ODOT contract 250159 bid tabulation
HAR-Detroit St. Reconstruction (MINOR RECONSTRUCTION). Let by Ohio DOT on March 27, 2025, HAR. 2 bids received; low bid $4,351,297 by Helms and Sons Excavating, -9.6% against the engineer's estimate of $4,816,000.
- Owner
- Ohio DOT
- Letting
- 27 MAR 2025
- Pay items
- 117
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Helms and Sons Excavating | $4,351,297 | Low | -10% |
| 2 | Miller Contracting Group Inc | $4,389,550 | +1.0% | -9.0% |
Engineer's estimate: $4,816,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Helms and Sons Excavating | 2. Miller Contracting Group Inc |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $90,000 | $58,078 |
| 2 | Pavement removed (202E23000) | SY | 10,890 | $17.00 | $12.20 |
| 3 | Walk removed (202E30000) | SF | 23,167 | $3.00 | $6.00 |
| 4 | Curb removed (202E32000) | FT | 3,881 | $6.00 | $3.30 |
| 5 | Pipe removed, 24" and under (202E35100) | FT | 905 | $20.00 | $32.30 |
| 6 | Manhole removed (202E58000) | EACH | 3 | $725.00 | $949.00 |
| 7 | Catch basin removed (202E58100) | EACH | 10 | $370.00 | $487.40 |
| 8 | Valve box removed (202E75610) | EACH | 2 | $175.00 | $297.00 |
| 9 | Removal misc.:concrete post (202E98100) | EACH | 1 | $500.00 | $242.00 |
| 10 | Removal misc.:conduit (202E98200) | FT | 500 | $34.00 | $45.70 |
| 11 | Excavation (203E10000) | CY | 4,826 | $25.00 | $23.20 |
| 12 | Embankment (203E20000) | CY | 154 | $20.00 | $21.90 |
| 13 | Subgrade compaction (204E10000) | SY | 12,109 | $2.00 | $1.90 |
| 14 | Excavation of subgrade (204E13000) | CY | 3,658 | $28.00 | $31.00 |
| 15 | Granular material, type C (204E30020) | CY | 3,658 | $54.00 | $54.00 |
| 16 | Proof rolling (204E45000) | HR | 12 | $150.00 | $237.60 |
| 17 | Geogrid (204E51000) | SY | 11,087 | $2.00 | $2.30 |
| 18 | 4" concrete walk, as per plan (608E10001) | SF | 19,516 | $7.00 | $8.70 |
| 19 | Curb ramp, as per plan (608E52001) | SF | 1,269 | $19.00 | $10.30 |
| 20 | Topsoil (659E00300) | CY | 599 | $40.00 | $75.31 |
| 21 | Seeding and mulching, class 1 (659E00500) | SY | 5,400 | $2.00 | $2.20 |
| 22 | Repair seeding and mulching (659E14000) | SY | 270 | $2.00 | $2.20 |
| 23 | Inter-seeding (659E15000) | SY | 270 | $1.00 | $1.20 |
| 24 | Commercial fertilizer (659E20000) | TON | 0.73 | $950.00 | $975.40 |
| 25 | Lime (659E31000) | ACRE | 1.12 | $50.00 | $35.00 |
| 26 | Water (659E35000) | MGAL | 29.15 | $10.00 | $1.00 |
| 27 | Deciduous tree, 2" caliper , ginko biloba' (661E40080) | EACH | 13 | $700.00 | $776.30 |
| 28 | Deciduous tree, 2" caliper ,ulmus japonica 'morta (661E40080) | EACH | 16 | $500.00 | $546.00 |
| 29 | Deciduous tree, 2" caliper ,gymnocladus dioicus (661E40080) | EACH | 20 | $580.00 | $631.20 |
| 30 | Deciduous tree, 2" caliper ,plantanus X acerifoli (661E40080) | EACH | 10 | $590.00 | $647.00 |
| 31 | Storm water pollution prevention plan (832E15000) | LS | 1 | $2,500.00 | $1,348.40 |
| 32 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $9,500.00 | $9,811.20 |
| 33 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $11,000 | $10,444 |
| 34 | Erosion control (832E30000) | EACH | 45,000 | $1.00 | $1.00 |
| 35 | 4" base pipe underdrains (605E06000) | FT | 3,422 | $13.00 | $17.90 |
| 36 | 4" conduit, type F for underdrain outlet (611E00410) | FT | 250 | $56.00 | $24.70 |
| 37 | 6" conduit, type B (611E00900) | FT | 31 | $102.00 | $73.50 |
| 38 | 10" conduit, type B (611E03100) | FT | 5 | $224.00 | $391.00 |
| 39 | 12" conduit, type B (611E04400) | FT | 709 | $131.00 | $68.40 |
| 40 | 15" conduit, type B (611E05900) | FT | 320 | $117.00 | $84.30 |
| 41 | 18" conduit, type B (611E07400) | FT | 309 | $120.00 | $101.50 |
| 42 | 24" conduit, type B (611E10400) | FT | 1,035 | $180.00 | $120.10 |
| 43 | Conduit, misc.:ype B for drainage discharge contin (611E97400) | FT | 100 | $140.00 | $52.00 |
| 44 | Conduit, misc.:ype C for drainage discharge contin (611E97400) | FT | 100 | $125.00 | $40.00 |
| 45 | Conduit, misc.:ype E for drainage discharge contin (611E97400) | FT | 100 | $140.00 | $52.00 |
| 46 | Conduit, misc.:ype F for drainage discharge contin (611E97400) | FT | 100 | $140.00 | $27.00 |
| 47 | Catch basin, misc.:type 1 (611E98690) | EACH | 31 | $4,200.00 | $3,273.60 |
| 48 | Manhole, no. 3 (611E99574) | EACH | 13 | $6,500.00 | $4,066.20 |
| 49 | Manhole, no. 3 with 96" base I.D. and 9" weir (611E99584) | EACH | 1 | $20,500 | $12,632 |
| 50 | Inspection well (611E99720) | EACH | 3 | $900.00 | $1,350.40 |
| 51 | Manufactured water quality structure, type 3 (895E10030) | EACH | 1 | $57,000 | $38,029 |
| 52 | Pavement planing, asphalt CONCRETE1-1/2" (254E01000) | SY | 277 | $16.00 | $5.80 |
| 53 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 1,529 | $220.00 | $203.20 |
| 54 | Aggregate base (304E20000) | CY | 2,561 | $59.00 | $49.70 |
| 55 | Non-tracking tack coat (407E20000) | GAL | 1,115 | $4.00 | $2.30 |
| 56 | Non-tracking tack coat (407E20000) | GAL | 25 | $4.00 | $2.30 |
| 57 | Stabilized crushed aggregate (411E10000) | CY | 193 | $235.00 | $68.00 |
| 58 | Asphalt concrete surface course, 12.5 MM, type A (448) (442E20000) | CY | 394 | $292.00 | $269.70 |
| 59 | Asphalt concrete intermediate course, 19 MM, type A (448) (442E20200) | CY | 637 | $232.00 | $228.40 |
| 60 | Asphalt concrete surface course, 12.5 MM, type A (449) (driveways) (442E22120) | CY | 10 | $830.00 | $1,061.50 |
| 61 | Asphalt concrete intermediate course, 19 MM, type A (449) (driveways) (442E22420) | CY | 16 | $565.00 | $803.30 |
| 62 | 6" non-reinforced concrete pavement, class QC 1P, as per plan (452E10011) | SY | 616 | $77.00 | $106.80 |
| 63 | 9" non-reinforced concrete pavement, class QC 1P, as per plan (452E13011) | SY | 187 | $98.00 | $129.60 |
| 64 | Combination curb and gutter, type 2, as per plan (609E12001) | FT | 4,301 | $32.00 | $26.00 |
| 65 | Curb, type 6, as per plan (609E26001) | FT | 105 | $31.00 | $35.70 |
| 66 | 4" water main ductile iron pipe ansi class 52, mechanical joints and fittings, as per plan (638E00201) | FT | 9 | $245.00 | $656.40 |
| 67 | 6" water main ductile iron pipe ansi class 52, mechanical joints and fittings, as per plan (638E00701) | FT | 32 | $131.00 | $354.00 |
| 68 | 8" water main ductile iron pipe ansi class 52, mechanical joints and fittings, as per plan (638E01301) | FT | 9 | $260.00 | $784.40 |
| 69 | 12" water main ductile iron pipe ansi class 52, mechanical joints and fittings, as per plan (638E02501) | FT | 2,325 | $178.00 | $160.20 |
| 70 | 1" copper service branch, as per plan (638E04901) | FT | 1,998 | $57.00 | $82.90 |
| 71 | 4" gate valve and valve box (638E07700) | EACH | 1 | $1,920.00 | $2,048.40 |
| 72 | 6" gate valve and valve box (638E07800) | EACH | 1 | $2,175.00 | $2,437.40 |
| 73 | 8" gate valve and valve box (638E07900) | EACH | 1 | $2,850.00 | $3,232.10 |
| 74 | 12" gate valve and valve box (638E08100) | EACH | 10 | $4,750.00 | $5,408.60 |
| 75 | 6" fire hydrant, as per plan (638E10201) | EACH | 6 | $11,575 | $12,088 |
| 76 | Fire hydrant removed (638E10480) | EACH | 3 | $650.00 | $1,109.80 |
| 77 | Meter, setting, stop and chamber, as per plan (638E11201) | EACH | 54 | $475.00 | $926.40 |
| 78 | Special - cut and plug existing 4" water line, cit (638E20876) | EACH | 1 | $2,900.00 | $2,427.00 |
| 79 | Special - cut and plug existing 6" water line, cit (638E20878) | EACH | 1 | $2,950.00 | $3,403.60 |
| 80 | Special - cut and plug existing 8" water line, cit (638E20880) | EACH | 1 | $2,950.00 | $3,766.80 |
| 81 | Special - cut and plug existing 12" water line, CI (638E20884) | EACH | 2 | $4,050.00 | $3,918.40 |
| 82 | Water work, misc.:12" line stop (638E98000) | EACH | 1 | $18,000 | $12,160 |
| 83 | Water work, misc.:12" watermain reconected (638E98000) | EACH | 2 | $5,750.00 | $936.60 |
| 84 | Water work, misc.:4" line stop (638E98000) | EACH | 1 | $12,200 | $9,126.80 |
| 85 | Water work, misc.:4" watermain reconected (638E98000) | EACH | 1 | $3,650.00 | $255.90 |
| 86 | Water work, misc.:6" line stop (638E98000) | EACH | 1 | $13,000 | $9,577.70 |
| 87 | Water work, misc.:6" watermain reconected (638E98000) | EACH | 1 | $3,800.00 | $345.00 |
| 88 | Water work, misc.:8" line stop (638E98000) | EACH | 1 | $13,600 | $11,015 |
| 89 | Water work, misc.:8" watermain reconected (638E98000) | EACH | 1 | $4,000.00 | $433.10 |
| 90 | Ground mounted support, no. 3 post (630E03100) | FT | 377 | $15.00 | $16.10 |
| 91 | Street name sign support, no. 3 post (630E08520) | FT | 38 | $15.00 | $16.10 |
| 92 | Sign, flat sheet (630E80100) | SF | 184 | $25.00 | $27.60 |
| 93 | Sign, double faced, street name (630E80500) | EACH | 6 | $155.00 | $172.20 |
| 94 | Removal of ground mounted sign and disposal (630E84900) | EACH | 36 | $26.00 | $28.70 |
| 95 | Removal of ground mounted sign and reerection (630E85100) | EACH | 3 | $62.00 | $68.90 |
| 96 | Removal of ground mounted post support and disposal (630E86002) | EACH | 25 | $16.00 | $17.30 |
| 97 | Removal of ground mounted post support and reerection (630E86010) | EACH | 2 | $47.00 | $51.70 |
| 98 | Edge line, 6" (644E00104) | MI | 0.04 | $5,250.00 | $5,737.50 |
| 99 | Center line (644E00300) | MI | 0.38 | $6,750.00 | $7,458.79 |
| 100 | Channelizing line, 8" (644E00400) | FT | 85 | $2.00 | $2.30 |
| 101 | Stop line (644E00500) | FT | 93 | $8.00 | $9.20 |
| 102 | Crosswalk line, 24" (644E00630) | FT | 504 | $8.00 | $9.20 |
| 103 | Transverse/diagonal line (644E00700) | FT | 36 | $8.00 | $9.20 |
| 104 | Lane arrow (644E01300) | EACH | 1 | $105.00 | $114.80 |
| 105 | Pavement repair (253E02000) | CY | 50 | $775.00 | $341.00 |
| 106 | Detour signing, as per plan (614E12421) | LS | 1 | $4,000.00 | $14,321 |
| 107 | Portable changeable message sign, as per plan (614E18601) | SNMT | 16 | $1,200.00 | $1,090.20 |
| 108 | Water (616E10000) | MGAL | 18 | $10.00 | $201.10 |
| 109 | Compacted aggregate (617E10100) | CY | 50 | $150.00 | $71.50 |
| 110 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $55,000 | $48,200 |
| 111 | Maintaining traffic (614E11000) | LS | 1 | $75,000 | $18,509 |
| 112 | Field office, type B (619E16010) | MNTH | 9 | $500.00 | $1,718.10 |
| 113 | Construction layout stakes and surveying (623E10000) | LS | 1 | $55,000 | $26,335 |
| 114 | Monument, misc.:post construction survey monument (623E40900) | EACH | 1 | $20,000 | $4,590.00 |
| 115 | Monument, misc.:preconstruction survey monument VE (623E40900) | EACH | 1 | $20,000 | $4,590.00 |
| 116 | Mobilization (624E10000) | LS | 1 | $175,000 | $580,000 |
| 117 | Special - work involving petroleum contaminated soil (690E65016) | TON | 1,000 | $95.00 | $107.60 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of March 27, 2025. Compiled by Mirage Metrics.