MoDOT contract 250919-H03 bid tabulation
J9S3691-ROUTE AF-WRIGHT COUNTY. Let by Missouri DOT on September 19, 2025, Wright, Southeast. 8 bids received; low bid $1,925,438 by Gene Haile Excavating, Inc..
- Owner
- Missouri DOT
- Letting
- 19 SEP 2025
- Pay items
- 56
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Gene Haile Excavating, Inc. | $1,925,438 | Low |
| 2 | West Plains Bridge & Grading, LLC | $1,993,000 | +4.0% |
| 3 | Mera Excavating, LLC | $2,053,699 | +7.0% |
| 4 | Hartman and Company, Inc. | $2,217,000 | +15% |
| 5 | Louis-Company, LLC | $2,232,407 | +16% |
| 6 | Capital Paving & Construction, LLC | $2,557,689 | +33% |
| 7 | Robertson Contractors, Inc. | $2,564,192 | +33% |
| 8 | KCI Construction Company | $3,192,950 | +66% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Gene Haile Excavating, Inc. | 2. West Plains Bridge & Grading, LLC | 3. Mera Excavating, LLC | 4. Hartman and Company, Inc. | 5. Louis-Company, LLC | 6. Capital Paving & Construction, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Removal of improvements (2022010) | LS | 1 | $110,000 | $3,000.00 | $8,942.85 | $11,100 | $12,000 | $131,000 |
| 0015 | Class A excavation (2031000) | CY | 205 | $25.00 | $25.00 | $1.64 | $24.20 | $24.69 | $20.00 |
| 0020 | Porous backfill (2064000) | CY | 54 | $115.00 | $150.00 | $5.50 | $167.00 | $81.11 | $150.00 |
| 0030 | Linear grading class 2 (2072000) | STA | 10.70 | $1,500.00 | $2,300.00 | $2,862.58 | $1,340.00 | $2,772.14 | $2,700.00 |
| 0040 | Type 1 aggregate for base (6 in. thick) (3040163) | SY | 873 | $20.50 | $18.50 | $20.75 | $21.50 | $18.18 | $13.00 |
| 0050 | Gravel (A) or crushed stone (B) (3105002) | TON | 100 | $51.50 | $46.00 | $60.48 | $102.00 | $20.56 | $39.00 |
| 0060 | Bituminous pavement mixture PG70-22, (BP-1) (4011207) | TON | 50.60 | $146.00 | $145.00 | $166.89 | $132.50 | $170.01 | $147.00 |
| 0070 | Misc.optional pavement (4019905) | SY | 873 | $96.50 | $100.00 | $109.03 | $91.00 | $112.08 | $101.00 |
| 0080 | Tack coat (4071005) | GAL | 44 | $3.50 | $5.50 | $5.75 | $5.00 | $3.97 | $6.00 |
| 0090 | Furnishing type 1 rock ditch liner (6096010A) | CY | 8 | $100.00 | $60.00 | $68.85 | $72.00 | $400.00 | $65.00 |
| 0100 | Placing type 1 rock ditch liner (6096041) | CY | 8 | $100.00 | $70.00 | $84.20 | $266.50 | $350.00 | $110.00 |
| 0110 | Furnishing type 2 rock blanket (6113020) | CY | 2,428 | $65.00 | $60.00 | $66.85 | $77.90 | $79.51 | $75.00 |
| 0120 | Placing type 2 rock blanket (6113040) | CY | 2,428 | $15.00 | $18.00 | $10.57 | $14.80 | $20.84 | $42.00 |
| 0130 | Construction signs (6161005) | SF | 373 | $8.00 | $7.75 | $8.79 | $10.00 | $8.82 | $11.50 |
| 0140 | Type 3 moveable barricade (6161030) | EACH | 6 | $250.00 | $160.00 | $191.40 | $200.00 | $182.60 | $250.00 |
| 0150 | Changeable message sign without communication interface, contractor furnished retained (6161098A) | EACH | 4 | $3,750.00 | $3,350.00 | $3,692.88 | $3,000.00 | $3,777.95 | $3,500.00 |
| 0160 | Mobilization (6181000) | LS | 1 | $250,000 | $134,063 | $161,662 | $265,052 | $160,000 | $188,000 |
| 0170 | 4 in. white class 1 pavement marking paint (18-mil, type P beads) (6206000D) | LF | 1,734 | $1.50 | $0.50 | $0.66 | $1.00 | $0.63 | $1.20 |
| 0180 | 4 in. yellow class 1 pavement marking paint (18-mil, type P beads) (6206001D) | LF | 1,200 | $1.50 | $0.52 | $0.71 | $1.00 | $0.65 | $1.20 |
| 0190 | Coldmilling bituminous pavement for removal of surfacing (3 in. thick or less) (6221001) | SY | 444 | $7.00 | $13.75 | $7.96 | $12.50 | $8.00 | $14.00 |
| 0200 | Permanent erosion control geotextile (6240103A) | SY | 2,305 | $3.00 | $3.50 | $1.59 | $5.70 | $2.91 | $4.25 |
| 0210 | Contractor furnished surveying and staking (6274000) | LS | 1 | $7,500.00 | $22,000 | $35,107 | $13,000 | $21,975 | $20,500 |
| 0220 | 18 in. pipe group C (7250418) | LF | 56 | $65.00 | $85.00 | $59.85 | $160.00 | $99.79 | $76.00 |
| 0230 | Mulching (8025006) | ACRE | 0.30 | $7,000.00 | $6,500.00 | $9,458.46 | $7,500.00 | $9,444.87 | $7,800.00 |
| 0240 | Seeding - cool season grasses (8051000A) | ACRE | 0.30 | $10,000 | $9,500.00 | $11,906 | $9,500.00 | $11,964 | $11,400 |
| 0250 | Rock ditch check (8061005) | LF | 48 | $20.00 | $16.00 | $17.28 | $30.00 | $37.78 | $50.00 |
| 0260 | Sediment removal (8061016) | CY | 14 | $20.00 | $6.00 | $11.93 | $478.50 | $210.87 | $20.00 |
| 0270 | Silt fence (8061019) | LF | 529 | $4.25 | $4.00 | $5.67 | $4.50 | $5.67 | $4.50 |
| 0280 | Type C berm (8061050) | LF | 396 | $20.00 | $35.00 | $13.46 | $20.00 | $25.19 | $20.00 |
| 0290 | Concrete footings, embedded (9031010) | CY | 1.60 | $500.00 | $750.00 | $970.21 | $500.00 | $3,500.00 | $1.00 |
| 0300 | Driven post anchor for 2 in. PSST - 12 GA. (9031271A) | EACH | 144 | $15.25 | $13.85 | $141.34 | $13.90 | $144.82 | $16.50 |
| 0310 | Concrete post anchor for 2 in. PSST. - 7 GA. (9031274) | EACH | 12 | $440.00 | $409.25 | $129.36 | $409.50 | $125.93 | $465.00 |
| 0320 | SHF-flat sheet fluorescent (9035069A) | SF | 36 | $26.00 | $23.25 | $48.83 | $23.30 | $47.85 | $26.00 |
| 0330 | Class 1 excavation (2061000) | CY | 85 | $50.00 | $50.00 | $27.96 | $77.80 | $50.00 | $155.00 |
| 0340 | Class 1 excavation in rock (2061003) | CY | 10 | $400.00 | $550.00 | $522.44 | $1,200.00 | $3,000.00 | $1,300.00 |
| 0350 | Removal of bridges (2160500) | LS | 1 | $65,000 | $80,000 | $191,895 | $48,500 | $165,000 | $310,000 |
| 0360 | Bridge approach slab (minor road) (5031011A) | SY | 109 | $120.00 | $210.00 | $182.14 | $101.50 | $448.26 | $155.00 |
| 0370 | Drilled shafts (4 FT. 0 in. dia.) (7011106) | LF | 47 | $950.00 | $1,100.00 | $1,229.26 | $1,230.00 | $1,674.11 | $1,455.00 |
| 0380 | Rock sockets (3 FT 6 in. dia.) (7011205) | LF | 26 | $850.00 | $1,175.00 | $2,049.95 | $1,610.00 | $755.59 | $1,150.00 |
| 0390 | Video camera inspection (7011300) | EACH | 2 | $400.00 | $250.00 | $1,620.73 | $500.00 | $2,000.00 | $2,700.00 |
| 0400 | Foundation inspection holes (7011400) | LF | 46 | $175.00 | $190.00 | $449.80 | $183.00 | $384.09 | $215.00 |
| 0410 | Sonic logging testing (7011600) | EACH | 2 | $1,500.00 | $3,400.00 | $5,145.85 | $4,340.00 | $2,801.98 | $1,400.00 |
| 0420 | Galvanized structural steel piles (12 in) (7021212) | LF | 156 | $210.00 | $150.00 | $160.18 | $138.50 | $143.86 | $155.00 |
| 0430 | Pre-bore for piling (7026000) | LF | 67 | $135.00 | $190.00 | $461.61 | $130.00 | $151.12 | $233.00 |
| 0440 | Pile point reinforcement (7027000) | EACH | 6 | $100.00 | $325.00 | $1,209.72 | $151.50 | $207.79 | $300.00 |
| 0450 | Class B concrete (substructure) (7032003) | CY | 87.30 | $1,100.00 | $1,800.00 | $1,286.77 | $2,210.00 | $2,200.00 | $1,600.00 |
| 0460 | Type D barrier (7034219A) | LF | 551 | $91.50 | $150.00 | $186.49 | $156.00 | $158.01 | $145.00 |
| 0470 | Slab on concrete NU-girder (7034221) | SY | 780 | $445.00 | $530.00 | $348.85 | $530.50 | $450.00 | $525.00 |
| 0480 | NU 63, prestressed concrete NU-girder (7056024) | LF | 781 | $460.00 | $525.00 | $513.20 | $554.50 | $515.92 | $565.00 |
| 0490 | Reinforcing steel (bridges) (7061060) | LB | 11,180 | $1.65 | $2.45 | $2.57 | $1.90 | $0.88 | $2.50 |
| 0500 | Reinforcing steel (epoxy coated) (7101000) | LB | 5,540 | $1.60 | $2.20 | $2.10 | $2.20 | $0.94 | $2.00 |
| 0510 | Steel intermediate diaphragm for P/S concrete girders (7123301) | EACH | 8 | $2,000.00 | $2,200.00 | $2,133.74 | $2,650.00 | $2,606.65 | $2,800.00 |
| 0520 | Slab drain (7123610) | EACH | 48 | $550.00 | $650.00 | $650.48 | $731.00 | $624.27 | $700.00 |
| 0530 | Vertical drain at end bents (7151001) | EACH | 2 | $3,000.00 | $1,750.00 | $2,515.01 | $4,320.00 | $2,701.32 | $5,100.00 |
| 0540 | Laminated neoprene bearing pad (7161002) | EACH | 9 | $240.00 | $300.00 | $279.38 | $537.00 | $300.98 | $320.00 |
| 0550 | Type N ptfe bearing (7163000) | EACH | 3 | $6,200.00 | $5,000.00 | $4,918.34 | $6,900.00 | $6,501.01 | $6,600.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of September 19, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.