B Anthony Construction Corp J/V A. Servidone Inc: NJDOT bid record
B Anthony Construction Corp J/V A. Servidone Inc submitted 10 bids on New Jersey DOT contracts in the data, from 19 OCT 2017 to 01 MAY 2025, and was the low bidder on 0 of them (0%). When it was not low, its total sat a median +35% above the low bid.
- Owner
- New Jersey DOT
- Low bid volume
- $0
- Latest bid
- 01 MAY 2025
- Data through
- 16 APR 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2017 | 2 | 0 | 0% |
| 2020 | 3 | 0 | 0% |
| 2021 | 2 | 0 | 0% |
| 2022 | 1 | 0 | 0% |
| 2024 | 1 | 0 | 0% |
| 2025 | 1 | 0 | 0% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| N1 | 8 | 0 | 0% |
| C1 | 2 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Fuel price adjustment | 160004M | DOL | 10 | 10 (100%) | $13,300 | $2,700.00 |
| Asphalt price adjustment | 160007M | DOL | 10 | 10 (100%) | $11,350 | $10,200 |
| Trainees | 153011M | HR | 8 | 7 (88%) | $1.00 | $1.00 |
| Reinforcement steel, epoxy- coated | 504006P | LB | 20 | 2 (10%) | $4.50 | $2.52 |
| Core samples, hot mix asphalt | 401108M | U | 10 | 2 (20%) | $225.00 | $150.00 |
| Tack coat | 401030M | GAL | 9 | 2 (22%) | $3.50 | $1.00 |
| Fertilizing and seeding, type F | 806018P | SY | 9 | 2 (22%) | $2.50 | $2.10 |
| Prime coat | 401036M | GAL | 8 | 2 (25%) | $1.00 | $0.01 |
| Inlet, type E | 602018M | U | 7 | 2 (29%) | $3,800.00 | $6,000.00 |
| Concrete compression testing equipment | 156021M | U | 6 | 2 (33%) | $5,900.00 | $9,444.00 |
| Wood mulching | 809018M | SY | 5 | 2 (40%) | $6.00 | $7.00 |
| Reinforcement steel | 504003P | LB | 5 | 2 (40%) | $2.00 | $1.95 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Anselmi & Decicco, Inc. | 9 | 5 of 9 |
| Union Paving & Construction Co., Inc. | 8 | 8 of 8 |
| Carbro Constructors Corp. | 6 | 5 of 6 |
| Konkus Corporation | 5 | 5 of 5 |
| Iew Construction Group, Inc. | 5 | 2 of 5 |
| Ferreira Construction Co., Inc. | 5 | 3 of 5 |
| Joseph M. Sanzari, Inc. | 4 | 3 of 4 |
| J. Fletcher Creamer & Son, Inc. | 4 | 2 of 4 |
| Mount Construction Co., Inc. | 4 | 2 of 4 |
| Ritacco Construction, Inc. | 3 | 3 of 3 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 01 MAY 2025 | 25102 | N1 | Rt 46 Bridge over Paulins Kill | 6 of 10 | $27,555,505 | +28% |
| 11 APR 2024 | 24103 | N1 | Rt 15 Corridor, Rockfall Mitigation, Contract A | 7 of 7 | $14,972,851 | +52% |
| 06 JAN 2022 | 21140 | N1 | Weldon Road Over Route 15 Superstructure Replacement | 8 of 8 | $11,577,251 | +53% |
| 03 JUN 2021 | 21113 | N1 | Route 22 / Route 82 / Garden State Parkway Interchange | 7 of 7 | $50,989,982 | +25% |
| 18 MAR 2021 | 21105 | N1 | Route 280 Rockfall Mitigation, West Orange Township | 2 of 7 | $6,216,232 | +11% |
| 12 NOV 2020 | 20133 | N1 | I-80 Rockfall Mitigation | 6 of 6 | $3,995,554 | +24% |
| 15 OCT 2020 | 20131 | N1 | Route 206 Doctors Way to Valley Road | 9 of 9 | $62,279,064 | +49% |
| 02 JUL 2020 | 20122 | N1 | Route 78 Rockfall Mitigation | 5 of 14 | $31,697,854 | +42% |
| 30 NOV 2017 | 17144 | C1 | ROUTE US 206 BYPASS - CONTRACT B SEC 14A & 15A | 6 of 13 | $44,492,458 | +21% |
| 19 OCT 2017 | 17147 | C1 | ROUTE 35, PERTH AMBOY CONNECTOR BRIDGE REPLACEMENT | 6 of 11 | $13,947,117 | +41% |
How this record was read
NJDOT bid tabulation PDFs linked from its 2018 to 2026 award pages (lettings from June 2017 to April 2026). Bids on redacted tabulations with scanned pages could not be read and are left out, as are bids that did not match their published total. Some maintenance contracts price an adjustment factor (unit PCT): published as is, not a unit price.
- Every bid counted here matched its published total to within one dollar; NJDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.