ODOT contract 250159 bid tabulation

HAR-Detroit St. Reconstruction (MINOR RECONSTRUCTION). Let by Ohio DOT on March 27, 2025, HAR. 2 bids received; low bid $4,351,297 by Helms and Sons Excavating, -9.6% against the engineer's estimate of $4,816,000.

Owner
Ohio DOT
Letting
27 MAR 2025
Pay items
117
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Helms and Sons Excavating$4,351,297Low-10%
2Miller Contracting Group Inc$4,389,550+1.0%-9.0%
ODOT contract 250159: bids by rank

Engineer's estimate: $4,816,000.

Bid tabulation

LinePay itemUnitQuantity1. Helms and Sons Excavating2. Miller Contracting Group Inc
1Clearing and grubbing (201E11000)LS1$90,000$58,078
2Pavement removed (202E23000)SY10,890$17.00$12.20
3Walk removed (202E30000)SF23,167$3.00$6.00
4Curb removed (202E32000)FT3,881$6.00$3.30
5Pipe removed, 24" and under (202E35100)FT905$20.00$32.30
6Manhole removed (202E58000)EACH3$725.00$949.00
7Catch basin removed (202E58100)EACH10$370.00$487.40
8Valve box removed (202E75610)EACH2$175.00$297.00
9Removal misc.:concrete post (202E98100)EACH1$500.00$242.00
10Removal misc.:conduit (202E98200)FT500$34.00$45.70
11Excavation (203E10000)CY4,826$25.00$23.20
12Embankment (203E20000)CY154$20.00$21.90
13Subgrade compaction (204E10000)SY12,109$2.00$1.90
14Excavation of subgrade (204E13000)CY3,658$28.00$31.00
15Granular material, type C (204E30020)CY3,658$54.00$54.00
16Proof rolling (204E45000)HR12$150.00$237.60
17Geogrid (204E51000)SY11,087$2.00$2.30
184" concrete walk, as per plan (608E10001)SF19,516$7.00$8.70
19Curb ramp, as per plan (608E52001)SF1,269$19.00$10.30
20Topsoil (659E00300)CY599$40.00$75.31
21Seeding and mulching, class 1 (659E00500)SY5,400$2.00$2.20
22Repair seeding and mulching (659E14000)SY270$2.00$2.20
23Inter-seeding (659E15000)SY270$1.00$1.20
24Commercial fertilizer (659E20000)TON0.73$950.00$975.40
25Lime (659E31000)ACRE1.12$50.00$35.00
26Water (659E35000)MGAL29.15$10.00$1.00
27Deciduous tree, 2" caliper , ginko biloba' (661E40080)EACH13$700.00$776.30
28Deciduous tree, 2" caliper ,ulmus japonica 'morta (661E40080)EACH16$500.00$546.00
29Deciduous tree, 2" caliper ,gymnocladus dioicus (661E40080)EACH20$580.00$631.20
30Deciduous tree, 2" caliper ,plantanus X acerifoli (661E40080)EACH10$590.00$647.00
31Storm water pollution prevention plan (832E15000)LS1$2,500.00$1,348.40
32Storm water pollution prevention inspections (832E15002)LS1$9,500.00$9,811.20
33Storm water pollution prevention inspection software (832E15010)LS1$11,000$10,444
34Erosion control (832E30000)EACH45,000$1.00$1.00
354" base pipe underdrains (605E06000)FT3,422$13.00$17.90
364" conduit, type F for underdrain outlet (611E00410)FT250$56.00$24.70
376" conduit, type B (611E00900)FT31$102.00$73.50
3810" conduit, type B (611E03100)FT5$224.00$391.00
3912" conduit, type B (611E04400)FT709$131.00$68.40
4015" conduit, type B (611E05900)FT320$117.00$84.30
4118" conduit, type B (611E07400)FT309$120.00$101.50
4224" conduit, type B (611E10400)FT1,035$180.00$120.10
43Conduit, misc.:ype B for drainage discharge contin (611E97400)FT100$140.00$52.00
44Conduit, misc.:ype C for drainage discharge contin (611E97400)FT100$125.00$40.00
45Conduit, misc.:ype E for drainage discharge contin (611E97400)FT100$140.00$52.00
46Conduit, misc.:ype F for drainage discharge contin (611E97400)FT100$140.00$27.00
47Catch basin, misc.:type 1 (611E98690)EACH31$4,200.00$3,273.60
48Manhole, no. 3 (611E99574)EACH13$6,500.00$4,066.20
49Manhole, no. 3 with 96" base I.D. and 9" weir (611E99584)EACH1$20,500$12,632
50Inspection well (611E99720)EACH3$900.00$1,350.40
51Manufactured water quality structure, type 3 (895E10030)EACH1$57,000$38,029
52Pavement planing, asphalt CONCRETE1-1/2" (254E01000)SY277$16.00$5.80
53Asphalt concrete base, PG64-22, (449) (301E56000)CY1,529$220.00$203.20
54Aggregate base (304E20000)CY2,561$59.00$49.70
55Non-tracking tack coat (407E20000)GAL1,115$4.00$2.30
56Non-tracking tack coat (407E20000)GAL25$4.00$2.30
57Stabilized crushed aggregate (411E10000)CY193$235.00$68.00
58Asphalt concrete surface course, 12.5 MM, type A (448) (442E20000)CY394$292.00$269.70
59Asphalt concrete intermediate course, 19 MM, type A (448) (442E20200)CY637$232.00$228.40
60Asphalt concrete surface course, 12.5 MM, type A (449) (driveways) (442E22120)CY10$830.00$1,061.50
61Asphalt concrete intermediate course, 19 MM, type A (449) (driveways) (442E22420)CY16$565.00$803.30
626" non-reinforced concrete pavement, class QC 1P, as per plan (452E10011)SY616$77.00$106.80
639" non-reinforced concrete pavement, class QC 1P, as per plan (452E13011)SY187$98.00$129.60
64Combination curb and gutter, type 2, as per plan (609E12001)FT4,301$32.00$26.00
65Curb, type 6, as per plan (609E26001)FT105$31.00$35.70
664" water main ductile iron pipe ansi class 52, mechanical joints and fittings, as per plan (638E00201)FT9$245.00$656.40
676" water main ductile iron pipe ansi class 52, mechanical joints and fittings, as per plan (638E00701)FT32$131.00$354.00
688" water main ductile iron pipe ansi class 52, mechanical joints and fittings, as per plan (638E01301)FT9$260.00$784.40
6912" water main ductile iron pipe ansi class 52, mechanical joints and fittings, as per plan (638E02501)FT2,325$178.00$160.20
701" copper service branch, as per plan (638E04901)FT1,998$57.00$82.90
714" gate valve and valve box (638E07700)EACH1$1,920.00$2,048.40
726" gate valve and valve box (638E07800)EACH1$2,175.00$2,437.40
738" gate valve and valve box (638E07900)EACH1$2,850.00$3,232.10
7412" gate valve and valve box (638E08100)EACH10$4,750.00$5,408.60
756" fire hydrant, as per plan (638E10201)EACH6$11,575$12,088
76Fire hydrant removed (638E10480)EACH3$650.00$1,109.80
77Meter, setting, stop and chamber, as per plan (638E11201)EACH54$475.00$926.40
78Special - cut and plug existing 4" water line, cit (638E20876)EACH1$2,900.00$2,427.00
79Special - cut and plug existing 6" water line, cit (638E20878)EACH1$2,950.00$3,403.60
80Special - cut and plug existing 8" water line, cit (638E20880)EACH1$2,950.00$3,766.80
81Special - cut and plug existing 12" water line, CI (638E20884)EACH2$4,050.00$3,918.40
82Water work, misc.:12" line stop (638E98000)EACH1$18,000$12,160
83Water work, misc.:12" watermain reconected (638E98000)EACH2$5,750.00$936.60
84Water work, misc.:4" line stop (638E98000)EACH1$12,200$9,126.80
85Water work, misc.:4" watermain reconected (638E98000)EACH1$3,650.00$255.90
86Water work, misc.:6" line stop (638E98000)EACH1$13,000$9,577.70
87Water work, misc.:6" watermain reconected (638E98000)EACH1$3,800.00$345.00
88Water work, misc.:8" line stop (638E98000)EACH1$13,600$11,015
89Water work, misc.:8" watermain reconected (638E98000)EACH1$4,000.00$433.10
90Ground mounted support, no. 3 post (630E03100)FT377$15.00$16.10
91Street name sign support, no. 3 post (630E08520)FT38$15.00$16.10
92Sign, flat sheet (630E80100)SF184$25.00$27.60
93Sign, double faced, street name (630E80500)EACH6$155.00$172.20
94Removal of ground mounted sign and disposal (630E84900)EACH36$26.00$28.70
95Removal of ground mounted sign and reerection (630E85100)EACH3$62.00$68.90
96Removal of ground mounted post support and disposal (630E86002)EACH25$16.00$17.30
97Removal of ground mounted post support and reerection (630E86010)EACH2$47.00$51.70
98Edge line, 6" (644E00104)MI0.04$5,250.00$5,737.50
99Center line (644E00300)MI0.38$6,750.00$7,458.79
100Channelizing line, 8" (644E00400)FT85$2.00$2.30
101Stop line (644E00500)FT93$8.00$9.20
102Crosswalk line, 24" (644E00630)FT504$8.00$9.20
103Transverse/diagonal line (644E00700)FT36$8.00$9.20
104Lane arrow (644E01300)EACH1$105.00$114.80
105Pavement repair (253E02000)CY50$775.00$341.00
106Detour signing, as per plan (614E12421)LS1$4,000.00$14,321
107Portable changeable message sign, as per plan (614E18601)SNMT16$1,200.00$1,090.20
108Water (616E10000)MGAL18$10.00$201.10
109Compacted aggregate (617E10100)CY50$150.00$71.50
110Premium for contract performance bond and for payment bond (103E05000)LS1$55,000$48,200
111Maintaining traffic (614E11000)LS1$75,000$18,509
112Field office, type B (619E16010)MNTH9$500.00$1,718.10
113Construction layout stakes and surveying (623E10000)LS1$55,000$26,335
114Monument, misc.:post construction survey monument (623E40900)EACH1$20,000$4,590.00
115Monument, misc.:preconstruction survey monument VE (623E40900)EACH1$20,000$4,590.00
116Mobilization (624E10000)LS1$175,000$580,000
117Special - work involving petroleum contaminated soil (690E65016)TON1,000$95.00$107.60
ODOT contract 250159: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of March 27, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy