ODOT contract 250232 bid tabulation
BEL-SR 7-10.96 (SLIDE REPAIR). Let by Ohio DOT on April 24, 2025, BEL. 4 bids received; low bid $887,121 by Ohio-West Virginia Excavating Co, -21% against the engineer's estimate of $1,121,000.
- Owner
- Ohio DOT
- Letting
- 24 APR 2025
- Pay items
- 66
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Ohio-West Virginia Excavating Co | $887,121 | Low | -21% |
| 2 | Alan Stone Co Inc | $1,340,581 | +51% | +20% |
| 3 | Craig Edward Susany Inc | $1,374,829 | +55% | +23% |
| 4 | Shelly & Sands Inc | $1,430,554 | +61% | +28% |
Engineer's estimate: $1,121,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ohio-West Virginia Excavating Co | 2. Alan Stone Co Inc | 3. Craig Edward Susany Inc | 4. Shelly & Sands Inc |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $5,000.00 | $200,000 | $10,000 | $165,000 |
| 2 | Pavement removed (202E23000) | SY | 622 | $15.00 | $13.00 | $25.00 | $13.00 |
| 3 | Pipe removed, 24" and under (202E35100) | FT | 11 | $55.00 | $35.00 | $25.00 | $20.00 |
| 4 | Guardrail removed (202E38000) | FT | 151 | $12.00 | $6.00 | $3.50 | $3.50 |
| 5 | Fence removed (202E75000) | FT | 260 | $5.00 | $20.00 | $3.00 | $7.50 |
| 6 | Removal misc.:, inclinometer (202E98100) | EACH | 1 | $800.00 | $1,400.00 | $100.00 | $200.00 |
| 7 | Excavation (203E10000) | CY | 1,580 | $37.00 | $35.00 | $70.00 | $63.00 |
| 8 | Embankment (203E20000) | CY | 13 | $140.00 | $45.00 | $200.00 | $110.00 |
| 9 | Subgrade compaction (204E10000) | SY | 2,072 | $1.50 | $3.50 | $3.00 | $3.00 |
| 10 | Proof rolling (204E45000) | HR | 0.69 | $200.00 | $500.00 | $250.00 | $350.00 |
| 11 | Guardrail, type MGS half post spacing with long posts (606E15200) | FT | 262.50 | $48.00 | $40.00 | $50.00 | $47.50 |
| 12 | Anchor assembly, MGS type T (606E26550) | EACH | 1 | $1,300.00 | $1,300.00 | $2,500.00 | $1,250.00 |
| 13 | Fence, misc.:, rock catchment fence (607E98000) | FT | 264 | $556.00 | $625.00 | $525.00 | $525.00 |
| 14 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 1 | $800.00 | $580.00 | $200.00 | $350.00 |
| 15 | Rock channel protection, type B with filter (601E32100) | CY | 1,881 | $84.15 | $130.00 | $180.00 | $150.00 |
| 16 | Rock channel protection, type C with filter (601E32200) | CY | 4 | $150.00 | $300.00 | $300.00 | $330.00 |
| 17 | Soil analysis test (659E00100) | EACH | 2 | $150.00 | $300.00 | $25.00 | $150.00 |
| 18 | Topsoil (659E00300) | CY | 34 | $65.00 | $80.00 | $200.00 | $45.00 |
| 19 | Seeding and mulching (659E10000) | SY | 306 | $8.00 | $16.00 | $10.00 | $8.50 |
| 20 | Repair seeding and mulching (659E14000) | SY | 15 | $3.00 | $20.00 | $10.00 | $8.50 |
| 21 | Inter-seeding (659E15000) | SY | 15 | $2.00 | $20.00 | $5.00 | $8.50 |
| 22 | Commercial fertilizer (659E20000) | TON | 0.04 | $1,350.00 | $630.00 | $300.00 | $1,250.00 |
| 23 | Lime (659E31000) | ACRE | 0.07 | $160.00 | $910.00 | $200.00 | $150.00 |
| 24 | Water (659E35000) | MGAL | 2 | $1.00 | $110.00 | $1.00 | $1.00 |
| 25 | Erosion control (832E30000) | EACH | 10,130 | $1.00 | $1.00 | $1.00 | $1.00 |
| 26 | Concrete masonry (602E20000) | CY | 0.20 | $13,000 | $6,800.00 | $3,000.00 | $12,000 |
| 27 | 6" base pipe underdrains with geotextile fabric (605E14020) | FT | 280 | $15.00 | $20.00 | $25.00 | $22.00 |
| 28 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 30 | $33.00 | $190.00 | $25.00 | $35.00 |
| 29 | 12" conduit, type C (611E04600) | FT | 11 | $410.00 | $180.00 | $148.00 | $150.00 |
| 30 | 15" conduit, type D (611E06400) | FT | 57 | $260.00 | $130.00 | $150.00 | $112.00 |
| 31 | Precast reinforced concrete outlet (611E99710) | EACH | 1 | $375.00 | $1,000.00 | $250.00 | $400.00 |
| 32 | Pavement planing, asphalt concrete(1.25") (254E01000) | SY | 662 | $7.00 | $15.00 | $16.00 | $15.00 |
| 33 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 105 | $237.00 | $300.00 | $330.00 | $300.00 |
| 34 | Aggregate base (304E20000) | CY | 259 | $102.00 | $110.00 | $130.00 | $125.00 |
| 35 | Tack coat (407E10000) | GAL | 139 | $7.00 | $4.00 | $6.00 | $3.50 |
| 36 | Asphalt concrete surface course, type 1, (449), PG70-22M (441E70100) | CY | 45 | $330.00 | $550.00 | $530.00 | $500.00 |
| 37 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 30 | $330.00 | $460.00 | $530.00 | $500.00 |
| 38 | Rumble strips, shoulder (asphalt concrete) (618E40100) | FT | 643 | $10.00 | $20.00 | $10.00 | $9.00 |
| 39 | RPM (621E00100) | EACH | 56 | $50.00 | $55.00 | $50.00 | $50.00 |
| 40 | Raised pavement marker removed (621E54000) | EACH | 56 | $6.00 | $15.00 | $10.00 | $10.00 |
| 41 | Barrier reflector, type 2 , one way (626E00110) | EACH | 5 | $50.00 | $25.00 | $12.00 | $12.00 |
| 42 | Ground mounted support, no. 3 post (630E03100) | FT | 34.50 | $12.00 | $30.00 | $25.00 | $25.00 |
| 43 | Removal of ground mounted sign and reerection (630E85100) | EACH | 1 | $50.00 | $110.00 | $200.00 | $100.00 |
| 44 | Wet reflective epoxy pavement marking, edge line, 6" (807E12010) | MI | 0.89 | $9,000.00 | $10,000 | $9,000.00 | $8,975.00 |
| 45 | Wet reflective epoxy pavement marking, lane line, 6" (807E12110) | MI | 0.85 | $6,000.00 | $6,000.00 | $6,000.00 | $5,822.00 |
| 46 | Grooving for 6" recessed pavement marking, (asphalt) (850E10010) | MI | 1.74 | $2,800.00 | $3,000.00 | $3,000.00 | $2,735.00 |
| 47 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 50 | $75.00 | $150.00 | $100.00 | $104.00 |
| 48 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 2 | $3,000.00 | $2,500.00 | $2,950.00 | $2,350.00 |
| 49 | Barrier reflector, type 1 (one way) (614E13310) | EACH | 38 | $28.00 | $30.00 | $26.00 | $11.00 |
| 50 | Object marker, one way (614E13350) | EACH | 38 | $30.00 | $32.00 | $28.00 | $17.00 |
| 51 | Work zone lane line, class I, 6", 642 paint (614E20110) | MI | 0.81 | $960.00 | $1,000.00 | $900.00 | $895.00 |
| 52 | Work zone edge line, class I, 6", 642 paint (614E22110) | MI | 0.31 | $2,600.00 | $2,900.00 | $2,600.00 | $2,595.00 |
| 53 | Work zone edge line, class I, 6", 873 (614E22326) | MI | 1.04 | $15,000 | $17,000 | $15,000 | $14,750 |
| 54 | Work zone dotted line, class I, 6", 873 (614E24122) | FT | 1,515 | $1.00 | $1.00 | $2.00 | $0.95 |
| 55 | Water (616E10000) | MGAL | 5 | $10.00 | $0.20 | $1.00 | $70.00 |
| 56 | Portable barrier, unanchored (622E41100) | FT | 1,830 | $14.00 | $21.00 | $45.00 | $30.00 |
| 57 | Steel piles, misc.:HP12X53, furnished (507E00400) | FT | 1,792 | $43.00 | $45.00 | $70.00 | $41.00 |
| 58 | Steel piles, misc.: HP 12X53 steel beam splice (507E00410) | EACH | 5 | $500.00 | $300.00 | $1,000.00 | $600.00 |
| 59 | Drilled shafts, 24" diameter, above bedrock, as per plan (524E94503) | FT | 1,192 | $35.00 | $50.00 | $100.00 | $78.00 |
| 60 | Drilled shafts, 24" diameter, into bedrock, as per plan (524E94505) | FT | 408 | $85.00 | $95.00 | $100.00 | $179.00 |
| 61 | Drilled shafts, misc.: plug pile 30" diameter, unr (524E95000) | FT | 384 | $78.00 | $80.00 | $120.00 | $114.00 |
| 62 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $10,000 | $15,000 | $40,000 | $8,300.00 |
| 63 | Maintaining traffic (614E11000) | LS | 1 | $35,000 | $25,000 | $6,000.00 | $34,596 |
| 64 | Field office, type B (619E16010) | MNTH | 13 | $1,500.00 | $1,000.00 | $2,000.00 | $3,250.00 |
| 65 | Construction layout stakes and surveying (623E10000) | LS | 1 | $5,000.00 | $20,000 | $7,000.00 | $17,500 |
| 66 | Mobilization (624E10000) | LS | 1 | $20,000 | $91,000 | $15,000 | $65,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 24, 2025. Compiled by Mirage Metrics.