SCI-US 52-15.06 (RELOCATION). Let by Ohio DOT on April 10, 2025, SCI. 3 bids received; low bid $1,898,155 by Allard Excavation LLC, +25% against the engineer's estimate of $1,515,000.

Owner
Ohio DOT
Letting
10 APR 2025
Pay items
82
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Allard Excavation LLC$1,898,155Low+25%
2D G M Inc$2,059,322+8.0%+36%
3Alan Stone Co Inc$2,200,403+16%+45%
ODOT contract 250199: bids by rank

Engineer's estimate: $1,515,000.

Bid tabulation

LinePay itemUnitQuantity1. Allard Excavation LLC2. D G M Inc3. Alan Stone Co Inc
1Clearing and grubbing (201E11000)LS1$11,634$25,000$12,000
2Headwall removed (202E20010)EACH1$196.00$500.00$480.00
3Pavement removed (202E23000)SY5,994$14.00$7.00$20.00
4Guardrail removed (202E38000)FT1,803$3.00$1.00$3.00
5Mailbox removed (202E53100)EACH2$54.00$50.00$130.00
6Fence removed (202E75000)FT439$2.00$5.00$4.50
7Gate removed (202E75250)EACH1$48.00$100.00$480.00
8Excavation (203E10000)CY329$18.00$30.00$40.00
9Embankment (203E20000)CY11,056$25.00$20.50$35.00
10Subgrade compaction (204E10000)SY5,216$2.00$3.00$3.50
11Proof rolling (204E45000)HR2$259.00$75.00$220.00
12Guardrail, type MGS (606E15050)FT675$21.10$24.00$25.00
13Flared end section (606E20000)EACH1$40.00$80.00$80.00
14Rounded end section (606E20050)EACH2$60.00$80.00$80.00
15Anchor assembly, type E (606E26100)EACH1$2,260.00$2,800.00$2,800.00
16Anchor assembly, type T (606E26500)EACH4$1,050.00$1,200.00$1,200.00
17Monument assembly, type C (623E38500)EACH10$1,134.00$1,000.00$1,400.00
18Special - mailbox support (690E50000)EACH2$200.00$200.00$100.00
19Inspection and compaction testing of unbound materials (878E25000)LS1$25,847$12,000$17,500
20Rock channel protection, type C with geotextile fabric (601E32204)CY45$64.00$120.00$280.00
21Topsoil (659E00300)CY883$32.00$20.00$20.00
22Seeding and mulching, class 1 (659E00500)SY7,952$1.00$1.35$1.50
23Repair seeding and mulching (659E14000)SY398$0.05$0.05$2.00
24Inter-seeding (659E15000)SY398$0.05$0.05$1.00
25Commercial fertilizer (659E20000)TON1.07$500.00$1,500.00$600.00
26Lime (659E31000)ACRE1.64$500.00$300.00$800.00
27Water (659E35000)MGAL43$1.00$1.00$100.00
28Slope erosion protection mat, type B (670E00520)SY931$3.00$2.50$9.00
29Ditch erosion protection mat, type B (670E00720)SY81$3.00$2.50$13.00
30Storm water pollution prevention plan (832E15000)LS1$3,406.00$3,000.00$2,000.00
31Storm water pollution prevention inspections (832E15002)LS1$13,302$7,500.00$8,500.00
32Storm water pollution prevention inspection software (832E15010)LS1$9,970.00$9,000.00$9,200.00
33Erosion control (832E30000)EACH30,000$1.00$1.00$1.00
34Concrete masonry (602E20000)CY0.60$5,768.00$2,500.00$2,100.00
35Aggregate drains (605E31100)FT1,029$16.00$15.00$9.50
3630" conduit, type A, 706.02 (611E13200)FT37$422.00$405.00$420.00
37Asphalt concrete base, PG64-22, (449) (301E56000)CY1,069$199.00$205.00$260.00
38Aggregate base (304E20000)CY1,011$61.00$90.00$70.00
39Non-tracking tack coat (407E20000)GAL775$3.90$3.90$6.50
40Aggregate, single chip seal, type A (422E11000)SY643$14.35$14.00$40.00
41Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000)CY163$230.00$236.00$300.00
42Asphalt concrete intermediate course, type 2, (449) (441E70300)CY229$287.00$294.00$290.00
43Asphalt concrete surface course, type 1, (449), (driveways) (441E70500)CY3$590.00$600.00$1,200.00
44RPM (621E00100)EACH23$165.00$165.00$190.00
45Pull box removed (625E31510)EACH3$250.00$250.00$290.00
46Barrier reflector, type 3, bidirectional (626E00112)EACH17$10.00$13.00$15.00
47Ground mounted support, no. 3 post (630E03100)FT61$15.00$20.00$15.00
48Sign, flat sheet (630E80100)SF45.90$22.00$25.00$25.00
49Removal of ground mounted sign and disposal (630E84900)EACH11$12.00$20.00$25.00
50Removal of ground mounted post support and disposal (630E86002)EACH8$12.00$20.00$25.00
51Sign flasher assembly, as per plan (631E92001)EACH1$10,300$12,000$12,000
52Removal, misc.: removal of sign flasher assembly (631E94490)EACH1$1,136.00$1,000.00$1,100.00
53Sign lighting, misc.: removal of electrical condui (631E97900)FT686$2.00$1.50$1.00
54Edge line, 6" (644E00104)MI0.54$8,580.00$9,000.00$9,600.00
55Center line (644E00300)MI0.34$11,440$12,000$12,000
56Stop line (644E00500)FT12$13.00$13.00$8.50
57Transverse/diagonal line (644E00700)FT109$13.00$10.00$8.50
58Island marking (644E00900)SF48$10.00$5.00$8.00
59School symbol marking, 96" (644E01110)EACH1$900.00$1,000.00$570.00
60Traffic compacted surface, type A or B (410E12000)CY50$74.00$60.00$80.00
61Law enforcement officer with patrol car for assistance (614E11110)HR80$85.00$70.00$95.00
62Increased barrier delineation (614E11630)FT2,390$1.50$2.00$1.50
63Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384)EACH14$2,135.00$2,200.00$2,500.00
64Asphalt concrete for maintaining traffic (614E13000)CY50$200.00$150.00$265.00
65Object marker, two way (614E13360)EACH54$36.00$40.00$40.00
66Portable changeable message sign, as per plan (614E18601)SNMT8$1,025.00$1,500.00$1,700.00
67Work zone center line, class I, 740.06, type I (614E21200)MI0.01$56,570$60,000$60,000
68Work zone edge line, class I, 4", 740.06, type I (614E22200)MI0.99$7,750.00$9,000.00$8,000.00
69Work zone dotted line, class I, 4", 740.06, type I (614E24400)FT118$2.75$3.00$3.00
70Work zone stop line, class I, 740.06, type I (614E26400)FT24$14.00$15.00$15.00
71Pavement for maintaining traffic, class A (615E20000)SY84$151.00$100.00$275.00
72Water (616E10000)MGAL24$1.00$1.00$0.10
73Portable barrier, unanchored (622E41100)FT960$19.84$17.00$20.00
74Portable barrier, anchored (622E41110)FT1,430$25.53$24.00$26.00
75Steel piles, misc.: W33X169 steel beam, furnished, (507E00400)FT1,035$175.00$193.00$150.00
76Drilled shafts, 42" diameter, above bedrock, as per plan (524E94803)FT733$125.00$110.00$130.00
77Drilled shafts, 42" diameter, into bedrock, as per plan (524E94805)FT230$139.00$400.00$235.00
78Premium for contract performance bond and for payment bond (103E05000)LS1$14,100$59,000$22,600
79Maintaining traffic (614E11000)LS1$299,000$419,000$340,000
80Field office, type B (619E16010)MNTH7$1,500.00$1,250.00$1,400.00
81Construction layout stakes and surveying (623E10000)LS1$31,080$12,000$23,000
82Mobilization (624E10000)LS1$85,000$100,000$50,000
ODOT contract 250199: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of April 10, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy