019Stormwater management implementation (205-12616)LS1$83,600$22,500$10,810$19,535$2,100.00$3,500.00
0020SWQCP preparation (205-12618)LS1$35,709$3,000.00$3,087.00$3,490.30$1,700.00$2,500.00
0021Excavation, wet (206-51220)CYS110$52.69$120.00$71.00$78.95$68.00$100.00
0022Excavation, dry (206-51225)CYS60$54.59$85.00$53.00$98.97$54.00$100.00
0023Cofferdam (206-51235)LS1$105,944$50,000$298,210$181,245$119,000$411,030
0024Subgrade treatment, type II (207-08264)SYS43$67.69$20.00$59.00$92.99$56.00$70.00
0025Subgrade treatment, type IC (207-09935)SYS1,459$27.29$60.00$33.00$37.65$30.50$45.00
0026B borrow (211-02050)CYS195$59.96$15.00$67.00$98.25$68.00$110.00
0027Aggregate for end bent backfill (211-06467)CYS28$226.79$165.00$141.00$363.56$265.00$120.00
0028Structure backfill, type 2 (211-09265)CYS36$129.18$165.00$100.00$56.04$142.00$90.00
0029Geotextile for pavement, type 2B (214-12239)SYS1,492$4.28$6.00$4.60$2.76$3.05$4.00
0030Compacted aggregate, no. 8 (301-12233)CYS20$153.46$150.00$117.00$143.41$128.00$120.00
0031Compacted aggregate, no. 53 (301-12234)CYS185$93.57$145.00$85.00$128.20$76.00$100.00
0032Subbase for PCCP (302-06464)CYS62$134.66$170.00$155.00$132.13$185.00$140.00
0033Compacted aggregate, no. 53 (303-01180)TON260$34.16$55.00$59.00$63.92$70.00$68.00
0034Compacted aggregate, no. 53, temporary for driveways (303-08210)TON334$43.20$25.00$51.00$61.41$41.00$72.00
0035Milling, transition (306-08043)SYS160$41.91$40.00$23.00$31.28$32.00$12.00
0036QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005)TON106$191.33$137.00$129.00$226.54$185.00$220.00
0037QC/QA-HMA, 3, 58H, intermediate, 19.0 MM (401-000041)TON153$155.30$137.00$129.00$138.97$145.00$165.00
0038QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047)TON641$149.09$137.00$129.00$93.65$152.00$120.00
0039Joint adhesive, surface (401-10258)LFT905$0.62$0.55$0.50$0.77$1.45$0.60
0040Joint adhesive, intermediate (401-10259)LFT845$0.62$0.55$0.50$0.89$1.65$0.90
0041Liquid asphalt sealant (401-11785)LFT905$0.01$0.06$0.05$0.01$1.00$0.35
0042Asphalt for tack coat (406-05521)SYS3,424$1.24$0.55$0.50$0.01$1.00$0.70
0043Cracks in asphalt pavement, fill (408-12028)TON1$2,283.55$2,750.00$2,572.00$5,438.04$2,100.00$6,000.00
0044Terminal joint, type HMA (503-12477)LFT80$205.00$325.00$403.00$357.69$420.00$405.00
0045Guardrail transition, type TGB (601-01522)EACH2$3,721.02$3,295.00$2,572.00$2,500.00$2,995.00$2,500.00
0046Guardrail terminal system, W-beam curved, type 1 (601-01700)EACH1$3,634.05$3,218.00$3,087.00$3,000.00$2,925.00$3,000.00
0047Guardrail, W-beam, shop curved, 6 FT 3 in. spacing (601-02103)LFT13$49.70$44.00$37.00$36.00$40.00$36.00
0048Guardrail, remove (601-02241)LFT282$3.73$3.30$5.40$5.25$3.00$5.25
0049Curved terminal end (601-05999)EACH1$155.29$138.00$111.00$108.00$125.00$108.00
0050Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281)LFT32$23.61$22.00$22.00$21.00$19.00$21.00
0051Guardrail transition, MGS without curb (601-12292)EACH2$3,789.35$3,355.00$2,701.00$2,625.00$3,050.00$2,625.00
0052Guardrail end treatment, type OS (601-94689)EACH2$3,478.75$3,080.00$2,932.00$2,850.00$2,800.00$2,850.00
0053Barrier delineator (602-06729)EACH14$28.34$20.00$31.00$37.15$41.08$23.41
0054Fence, farm field, 47 in. (603-06040)LFT75$29.82$26.50$45.00$44.00$24.00$44.00
0055Reinforced concrete bridge approach, 12 in. (609-06259)SYS248$240.54$250.00$191.00$205.07$200.00$205.00
0056Mailbox assembly, single (611-06497)EACH1$260.91$230.00$283.00$275.00$210.00$275.00
0057Monument, type B (615-06505)EACH2$1,105.75$980.00$1,646.00$1,600.00$890.00$1,600.00
0058Riprap, class 1 (616-05688)TON678$89.65$110.00$106.00$108.60$91.00$78.00
0059Riprap, revetment (616-06405)TON109$73.73$65.00$51.00$138.61$115.00$140.00
0060Geotextile for riprap, type 1A (616-12246)SYS796$5.58$5.00$3.60$1.16$2.25$3.00
0061Mobilization and demobilization for seeding (621-01004)EACH1$807.57$770.00$720.00$1,500.00$1,500.00$1,500.00
0062Erosion control blanket (621-02770)SYS1,241$3.76$2.20$2.10$2.75$2.75$2.75
0063Water (621-06567)KGAL6$31.06$16.50$15.00$0.50$0.50$0.50
0064Sodding (621-06574)SYS53$70.44$52.00$49.00$90.00$90.00$90.00
0065Seed mixture, floodplain (621-12612)LBS18$172.70$120.00$113.00$225.00$225.00$225.00
0066Sign, "DO not mow or spray" (622-52436)EACH4$105.61$110.00$98.00$130.00$130.00$130.00
0067Field office, type C (628-09403)MOS9$1,950.03$3,000.00$3,293.00$3,608.87$4,100.00$3,600.00
0068Plant growth layer (629-12029)SYS1,241$10.92$8.00$9.30$10.31$5.00$15.50
0069Dynamic pile load test (701-06011)EACH2$8,079.26$2,000.00$5,499.00$4,264.02$12,600$3,140.00
0070Test pile, dynamic, production (701-09557)LFT105$43.43$90.00$155.00$52.19$53.00$225.00
0071Test pile, dynamic, restrike (701-09559)EACH2$7,458.05$2,000.00$2,749.00$1,885.21$4,600.00$3,250.00
0072Pile, steel pipe, 0.375 in., diameter 14 in. (701-09665)LFT1,359$106.35$100.00$72.00$61.83$120.00$112.00
0073Conical pile tip, 14 in. (701-09679)EACH34$549.15$600.00$360.00$371.50$410.00$425.00
0074Concrete, A, substructure (702-51005)CYS177.20$880.86$1,000.00$1,485.00$1,290.12$1,435.00$1,295.00
0075Concrete, B, footings (702-51015)CYS8.90$2,084.67$700.00$1,228.00$1,743.95$3,050.00$1,000.00
0076Concrete, C, substructure (702-92857)CYS44.40$1,780.16$1,500.00$1,182.00$1,292.45$1,323.00$1,750.00
0077Reinforcing bars (703-06028)LBS15,407$1.38$1.50$1.40$1.14$1.30$1.09
0078Reinforcing bars, epoxy coated (703-06029)LBS112,678$1.36$1.50$1.20$1.21$1.55$1.22
0079Threaded tie bar assembly, epoxy coated (703-97936)EACH40$110.09$75.00$46.00$62.83$45.00$100.00
0080Concrete, C, superstructure (704-51002)CYS269.20$989.48$950.00$1,067.00$1,191.52$1,180.00$1,250.00
0081Railing, concrete type FC (706-11600)CYS35.20$888.32$1,000.00$736.00$715.00$715.00$715.00
0082Concrete bridge railing transition, type TFC (706-11620)EACH4$1,497.10$2,500.00$1,240.00$1,205.00$1,205.00$1,205.00
0083Structural member, concrete, box beam, 27 in. X 48 in. (707-09862)LFT990$279.90$475.00$327.00$281.39$330.00$330.00
0084Surface seal STR. no. 1 (709-51821)LS1$3,205.42$4,000.00$1.00$1.00$0.01$6,200.00
0085Anchor plate (711-02707)EACH20$80.76$150.00$500.00$147.52$335.00$445.00
0086Pipe, type 3, circular, diameter 36 in. (715-05177)LFT111$112.67$150.00$140.00$195.61$90.00$190.00
0087Pipe, end bent drain, diameter 6 in. (715-05407)LFT120$20.15$18.00$19.00$38.10$22.00$80.00
0088Pipe end section, diameter 36 in. (715-46040)EACH1$2,942.82$2,000.00$2,140.00$2,070.18$1,600.00$1,800.00
0089Geotextile for underdrains, type 1A (718-12305)SYS90$9.68$4.00$3.10$1.70$3.25$7.00
0090Automatic drainage gate 36" diameter (721-09548)EACH1$35,507$20,000$24,160$27,225$33,000$28,225
0091Longitudinal grooving (722-12732)SYS1,123$4.35$9.00$4.10$4.34$8.50$3.50
0092Bearing assembly, elastomeric (726-92406)EACH40$552.17$350.00$194.00$424.66$450.00$165.50
0093Road closure sign assembly (801-04308)EACH9$325.51$275.00$269.00$262.00$261.00$261.00
0094Detour route marker assembly (801-06625)EACH42$188.85$94.00$158.00$152.00$154.00$154.00
0095Construction sign, type A (801-06640)EACH8$279.54$220.00$238.00$225.00$231.00$231.00
0096Construction sign, type B (801-06645)EACH2$80.76$110.00$119.00$65.00$116.00$116.00
0097Maintaining traffic (801-06775)LS1$6,833.25$45,000$161,000$25,000$15,000$29,585
0098Barricade, type III-A (801-07118)LFT64$14.91$22.00$17.00$12.00$16.88$16.88
0099Barricade, type III-B (801-07119)LFT64$18.64$22.00$17.00$15.00$16.88$16.88
0100Sign post, square, type 1, reinforced anchor base (802-05701)LFT70$33.55$30.00$19.00$18.00$27.00$18.00
0101Sign post, square, type 2, reinforced anchor base (802-05702)LFT29$31.06$27.50$15.00$15.00$25.00$15.00
0102Sign, sheet, relocate (802-07060)EACH8$310.60$275.00$317.00$308.00$250.00$308.00
0103Line, multi-component, solid, white, 6 in. (808-10049)LFT1,122$2.48$2.20$1.20$5.66$1.16$1.16
0104Line, multi-component, solid, yellow, 6 in. (808-10057)LFT561$2.48$2.20$1.20$5.66$1.16$1.16
0105Grooving for pavement markings (808-12032)LFT1,824$3.49$3.30$0.90$2.81$0.89$0.89
0106Line, multi-component, broken, yellow, 6 in. (808-12841)LFT141$2.48$2.20$2.20$5.66$2.18$2.18
0107Snowplowable raised pavement marker, remove (808-75996)EACH8$155.30$30.00$79.00$66.34$75.00$80.00
0108Snowplowable raised pavement marker (808-75998)EACH8$155.30$138.00$117.00$353.59$114.00$114.00
INDOT contract B-44359-A: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.

Every contract let that day: INDOT letting of February 12, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy