NCDOT contract C204835 bid tabulation
GRADING, DRAINAGE, PAVING, AND CULVERT. NC-45 FROM WASHINGTON COUNTY LINE TO US-17. Let by North Carolina DOT on January 21, 2025, Bertie. 3 bids received; low bid $11,778,894 by FSC II LLC DBA Fred Smith Company.
- Owner
- North Carolina DOT
- Letting
- 21 JAN 2025
- Pay items
- 121
- Data through
- 20 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | FSC II LLC DBA Fred Smith Company | $11,778,894 | Low |
| 2 | Barnhill Contracting Company | $12,077,729 | +3.0% |
| 3 | Trader Construction Co. | $13,088,608 | +11% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. FSC II LLC DBA Fred Smith Company | 2. Barnhill Contracting Company | 3. Trader Construction Co. |
|---|---|---|---|---|---|---|
| 0001 | Mobilization (0000100000-N) | LS | 1 | $580,000 | $603,000 | $655,000 |
| 0002 | Construction surveying (0000400000-N) | LS | 1 | $350,000 | $750,000 | $230,000 |
| 0004 | Supplementary clearing & grubbing (0050000000-E) | ACRE | 1 | $1,000.00 | $10,000 | $1,000.00 |
| 0005 | Undercut excavation (0057000000-E) | CY | 1,000 | $25.00 | $15.00 | $35.00 |
| 0006 | Drainage ditch excavation (0134000000-E) | CY | 30 | $80.00 | $38.50 | $25.00 |
| 0007 | Select granular material (0195000000-E) | CY | 1,000 | $25.00 | $32.53 | $100.00 |
| 0008 | Geotextile for soil stabilization (0196000000-E) | SY | 1,000 | $4.25 | $4.00 | $6.30 |
| 0009 | Temporary shoring (0199000000-E) | SF | 16,000 | $40.00 | $100.00 | $114.00 |
| 0010 | Foundation conditioning material, minor structures (0318000000-E) | TON | 533 | $65.00 | $65.00 | $60.00 |
| 0011 | FND condit geotextile (4A) (0321000000-E) | SY | 985 | $5.00 | $5.00 | $6.00 |
| 0012 | ***" RCP culv class IV - (54") (0448000000-E) | LF | 224 | $601.00 | $601.00 | $712.00 |
| 0013 | 18" RC pipe culverts, class IV (0448300000-E) | LF | 244 | $116.00 | $116.00 | $303.00 |
| 0014 | 24" RC pipe culverts, class IV (0448400000-E) | LF | 636 | $170.00 | $170.00 | $327.00 |
| 0015 | 30" RC pipe culverts, class IV (0448500000-E) | LF | 344 | $240.00 | $240.00 | $380.00 |
| 0016 | 36" RC pipe culverts, class IV (0448600000-E) | LF | 160 | $341.00 | $341.00 | $422.00 |
| 0017 | 42" RC pipe culverts, class IV (0448700000-E) | LF | 64 | $427.00 | $427.00 | $545.00 |
| 0018 | **" RC pipe culv class V - (18") (0449000000-E) | LF | 172 | $145.00 | $145.00 | $410.00 |
| 0019 | **" RC pipe culv class V - (24") (0449000000-E) | LF | 60 | $215.00 | $215.00 | $400.00 |
| 0020 | **" RC pipe culv class V - (30") (0449000000-E) | LF | 84 | $301.00 | $301.00 | $430.00 |
| 0021 | **" RC pipe culv class V - (36") (0449000000-E) | LF | 60 | $416.00 | $416.00 | $600.00 |
| 0022 | **" RC pipe culv class V - (66") (0449000000-E) | LF | 56 | $1,200.00 | $1,200.00 | $1,310.00 |
| 0023 | Shallow undercut (1099500000-E) | CY | 500 | $30.00 | $25.00 | $20.00 |
| 0024 | Class IV subgrade stabilization (1099700000-E) | TON | 950 | $45.00 | $54.00 | $65.00 |
| 0025 | Geotextile for subgrade stabilization (1112000000-E) | SY | 1,500 | $4.75 | $4.00 | $6.00 |
| 0026 | Aggregate base course (1121000000-E) | TON | 13,000 | $40.00 | $45.25 | $57.00 |
| 0027 | Incidental stone base (1220000000-E) | TON | 200 | $77.00 | $120.00 | $50.00 |
| 0028 | Prime coat (1275000000-E) | GAL | 3,445 | $4.00 | $1.00 | $9.75 |
| 0029 | Mill asp PVMT *****" DTH - (1-1/2") (1297000000-E) | SY | 109,240 | $2.00 | $2.60 | $2.15 |
| 0030 | Asphalt conc surface course, type S9.5B (1519000000-E) | TON | 14,800 | $69.00 | $70.50 | $80.00 |
| 0031 | Asphalt binder for plant mix (1575000000-E) | TON | 965 | $500.00 | $558.35 | $600.00 |
| 0032 | Asphalt plant mix, pavement repair (1693000000-E) | TON | 240 | $225.00 | $250.00 | $285.00 |
| 0033 | Subdrain excavation (2022000000-E) | CY | 112 | $20.00 | $1.50 | $15.00 |
| 0034 | Geotextile for subsurface drains (2026000000-E) | SY | 500 | $3.00 | $1.00 | $6.00 |
| 0035 | Subdrain coarse aggregate (2036000000-E) | CY | 112 | $25.00 | $50.00 | $65.00 |
| 0036 | 6" perforated subdrain pipe (2044000000-E) | LF | 500 | $35.00 | $8.00 | $15.00 |
| 0037 | Subdrain pipe outlet (2070000000-N) | EACH | 1 | $1,500.00 | $200.00 | $500.00 |
| 0038 | 6" outlet pipe (2077000000-E) | LF | 6 | $35.00 | $50.00 | $75.00 |
| 0039 | Endwalls (2209000000-E) | CY | 17.80 | $1,300.00 | $1,300.00 | $3,000.00 |
| 0040 | Reinforced endwalls (2220000000-E) | CY | 18.20 | $1,450.00 | $1,450.00 | $3,200.00 |
| 0041 | Steel beam guardrail (3030000000-E) | LF | 5,250 | $27.45 | $24.75 | $24.75 |
| 0042 | Additional guardrail posts (3150000000-N) | EACH | 15 | $44.00 | $44.00 | $44.00 |
| 0043 | Guardrail anchor units, type III (3215000000-N) | EACH | 6 | $2,350.00 | $2,350.00 | $2,350.00 |
| 0044 | Guardrail end units, type TL-3 (3287000000-N) | EACH | 24 | $33.25 | $3,325.00 | $3,325.00 |
| 0045 | Remove existing guardrail (3360000000-E) | LF | 3,800 | $1.00 | $1.00 | $1.00 |
| 0046 | Rip rap, class I (3628000000-E) | TON | 222 | $126.00 | $132.50 | $145.00 |
| 0047 | Rip rap, class II (3635000000-E) | TON | 160 | $116.00 | $140.20 | $170.00 |
| 0048 | Rip rap, class B (3649000000-E) | TON | 80 | $116.00 | $127.35 | $150.00 |
| 0049 | Geotextile for drainage (3656000000-E) | SY | 1,170 | $5.00 | $4.90 | $6.00 |
| 0050 | Contr furn, type ***sign - (D) (4025000000-E) | SF | 62 | $21.00 | $13.00 | $21.00 |
| 0051 | Contr furn, type ***sign - (E) (4025000000-E) | SF | 268 | $16.25 | $12.00 | $16.25 |
| 0052 | Contr furn, type ***sign - (F) (4025000000-E) | SF | 129 | $16.25 | $13.00 | $16.25 |
| 0053 | Supports, 2-LB steel U-channel (4078000000-E) | EACH | 3 | $26.00 | $60.00 | $26.00 |
| 0054 | Supports, wood (4082000000-E) | LF | 468 | $12.00 | $12.00 | $12.00 |
| 0055 | Sign erection, type *** (GRD MTD) - (D) (4110000000-N) | EACH | 4 | $145.00 | $85.00 | $145.00 |
| 0056 | Sign erection, type *** (GRD MTD) - (E) (4110000000-N) | EACH | 34 | $90.00 | $75.00 | $90.00 |
| 0057 | Sign erection, type *** (GRD MTD) - (F) (4110000000-N) | EACH | 15 | $45.00 | $85.00 | $45.00 |
| 0058 | Disposal of sign system, U-channel (4155000000-N) | EACH | 3 | $20.00 | $10.00 | $20.00 |
| 0059 | Disposal of sign system, wood (4158000000-N) | EACH | 39 | $25.00 | $15.00 | $25.00 |
| 0060 | Stockpile sign, D, E or F (4237000000-N) | EACH | 1 | $15.00 | $10.00 | $20.00 |
| 0061 | Work zone signs (stationary) (4400000000-E) | SF | 112 | $10.00 | $40.00 | $20.00 |
| 0062 | Work zone signs (portable) (4405000000-E) | SF | 96 | $50.00 | $45.00 | $20.00 |
| 0063 | Work zone signs (barricade mounted) (4410000000-E) | SF | 36 | $10.00 | $22.60 | $9.00 |
| 0064 | Drums (4430000000-N) | EACH | 95 | $60.00 | $82.00 | $75.00 |
| 0065 | Barricades (type III) (4445000000-E) | LF | 24 | $25.00 | $120.00 | $40.00 |
| 0066 | Flagger (4455000000-N) | DAY | 690 | $700.00 | $285.00 | $125.00 |
| 0067 | Temporary crash cushions (4465000000-N) | EACH | 4 | $3,500.00 | $12,250 | $8,500.00 |
| 0068 | Remove & reset temporary crash cushion (4470000000-N) | EACH | 4 | $500.00 | $3,225.00 | $3,250.00 |
| 0069 | Portable concrete barrier (anchored) (4490000000-E) | LF | 2,796 | $50.00 | $75.77 | $75.00 |
| 0070 | Remove & reset portable concrete barrier (anchored) (4505000000-E) | LF | 712 | $30.00 | $20.25 | $20.00 |
| 0071 | Temporary raised pavement markers (4650000000-N) | EACH | 34 | $25.00 | $20.00 | $20.00 |
| 0072 | Thermoplastic pavement marking lines (6", 90 mils) (4688000000-E) | LF | 148,582 | $0.93 | $0.93 | $0.95 |
| 0073 | Paint pavement marking lines (4") (4810000000-E) | LF | 70,010 | $0.16 | $0.16 | $0.16 |
| 0074 | Removal of pavement marking lines (4") (4850000000-E) | LF | 46,130 | $0.22 | $0.22 | $0.22 |
| 0075 | Generic pavement marking item (EA) - polycarbonate H-shaped markers (4895000000-N) | EACH | 530 | $53.50 | $53.50 | $53.50 |
| 0076 | Class B concrete for encasing utility lines (5319000000-E) | CY | 24 | $605.00 | $605.00 | $7,500.00 |
| 0077 | 6" water line (5325600000-E) | LF | 1,236 | $110.00 | $110.00 | $165.00 |
| 0078 | DI H2O pipe fittings (5329000000-E) | LB | 10,070 | $18.00 | $18.00 | $20.00 |
| 0079 | **" insertion valve - (6") (5562000000-E) | EACH | 2 | $25,500 | $25,500 | $8,000.00 |
| 0080 | 6" tapping sleeve & valve (5571600000-E) | EACH | 2 | $7,500.00 | $7,500.00 | $15,000 |
| 0081 | Abandon 6" utility pipe (5800000000-E) | LF | 196 | $50.00 | $50.00 | $25.00 |
| 0082 | 16" encasement pipe (5835700000-E) | LF | 88 | $198.00 | $198.00 | $450.00 |
| 0083 | Bore & jack **" - (16") (5872500000-E) | LF | 88 | $750.00 | $750.00 | $1,200.00 |
| 0084 | Direct drill **" - (6") (5872600000-E) | LF | 366 | $330.00 | $330.00 | $400.00 |
| 0085 | Generic utility item (EA) - connect to existing 6" water line (5882000000-N) | EACH | 46 | $2,500.00 | $2,500.00 | $1,000.00 |
| 0086 | Generic utility item (LF) - 6" bypass water line (5888000000-E) | LF | 624 | $450.00 | $450.00 | $150.00 |
| 0087 | Temporary silt fence (6000000000-E) | LF | 10,500 | $3.10 | $2.75 | $3.00 |
| 0088 | Stone for erosion control, class A (6006000000-E) | TON | 540 | $30.00 | $80.00 | $160.00 |
| 0089 | Stone for erosion control, class B (6009000000-E) | TON | 710 | $35.00 | $90.00 | $150.00 |
| 0090 | Sediment control stone (6012000000-E) | TON | 375 | $35.00 | $60.00 | $140.00 |
| 0091 | Temporary mulching (6015000000-E) | ACRE | 19 | $900.00 | $879.50 | $900.00 |
| 0092 | Seed for temporary seeding (6018000000-E) | LB | 900 | $4.25 | $7.25 | $8.00 |
| 0093 | Fertilizer for temporary seeding (6021000000-E) | TON | 4.50 | $750.00 | $1,560.00 | $1,700.00 |
| 0094 | Temporary slope drains (6024000000-E) | LF | 200 | $28.00 | $26.80 | $25.00 |
| 0095 | Safety fence (6029000000-E) | LF | 520 | $4.50 | $3.24 | $3.50 |
| 0096 | Silt excavation (6030000000-E) | CY | 1,320 | $1.00 | $1.00 | $15.00 |
| 0097 | Matting for erosion control (6036000000-E) | SY | 18,110 | $1.75 | $1.59 | $1.60 |
| 0098 | Coir fiber mat (6037000000-E) | SY | 100 | $10.00 | $7.50 | $8.00 |
| 0099 | 1/4" hardware cloth (6042000000-E) | LF | 65 | $10.00 | $7.95 | $8.00 |
| 0100 | **" temporary pipe - (36") (6045000000-E) | LF | 115 | $25.00 | $178.00 | $200.00 |
| 0101 | Special stilling basins (6070000000-N) | EACH | 1 | $3,500.00 | $1,500.00 | $1,500.00 |
| 0102 | Flocculant (6071002000-E) | LB | 3,235 | $0.50 | $7.00 | $15.00 |
| 0103 | Coir fiber wattle (6071012000-E) | LF | 7,080 | $8.00 | $10.12 | $10.50 |
| 0104 | Coir fiber baffle (6071030000-E) | LF | 55 | $12.00 | $7.85 | $8.00 |
| 0105 | Seeding and mulching (6084000000-E) | ACRE | 15 | $2,600.00 | $2,600.00 | $3,000.00 |
| 0106 | Mowing (6087000000-E) | ACRE | 12 | $395.00 | $395.00 | $450.00 |
| 0107 | Seed for repair seeding (6090000000-E) | LB | 200 | $1.00 | $1.00 | $1.00 |
| 0108 | Fertilizer for repair seeding (6093000000-E) | TON | 0.75 | $1.00 | $1.00 | $1.00 |
| 0109 | Seed for supplemental seeding (6096000000-E) | LB | 325 | $1.00 | $1.00 | $1.00 |
| 0110 | Fertilizer topdressing (6108000000-E) | TON | 9.75 | $750.00 | $950.00 | $1,000.00 |
| 0111 | Impervious dike (6111000000-E) | LF | 44 | $200.00 | $450.00 | $500.00 |
| 0112 | Specialized hand mowing (6114500000-N) | MHR | 25 | $115.00 | $95.00 | $100.00 |
| 0113 | Manual litter removal (6114800000-N) | MHR | 7 | $115.00 | $95.00 | $100.00 |
| 0114 | Litter disposal (6114900000-E) | TON | 12 | $225.00 | $225.00 | $225.00 |
| 0115 | Response for erosion control (6117000000-N) | EACH | 100 | $125.00 | $1.00 | $1.00 |
| 0116 | Concrete washout structure (6117500000-N) | EACH | 2 | $3,500.00 | $1,250.00 | $1,800.00 |
| 0117 | Box culv excav @ ******** - (398+84.00 -L-) (8130000000-N) | LS | 1 | $90,000 | $1,500,000 | $315,000 |
| 0118 | Foundation conditioning material, box culvert (8133000000-E) | TON | 323 | $80.00 | $80.00 | $145.00 |
| 0119 | Class A concrete (culvert) (8196000000-E) | CY | 635.70 | $1,050.00 | $1,050.00 | $1,750.00 |
| 0120 | Epoxy coated reinforcing steel (culvert) (8248000000-E) | LB | 101,738 | $2.25 | $2.25 | $3.50 |
| 0121 | Grading (0063000000-N) | LS | 1 | $3,400,000 | $605,577 | $1,515,000 |
| 0122 | Borrow excavation (0106000000-E) | CY | 9,000 | $25.00 | $32.53 | $35.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NCDOT's tabulation for this contract. NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
Every contract let that day: NCDOT letting of January 21, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.