ODOT contract 250219 bid tabulation
LAW-SR 141-05.70 (CULVERT REPLACEMENT). Let by Ohio DOT on April 24, 2025, LAW. 4 bids received; low bid $662,270 by Skeens Excavating Inc, -21% against the engineer's estimate of $835,000.
- Owner
- Ohio DOT
- Letting
- 24 APR 2025
- Pay items
- 68
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Skeens Excavating Inc | $662,270 | Low | -21% |
| 2 | D G M Inc | $1,038,771 | +57% | +24% |
| 3 | R C Construction Company and Son Inc | $1,040,904 | +57% | +25% |
| 4 | Axis Civil Construction LLC | $1,157,165 | +75% | +39% |
Engineer's estimate: $835,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Skeens Excavating Inc | 2. D G M Inc | 3. R C Construction Company and Son Inc | 4. Axis Civil Construction LLC |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $800.00 | $50,000 | $10,000 | $20,000 |
| 2 | Headwall removed (202E20010) | EACH | 3 | $120.00 | $400.00 | $1,000.00 | $700.00 |
| 3 | Pavement removed (202E23000) | SY | 476 | $10.00 | $12.00 | $35.00 | $18.00 |
| 4 | Pipe removed, 24" and under (202E35100) | FT | 240 | $12.00 | $20.00 | $50.00 | $75.00 |
| 5 | Guardrail removed (202E38000) | FT | 96 | $2.00 | $1.00 | $5.00 | $10.00 |
| 6 | Excavation (203E10000) | CY | 251 | $20.00 | $52.50 | $25.00 | $45.00 |
| 7 | Embankment (203E20000) | CY | 644 | $20.00 | $52.50 | $75.00 | $45.00 |
| 8 | Subgrade compaction (204E10000) | SY | 707 | $2.00 | $6.00 | $2.00 | $6.00 |
| 9 | 4" concrete walk (608E10000) | SF | 26 | $50.00 | $40.00 | $100.00 | $60.00 |
| 10 | Special - mailbox support system, single (690E50100) | EACH | 3 | $100.00 | $250.00 | $275.00 | $800.00 |
| 11 | Seeding and mulching (659E10000) | SY | 1,119 | $1.00 | $4.00 | $10.00 | $3.00 |
| 12 | Repair seeding and mulching (659E14000) | SY | 56 | $1.00 | $0.05 | $0.20 | $3.00 |
| 13 | Commercial fertilizer (659E20000) | TON | 0.26 | $100.00 | $1,500.00 | $1,950.00 | $1,250.00 |
| 14 | Lime (659E31000) | ACRE | 0.24 | $100.00 | $300.00 | $1,200.00 | $150.00 |
| 15 | Water (659E35000) | MGAL | 7 | $1.00 | $1.00 | $1.00 | $1.00 |
| 16 | Erosion control (832E30000) | EACH | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 17 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 2 | $200.00 | $250.00 | $500.00 | $450.00 |
| 18 | Concrete masonry (602E20000) | CY | 1.40 | $500.00 | $2,500.00 | $1,800.00 | $5,500.00 |
| 19 | 6" shallow pipe underdrains (605E11100) | FT | 448 | $4.00 | $25.00 | $45.00 | $32.00 |
| 20 | 4" conduit, type F (611E00406) | FT | 30 | $15.00 | $8.00 | $25.00 | $25.00 |
| 21 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 30 | $20.00 | $25.00 | $25.00 | $30.00 |
| 22 | 6" conduit, type B (611E00900) | FT | 47 | $25.00 | $30.00 | $25.00 | $30.00 |
| 23 | 12" conduit, type D (611E04900) | FT | 102 | $60.00 | $80.00 | $250.00 | $120.00 |
| 24 | 24" conduit, type B (611E10400) | FT | 60 | $80.00 | $225.00 | $275.00 | $180.00 |
| 25 | 24" conduit, type C (611E10600) | FT | 18 | $80.00 | $180.00 | $275.00 | $260.00 |
| 26 | 36" conduit, type C (611E16600) | FT | 57 | $120.00 | $300.00 | $375.00 | $243.00 |
| 27 | 36" conduit, type D (611E16900) | FT | 92 | $120.00 | $250.00 | $375.00 | $280.00 |
| 28 | Catch basin, no. 2-3 (611E98510) | EACH | 1 | $3,000.00 | $2,500.00 | $7,500.00 | $6,500.00 |
| 29 | Manhole, no. 3 (611E99574) | EACH | 1 | $3,000.00 | $10,000 | $10,000 | $10,000 |
| 30 | Precast reinforced concrete outlet (611E99710) | EACH | 1 | $250.00 | $300.00 | $275.00 | $800.00 |
| 31 | Full depth pavement sawing (252E01500) | FT | 34 | $10.00 | $15.00 | $100.00 | $8.00 |
| 32 | Pavement repair (253E02000) | CY | 50 | $240.00 | $390.00 | $50.00 | $350.00 |
| 33 | Pavement planing, asphalt concrete, variable thick (254E01000) | SY | 254 | $35.00 | $35.00 | $30.00 | $35.00 |
| 34 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 113 | $280.00 | $325.00 | $495.00 | $500.00 |
| 35 | Aggregate base (304E20000) | CY | 118 | $120.00 | $100.00 | $150.00 | $180.00 |
| 36 | Tack coat (407E10000) | GAL | 283 | $3.00 | $2.50 | $10.00 | $6.00 |
| 37 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 169 | $180.00 | $195.00 | $525.00 | $550.00 |
| 38 | 6" non-reinforced concrete pavement, class QC 1P (452E10010) | SY | 31 | $180.00 | $120.00 | $225.00 | $295.00 |
| 39 | Compacted aggregate (617E10100) | CY | 220 | $10.00 | $70.00 | $150.00 | $160.00 |
| 40 | RPM (621E00100) | EACH | 2 | $1,000.00 | $1,250.00 | $2,000.00 | $1,250.00 |
| 41 | Raised pavement marker removed (621E54000) | EACH | 2 | $100.00 | $1.00 | $100.00 | $65.00 |
| 42 | Edge line, 6", type 1 (642E00104) | MI | 0.10 | $11,000 | $11,000 | $18,500 | $9,850.00 |
| 43 | Center line, type 1 (642E00300) | MI | 0.05 | $22,000 | $20,000 | $32,000 | $18,500 |
| 44 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 8 | $30.00 | $60.00 | $65.00 | $75.00 |
| 45 | Detour signing (614E12420) | LS | 1 | $7,000.00 | $12,000 | $35,000 | $15,000 |
| 46 | Water (616E10000) | MGAL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 47 | Portions of structure removed, as per plan (202E11201) | LS | 1 | $25,000 | $50,000 | $15,000 | $20,000 |
| 48 | Removal misc.:gabion walls (202E98000) | LS | 1 | $5,000.00 | $1,000.00 | $10,000 | $5,000.00 |
| 49 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $25,000 | $500.00 | $15,000 | $20,000 |
| 50 | Unclassified excavation, as per plan (503E21301) | LS | 1 | $25,000 | $7,500.00 | $15,000 | $20,000 |
| 51 | Rock excavation, as per plan (503E31101) | CY | 41 | $200.00 | $60.00 | $200.00 | $280.00 |
| 52 | Epoxy coated steel reinforcement (509E10000) | LB | 7,174 | $2.20 | $2.50 | $4.00 | $3.80 |
| 53 | Class QC1 concrete, retaining/wingwall not including footing (511E46010) | CY | 17 | $1,500.00 | $1,900.00 | $950.00 | $2,750.00 |
| 54 | Class QC1 concrete, footing (511E46510) | CY | 35 | $1,500.00 | $1,300.00 | $950.00 | $1,080.00 |
| 55 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 67 | $80.00 | $45.00 | $75.00 | $35.00 |
| 56 | Type 2 waterproofing (512E33000) | SY | 356 | $12.00 | $20.00 | $45.00 | $32.00 |
| 57 | 1" preformed expansion joint filler (516E13600) | SF | 33 | $10.00 | $15.00 | $50.00 | $12.00 |
| 58 | Porous backfill with geotextile fabric (518E21200) | CY | 16 | $150.00 | $150.00 | $200.00 | $300.00 |
| 59 | Special - structures preconstruction condition sur (530E00200) | LS | 1 | $1,000.00 | $3,000.00 | $10,000 | $2,500.00 |
| 60 | Riprap, type D, as per plan (601E11001) | SY | 5 | $500.00 | $400.00 | $375.00 | $600.00 |
| 61 | Rock channel protection, type A with geotextile fabric (601E32004) | CY | 53 | $180.00 | $110.00 | $190.00 | $160.00 |
| 62 | 10' X 4' conduit, type A, 706.05, as per plan (611E94981) | FT | 121 | $1,300.00 | $2,750.00 | $1,500.00 | $2,900.00 |
| 63 | Catch basin frame and grate, as per plan (611E98651) | EACH | 1 | $300.00 | $7,500.00 | $1,900.00 | $3,900.00 |
| 64 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $6,800.00 | $50,000 | $40,000 | $8,500.00 |
| 65 | Maintaining traffic (614E11000) | LS | 1 | $15,000 | $50,000 | $40,000 | $12,500 |
| 66 | Field office, type A (619E16000) | MNTH | 2 | $10.00 | $1,000.00 | $500.00 | $2,000.00 |
| 67 | Construction layout stakes and surveying (623E10000) | LS | 1 | $15,000 | $8,000.00 | $25,000 | $15,000 |
| 68 | Mobilization (624E10000) | LS | 1 | $65,000 | $40,000 | $35,000 | $60,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 24, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.