ODOT contract 250021 bid tabulation
SAN-SR 412/SR 590-08.86/06.56 Resurf (TWO LANE RESURFACING). Let by Ohio DOT on January 16, 2025, SAN. 4 bids received; low bid $3,653,694 by Kokosing Construction Company Inc, -25% against the engineer's estimate of $4,859,000.
- Owner
- Ohio DOT
- Letting
- 16 JAN 2025
- Pay items
- 77
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Kokosing Construction Company Inc | $3,653,694 | Low | -25% |
| 2 | Gerken Paving Inc | $4,010,653 | +10% | -17% |
| 3 | Erie Blacktop Inc | $4,074,107 | +12% | -16% |
| 4 | M & B Asphalt Co Inc | $4,111,792 | +13% | -15% |
Engineer's estimate: $4,859,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Kokosing Construction Company Inc | 2. Gerken Paving Inc | 3. Erie Blacktop Inc | 4. M & B Asphalt Co Inc |
|---|---|---|---|---|---|---|---|
| 1 | Walk removed (202E30000) | SF | 935 | $5.55 | $3.50 | $3.70 | $3.50 |
| 2 | Excavation (203E10000) | CY | 345 | $17.55 | $35.00 | $38.00 | $17.55 |
| 3 | Embankment (203E20000) | CY | 231 | $17.55 | $35.00 | $29.00 | $17.55 |
| 4 | Granular material, type B (203E35110) | CY | 28 | $130.80 | $150.00 | $71.50 | $130.80 |
| 5 | Granular material, type C (203E35120) | CY | 18 | $144.00 | $130.00 | $194.00 | $144.00 |
| 6 | Granular material, type D (203E35130) | CY | 81 | $165.45 | $150.00 | $97.00 | $165.45 |
| 7 | Linear grading (209E60500) | MI | 24 | $1,940.00 | $2,000.00 | $1,450.00 | $1,100.00 |
| 8 | Guardrail, type MGS (606E15050) | FT | 100 | $25.60 | $25.60 | $26.90 | $25.60 |
| 9 | Guardrail, type MGS, long-span (606E17360) | FT | 75 | $29.40 | $29.40 | $30.85 | $29.40 |
| 10 | Anchor assembly, MGS type E, NCHRP 350/MASH 2016 (606E26150) | EACH | 4 | $2,545.00 | $2,545.00 | $2,675.00 | $2,545.00 |
| 11 | Curb ramp (608E52000) | SF | 935 | $18.65 | $13.85 | $14.50 | $14.00 |
| 12 | Detectable warning (608E53020) | SF | 104 | $18.65 | $33.75 | $35.50 | $34.00 |
| 13 | Curb, type 6 (609E26000) | FT | 98 | $25.00 | $32.95 | $34.60 | $33.00 |
| 14 | Rock channel protection, type C with filter (601E32200) | CY | 10 | $217.80 | $150.00 | $341.25 | $220.00 |
| 15 | Topsoil (659E00300) | CY | 100 | $101.40 | $70.00 | $50.40 | $101.40 |
| 16 | Seeding and mulching (659E10000) | SY | 901 | $4.00 | $4.95 | $5.20 | $4.95 |
| 17 | Repair seeding and mulching (659E14000) | SY | 45 | $1.00 | $1.30 | $1.05 | $1.30 |
| 18 | Inter-seeding (659E15000) | SY | 45 | $0.50 | $0.19 | $1.05 | $0.19 |
| 19 | Commercial fertilizer (659E20000) | TON | 1 | $600.00 | $275.00 | $1,680.00 | $275.00 |
| 20 | Lime (659E31000) | ACRE | 1 | $10.00 | $40.00 | $157.50 | $40.00 |
| 21 | Water (659E35000) | MGAL | 1 | $1.00 | $1.00 | $26.25 | $1.00 |
| 22 | Ditch erosion protection mat, type B (670E00720) | SY | 160 | $5.00 | $4.20 | $5.75 | $4.20 |
| 23 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 24 | Pipe removed, 24" and under (202E35100) | FT | 47 | $29.23 | $25.00 | $27.00 | $29.23 |
| 25 | Pipe removed, over 24" diameter (202E35200) | FT | 36 | $46.80 | $35.00 | $141.00 | $46.80 |
| 26 | Catch basin removed (202E58100) | EACH | 2 | $643.50 | $500.00 | $472.00 | $650.00 |
| 27 | Sealing of concrete surfaces (non-epoxy) (512E10050) | SY | 18 | $39.84 | $75.00 | $88.00 | $40.00 |
| 28 | Porous backfill (518E21220) | LS | 1 | $1,953.15 | $3,500.00 | $1,625.00 | $2,000.00 |
| 29 | Concrete masonry (602E20000) | CY | 15.20 | $2,125.69 | $1,695.00 | $2,050.00 | $2,125.69 |
| 30 | 24" conduit, type B (611E10400) | FT | 54 | $213.77 | $175.00 | $205.00 | $213.77 |
| 31 | 38" X 60" conduit, type A, 706.04 (611E53000) | FT | 44 | $824.77 | $900.00 | $546.00 | $824.77 |
| 32 | Catch basin, no. 2-3 (611E98510) | EACH | 2 | $3,267.00 | $3,500.00 | $3,465.00 | $3,267.00 |
| 33 | Catch basin adjusted to grade (611E98630) | EACH | 12 | $650.00 | $869.95 | $915.00 | $900.00 |
| 34 | Manhole adjusted to grade (611E99654) | EACH | 2 | $900.00 | $894.95 | $940.00 | $900.00 |
| 35 | Preparing subgrade for shoulder paving (209E72050) | MI | 21.90 | $600.00 | $650.00 | $1,450.00 | $1,000.00 |
| 36 | Pavement repair (253E02000) | CY | 3,419 | $165.00 | $194.00 | $200.00 | $210.00 |
| 37 | Pavement planing, asphalt concrete, 1.75" (254E01000) | SY | 119,710 | $1.00 | $2.06 | $1.00 | $1.70 |
| 38 | Pavement planing, asphalt concrete, 3" (254E01000) | SY | 52,635 | $1.90 | $2.44 | $1.45 | $3.35 |
| 39 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 32 | $250.00 | $275.00 | $230.00 | $450.00 |
| 40 | Aggregate base (304E20000) | CY | 34 | $134.10 | $150.00 | $140.00 | $134.10 |
| 41 | Tack coat (407E10000) | GAL | 17,545 | $2.50 | $2.50 | $2.55 | $2.77 |
| 42 | Fine graded polymer asphalt concrete, type B, (448), as per plan (424E14001) | CY | 1,513 | $228.00 | $238.00 | $260.00 | $236.00 |
| 44 | Asphalt concrete intermediate course, type 2, (446) (441E10200) | CY | 2,921 | $156.00 | $160.00 | $158.00 | $174.00 |
| 46 | Asphalt concrete surface course, type 1, (449), (driveways) (441E70500) | CY | 175 | $195.00 | $270.00 | $300.00 | $236.00 |
| 47 | Asphalt concrete surface course, 12.5 MM, type A (446) (442E10000) | CY | 5,886 | $186.00 | $205.00 | $228.00 | $210.00 |
| 48 | Compacted aggregate (617E10100) | CY | 2,344 | $35.00 | $62.00 | $63.00 | $69.00 |
| 49 | Longitudinal joint adhesive (875E10000) | LB | 10,208 | $0.85 | $1.85 | $1.80 | $0.75 |
| 50 | RPM (621E00100) | EACH | 766 | $37.50 | $37.50 | $39.40 | $40.00 |
| 51 | Raised pavement marker removed (621E54000) | EACH | 766 | $5.00 | $6.00 | $5.50 | $4.50 |
| 52 | Edge line, 6", type 1 (642E00104) | MI | 21.54 | $750.00 | $750.00 | $840.00 | $750.00 |
| 53 | Center line, type 1 (642E00300) | MI | 8.12 | $650.00 | $650.00 | $840.00 | $650.00 |
| 54 | Center line, type 1 (642E00300) | MI | 2.46 | $650.00 | $650.00 | $840.00 | $650.00 |
| 55 | Center line, type 1 (642E00300) | MI | 0.96 | $650.00 | $650.00 | $840.00 | $650.00 |
| 56 | Stop line (644E00500) | FT | 12 | $10.00 | $10.00 | $21.00 | $10.00 |
| 57 | Crosswalk line, 12" (644E00620) | FT | 230 | $4.00 | $4.00 | $5.25 | $4.00 |
| 58 | Transverse/diagonal line (644E00700) | FT | 200 | $9.00 | $9.00 | $8.40 | $9.00 |
| 59 | Parking lot stall marking (644E01200) | FT | 915 | $2.00 | $2.00 | $2.10 | $2.00 |
| 60 | Handicap symbol marking (644E01600) | EACH | 2 | $200.00 | $200.00 | $52.50 | $200.00 |
| 61 | Work zone marking sign (614E12460) | EACH | 50 | $85.00 | $125.00 | $90.00 | $100.00 |
| 62 | Replacement sign (614E12500) | EACH | 5 | $108.00 | $125.00 | $113.50 | $90.00 |
| 63 | Replacement drum (614E12600) | EACH | 10 | $56.00 | $55.00 | $59.00 | $45.00 |
| 64 | Work zone center line, class II (614E21400) | MI | 23.20 | $500.00 | $400.00 | $367.00 | $415.00 |
| 65 | Work zone stop line, class I (614E26000) | FT | 12 | $4.00 | $4.00 | $4.20 | $4.00 |
| 66 | Pavement planing, asphalt concrete, 1" (254E01000) | SY | 302 | $2.75 | $2.60 | $2.40 | $2.60 |
| 67 | Special - sawing and sealing bituminous concrete joints (516E31200) | FT | 130 | $26.04 | $30.00 | $27.35 | $26.04 |
| 68 | Pavement planing, asphalt concrete, 2.5" (254E01000) | SY | 281 | $3.40 | $3.45 | $2.00 | $3.40 |
| 69 | Special - sawing and sealing bituminous concrete joints (516E31200) | FT | 130 | $26.04 | $30.00 | $27.00 | $26.04 |
| 70 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $15,000 | $15,000 | $18,000 | $25,000 |
| 71 | Maintaining traffic (614E11000) | LS | 1 | $207,680 | $135,000 | $96,000 | $110,000 |
| 72 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 40 | $100.00 | $94.00 | $85.00 | $80.00 |
| 73 | Construction layout stakes and surveying (623E10000) | LS | 1 | $7,000.00 | $3,600.00 | $13,300 | $13,500 |
| 74 | Mobilization (624E10000) | LS | 1 | $182,500 | $120,000 | $200,000 | $100,000 |
| 100 | 6" conduit, type F (611E01500) | FT | 25 | $34.20 | $15.00 | $21.00 | $35.00 |
| 101 | 12" conduit, type E (611E05100) | FT | 50 | $33.90 | $15.00 | $31.50 | $35.00 |
| 102 | 15" conduit, type B (611E05900) | FT | 25 | $39.15 | $20.00 | $136.50 | $40.00 |
| 103 | Asphalt concrete, misc.: butt joints intersections (442E90000) | CY | 108 | $300.00 | $400.00 | $375.00 | $450.00 |
| 104 | Curb removed (202E32000) | FT | 98 | $11.00 | $21.95 | $23.00 | $22.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of January 16, 2025. Compiled by Mirage Metrics.