ODOT contract 250188 bid tabulation
BEL-SR 148-08.45 (SLIDE REPAIR). Let by Ohio DOT on April 10, 2025, BEL. 8 bids received; low bid $489,254 by Ohio-West Virginia Excavating Co, -16% against the engineer's estimate of $585,000.
- Owner
- Ohio DOT
- Letting
- 10 APR 2025
- Pay items
- 59
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Ohio-West Virginia Excavating Co | $489,254 | Low | -16% |
| 2 | Double B Excavating LLC | $493,447 | +1.0% | -16% |
| 3 | S.T.A.R.T., LLC | $505,094 | +3.0% | -14% |
| 4 | LMS Construction Inc | $529,933 | +8.0% | -9.0% |
| 5 | V3 Construction Group LTD | $563,470 | +15% | -4.0% |
| 6 | Ed Wilson Services LLC | $633,340 | +29% | +8.0% |
| 7 | Tucson Inc | $654,178 | +34% | +12% |
| 8 | Eclipse Co LLC | $862,808 | +76% | +47% |
Engineer's estimate: $585,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ohio-West Virginia Excavating Co | 2. Double B Excavating LLC | 3. S.T.A.R.T., LLC | 4. LMS Construction Inc | 5. V3 Construction Group LTD | 6. Ed Wilson Services LLC |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $5,000.00 | $5,000.00 | $4,954.10 | $5,000.00 | $8,900.00 | $6,000.00 |
| 2 | Pavement removed (202E23000) | SY | 271 | $30.00 | $18.46 | $41.21 | $14.00 | $14.00 | $48.00 |
| 3 | Pipe removed, over 24" diameter (202E35200) | FT | 99 | $48.00 | $12.15 | $65.21 | $8.00 | $47.00 | $38.00 |
| 4 | Guardrail removed (202E38000) | FT | 313 | $7.00 | $6.39 | $2.50 | $1.00 | $5.25 | $6.00 |
| 5 | Excavation (203E10000) | CY | 1,246 | $50.50 | $20.07 | $25.60 | $23.00 | $39.00 | $32.00 |
| 6 | Embankment (203E20000) | CY | 82 | $94.00 | $24.40 | $37.71 | $47.00 | $37.00 | $50.00 |
| 7 | Granular embankment, as per plan (203E35001) | CY | 139 | $102.00 | $86.34 | $91.80 | $143.00 | $100.00 | $90.00 |
| 8 | Subgrade compaction (204E10000) | SY | 316 | $6.00 | $7.92 | $8.91 | $4.00 | $20.00 | $5.00 |
| 9 | Geotextile fabric, as per plan (204E50001) | SY | 1,725 | $2.00 | $1.45 | $4.93 | $5.00 | $2.75 | $2.00 |
| 10 | Guardrail, type MGS with long posts (606E15100) | FT | 312.50 | $29.00 | $23.68 | $27.40 | $27.40 | $37.00 | $31.00 |
| 11 | Rock channel protection, type A with geotextile fabric (601E32004) | CY | 1,027 | $59.00 | $91.53 | $74.10 | $112.00 | $120.00 | $160.00 |
| 12 | Rock channel protection, type C with geotextile fabric (601E32204) | CY | 237 | $71.00 | $92.83 | $73.53 | $119.00 | $150.00 | $160.00 |
| 13 | Soil analysis test (659E00100) | EACH | 2 | $150.00 | $1,600.00 | $75.54 | $50.00 | $1,600.00 | $110.00 |
| 14 | Topsoil (659E00300) | CY | 138 | $55.00 | $61.60 | $48.94 | $10.00 | $39.00 | $65.00 |
| 15 | Seeding and mulching (659E10000) | SY | 1,240 | $3.00 | $4.84 | $1.78 | $2.00 | $4.25 | $2.00 |
| 16 | Repair seeding and mulching (659E14000) | SY | 62 | $3.00 | $5.17 | $2.07 | $2.00 | $9.50 | $4.00 |
| 17 | Commercial fertilizer (659E20000) | TON | 0.17 | $1,250.00 | $2,647.06 | $1,155.47 | $1,500.00 | $2,100.00 | $3,000.00 |
| 18 | Lime (659E31000) | ACRE | 0.26 | $150.00 | $769.23 | $185.00 | $1,200.00 | $1,300.00 | $2,000.00 |
| 19 | Water (659E35000) | MGAL | 10 | $1.00 | $20.00 | $1.00 | $10.00 | $160.00 | $30.00 |
| 20 | Sodding staked (660E25000) | SY | 10 | $100.00 | $40.00 | $48.34 | $20.00 | $74.00 | $42.00 |
| 21 | Sodding unstaked (660E30000) | SY | 51 | $35.00 | $31.38 | $37.71 | $12.00 | $53.00 | $30.00 |
| 22 | Erosion control (832E30000) | EACH | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 23 | Masonry, misc.: headwall, sloped & mitered concret (602E98300) | EACH | 2 | $6,200.00 | $2,200.00 | $4,748.24 | $8,000.00 | $7,900.00 | $9,000.00 |
| 24 | 36" conduit, type A (611E16200) | FT | 112 | $327.00 | $147.33 | $291.74 | $320.00 | $220.00 | $215.00 |
| 25 | Pavement planing, asphalt concrete, 1 1/4" (254E01000) | SY | 239 | $15.00 | $24.27 | $18.00 | $30.00 | $37.00 | $55.00 |
| 26 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 50 | $295.00 | $200.00 | $378.00 | $450.00 | $320.00 | $495.00 |
| 27 | Aggregate base (304E20000) | CY | 278 | $125.00 | $79.14 | $102.45 | $135.00 | $110.00 | $100.00 |
| 28 | Tack coat (407E10000) | GAL | 49 | $5.00 | $71.43 | $4.00 | $3.50 | $1.00 | $6.00 |
| 29 | Asphalt concrete surface course, type 1, (446), PG70-22M (441E10100) | CY | 17 | $395.00 | $235.30 | $767.00 | $650.00 | $420.00 | $710.00 |
| 30 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 13 | $450.00 | $230.77 | $584.00 | $575.00 | $470.00 | $660.00 |
| 31 | RPM (621E00100) | EACH | 6 | $475.00 | $58.34 | $814.40 | $475.00 | $670.00 | $520.00 |
| 32 | Raised pavement marker removed (621E54000) | EACH | 6 | $40.00 | $33.34 | $37.20 | $20.00 | $110.00 | $45.00 |
| 33 | Ground mounted support, no. 2 post (630E02100) | FT | 48.50 | $8.00 | $8.25 | $41.30 | $22.00 | $23.00 | $60.00 |
| 34 | Sign post reflector (630E08600) | EACH | 4 | $25.00 | $37.50 | $128.94 | $44.50 | $47.00 | $275.00 |
| 35 | Removal of ground mounted sign and reerection (630E85100) | EACH | 4 | $50.00 | $25.00 | $127.27 | $65.00 | $68.00 | $400.00 |
| 36 | Removal of ground mounted post support and disposal (630E86002) | EACH | 4 | $10.00 | $25.00 | $21.46 | $20.00 | $21.00 | $375.00 |
| 37 | Edge line, 6" (646E10010) | MI | 0.08 | $24,000 | $4,375.00 | $42,685 | $15,000 | $15,800 | $50,000 |
| 38 | Center line (646E10200) | MI | 0.04 | $34,000 | $7,500.00 | $56,980 | $40,000 | $21,500 | $66,000 |
| 39 | Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384) | EACH | 2 | $3,150.00 | $2,000.00 | $3,220.00 | $3,220.00 | $3,400.00 | $3,200.00 |
| 40 | Work zone lighting system (614E12740) | EACH | 2 | $2,000.00 | $2,000.00 | $3,929.10 | $2,500.00 | $4,200.00 | $11,000 |
| 41 | Asphalt concrete for maintaining traffic (614E13000) | CY | 15 | $350.00 | $186.67 | $274.40 | $100.00 | $530.00 | $200.00 |
| 42 | Barrier reflector, type 1, BI-directional (614E13310) | EACH | 8 | $40.00 | $77.50 | $40.00 | $40.00 | $56.00 | $45.00 |
| 43 | Barrier reflector, type 2, BI-directional (614E13312) | EACH | 15 | $45.00 | $166.67 | $44.00 | $44.00 | $62.00 | $45.00 |
| 44 | Object marker, two way (614E13360) | EACH | 23 | $35.00 | $108.70 | $34.00 | $34.00 | $48.00 | $40.00 |
| 45 | Work zone center line, class I, 642 paint (614E21100) | MI | 0.12 | $6,700.00 | $2,500.00 | $6,650.00 | $6,650.00 | $9,300.00 | $10,000 |
| 46 | Work zone center line, class I, 740.06, type I (614E21200) | MI | 0.18 | $15,000 | $2,083.33 | $14,250 | $14,250 | $20,000 | $17,000 |
| 47 | Work zone edge line, class I, 6", 642 paint (614E22110) | MI | 0.24 | $3,500.00 | $2,500.00 | $3,300.00 | $3,300.00 | $4,600.00 | $9,000.00 |
| 48 | Work zone edge line, class I, 6", 740.06, type I (614E22210) | MI | 0.38 | $10,000 | $1,973.68 | $9,750.00 | $9,750.00 | $13,700 | $14,000 |
| 49 | Work zone stop line, class I, 740.06, type I (614E26400) | FT | 20 | $15.00 | $30.00 | $14.00 | $14.00 | $20.00 | $8.00 |
| 50 | Roads for maintaining traffic (615E10000) | LS | 1 | $2,500.00 | $5,000.00 | $3,543.20 | $10,000 | $4,700.00 | $8,000.00 |
| 51 | Pavement for maintaining traffic, class B, as per plan (615E25001) | SY | 252 | $120.00 | $29.77 | $75.97 | $60.00 | $37.00 | $95.00 |
| 52 | Water (616E10000) | MGAL | 5 | $10.00 | $50.00 | $2.00 | $10.00 | $260.00 | $20.00 |
| 53 | Portable barrier, unanchored (622E41100) | FT | 350 | $22.00 | $28.58 | $41.01 | $50.00 | $21.00 | $50.00 |
| 54 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $21,000 | $130,000 | $20,189 | $500.00 | $34,400 | $15,000 |
| 55 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $10,000 | $16,000 | $8,500.00 | $20,000 | $5,900.00 | $8,000.00 |
| 56 | Maintaining traffic (614E11000) | LS | 1 | $30,000 | $5,000.00 | $35,050 | $30,000 | $10,100 | $7,000.00 |
| 57 | Field office, type B (619E16010) | MNTH | 4 | $1,000.00 | $1,250.00 | $3,000.00 | $1,500.00 | $2,600.00 | $2,100.00 |
| 58 | Construction layout stakes and surveying (623E10000) | LS | 1 | $4,400.00 | $8,000.00 | $4,598.00 | $2,000.00 | $8,900.00 | $11,000 |
| 59 | Mobilization (624E10000) | LS | 1 | $15,000 | $10,000 | $29,370 | $26,300 | $25,299 | $25,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 10, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.