ODOT contract 250378 bid tabulation
FUL-SR 109-16.98 Bridge Replace (BRIDGE REPLACEMENT (1 BRIDGE)). Let by Ohio DOT on August 14, 2025, FUL. 4 bids received; low bid $1,079,950 by Miller Bros Const Inc, -16% against the engineer's estimate of $1,288,000.
- Owner
- Ohio DOT
- Letting
- 14 AUG 2025
- Pay items
- 60
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Miller Bros Const Inc | $1,079,950 | Low | -16% |
| 2 | Vernon Nagel Inc | $1,097,097 | +2.0% | -15% |
| 3 | E S Wagner Company | $1,144,141 | +6.0% | -11% |
| 4 | R G Zachrich Construction Inc | $1,208,647 | +12% | -6.0% |
Engineer's estimate: $1,288,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Miller Bros Const Inc | 2. Vernon Nagel Inc | 3. E S Wagner Company | 4. R G Zachrich Construction Inc |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $717.52 | $2,000.00 | $3,000.00 | $1,000.00 |
| 2 | Pavement removed (202E23000) | SY | 496 | $15.62 | $15.00 | $10.00 | $12.00 |
| 3 | Pipe removed, 24" and under (202E35100) | FT | 40 | $21.13 | $3.00 | $15.00 | $30.00 |
| 4 | Guardrail removed (202E38000) | FT | 508 | $2.00 | $4.00 | $3.00 | $3.00 |
| 5 | Anchor assembly removed, type E (202E42010) | EACH | 3 | $145.00 | $145.00 | $250.00 | $250.00 |
| 6 | Anchor assembly removed, type T (202E42040) | EACH | 3 | $95.00 | $95.00 | $200.00 | $200.00 |
| 7 | Bridge terminal assembly removed (202E47000) | EACH | 4 | $75.00 | $75.00 | $200.00 | $200.00 |
| 8 | Subgrade compaction (204E10000) | SY | 267 | $4.47 | $1.00 | $6.00 | $2.50 |
| 9 | Linear grading (209E60200) | STA | 4 | $125.89 | $40.00 | $2,200.00 | $2,000.00 |
| 10 | Guardrail, type MGS (606E15050) | FT | 419 | $19.00 | $19.00 | $22.00 | $22.00 |
| 11 | Anchor assembly, MGS type E (606E26150) | EACH | 3 | $2,495.00 | $2,495.00 | $2,675.00 | $2,675.00 |
| 12 | Anchor assembly, type T (606E26500) | EACH | 3 | $920.00 | $920.00 | $1,450.00 | $1,450.00 |
| 13 | Bridge terminal assembly, type TST (606E32160) | EACH | 4 | $1,840.00 | $1,840.00 | $2,650.00 | $2,650.00 |
| 14 | Topsoil (659E00300) | CY | 16 | $76.79 | $50.00 | $115.00 | $45.00 |
| 15 | Seeding and mulching (659E10000) | SY | 279 | $9.00 | $9.00 | $9.00 | $9.00 |
| 16 | Repair seeding and mulching (659E14000) | SY | 14 | $12.00 | $12.00 | $12.00 | $12.00 |
| 17 | Inter-seeding (659E15000) | SY | 14 | $5.00 | $5.00 | $5.00 | $5.00 |
| 18 | Commercial fertilizer (659E20000) | TON | 0.10 | $600.00 | $600.00 | $600.00 | $600.00 |
| 19 | Water (659E35000) | MGAL | 1 | $30.00 | $10.00 | $30.00 | $30.00 |
| 20 | Erosion control (832E30000) | EACH | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 21 | 12" conduit, type D (611E04900) | FT | 72 | $63.64 | $40.00 | $45.00 | $80.00 |
| 22 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 45 | $300.00 | $300.00 | $350.00 | $375.00 |
| 23 | Aggregate base (304E20000) | CY | 46 | $137.51 | $65.00 | $120.00 | $80.00 |
| 24 | Non-tracking tack coat (407E20000) | GAL | 26 | $1.00 | $1.00 | $1.00 | $4.00 |
| 25 | Asphalt concrete surface course, type 1, (448), PG64-22 (441E50000) | CY | 30 | $390.00 | $390.00 | $425.00 | $400.00 |
| 26 | Detour signing (614E12420) | LS | 1 | $11,000 | $11,000 | $11,000 | $14,000 |
| 27 | Replacement sign (614E12500) | EACH | 3 | $250.00 | $250.00 | $250.00 | $250.00 |
| 28 | Portable changeable message sign (614E18600) | SNMT | 6 | $1,150.00 | $1,150.00 | $1,800.00 | $1,150.00 |
| 29 | Raised pavement marker removed (621E54000) | EACH | 3 | $26.13 | $25.00 | $60.00 | $100.00 |
| 30 | Portions of structure removed, as per plan (202E11201) | LS | 1 | $32,902 | $30,000 | $47,300 | $50,000 |
| 31 | Wearing course removed (202E23500) | SY | 190 | $12.25 | $12.25 | $10.00 | $12.00 |
| 32 | Unclassified excavation, as per plan (503E21101) | CY | 1,064 | $48.78 | $40.00 | $59.00 | $63.00 |
| 33 | Pile driving equipment mobilization (505E11100) | LS | 1 | $13,042 | $82,000 | $10,000 | $16,500 |
| 34 | 14" cast-in-place reinforced concrete piles, driven (507E00600) | FT | 1,615 | $19.03 | $6.00 | $27.50 | $52.80 |
| 35 | 14" cast-in-place reinforced concrete piles, furnished (507E00650) | FT | 1,785 | $45.10 | $45.00 | $34.00 | $48.00 |
| 36 | Epoxy coated steel reinforcement (509E10000) | LB | 25,137 | $1.48 | $1.50 | $1.50 | $1.30 |
| 37 | Class QC2 concrete, superstructure (511E31610) | CY | 70 | $1,059.20 | $1,000.00 | $1,185.00 | $1,318.00 |
| 38 | Class QC1 concrete with QC/QA, abutment not including footing (511E44112) | CY | 43 | $776.45 | $800.00 | $1,153.00 | $1,100.00 |
| 39 | Class QC1 concrete with QC/QA, footing (511E46512) | CY | 102 | $552.55 | $525.00 | $548.00 | $400.00 |
| 40 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 93 | $44.30 | $28.00 | $22.00 | $32.00 |
| 41 | Prestressed concrete composite box beam bridge members, level 1, CB27-48, as per plan (515E12071) | EACH | 11 | $21,681 | $21,700 | $21,000 | $21,764 |
| 42 | 1" preformed expansion joint filler (516E13600) | SF | 3 | $41.54 | $8.00 | $26.00 | $12.50 |
| 43 | 2" preformed expansion joint filler (516E13900) | SF | 18 | $9.15 | $8.00 | $12.00 | $13.50 |
| 44 | Semi-integral abutment expansion joint seal (516E14020) | FT | 88 | $29.31 | $40.00 | $35.00 | $42.00 |
| 45 | 1/8" preformed bearing pad, type CDP (516E41100) | EACH | 22 | $34.54 | $52.00 | $68.00 | $31.00 |
| 46 | Elastomeric bearing with internal laminates only (neoprene) (516E43100) | EACH | 44 | $129.42 | $120.00 | $164.00 | $90.00 |
| 47 | Railing (three steel tube bridge railing) (517E70100) | FT | 146 | $458.00 | $458.00 | $442.00 | $442.00 |
| 48 | Porous backfill with geotextile fabric (518E21200) | CY | 76 | $120.65 | $100.00 | $130.00 | $125.00 |
| 49 | Special - steel drip strip (518E22300) | FT | 146 | $18.78 | $12.00 | $27.00 | $20.00 |
| 50 | 6" perforated corrugated plastic pipe (518E40000) | FT | 152 | $6.78 | $14.00 | $9.00 | $12.00 |
| 51 | 6" non-perforated corrugated plastic pipe (518E40012) | FT | 40 | $13.16 | $14.00 | $26.00 | $12.00 |
| 52 | Reinforced concrete approach slabs (T=15") (526E25000) | SY | 245 | $345.25 | $300.00 | $350.00 | $332.00 |
| 53 | Type A installation (526E90010) | FT | 88 | $139.02 | $150.00 | $186.50 | $230.00 |
| 54 | Rock channel protection, type C with filter (601E32200) | CY | 354 | $97.64 | $100.00 | $120.00 | $102.00 |
| 55 | Polymer modified asphalt expansion joint system (846E00110) | CF | 37 | $655.19 | $660.00 | $655.19 | $655.19 |
| 56 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $5,233.39 | $12,000 | $5,500.00 | $17,846 |
| 57 | Maintaining traffic (614E11000) | LS | 1 | $4,627.93 | $3,850.00 | $3,850.00 | $5,000.00 |
| 58 | Construction layout stakes and surveying (623E10000) | LS | 1 | $7,290.00 | $11,000 | $5.00 | $8,000.00 |
| 59 | Mobilization (624E10000) | LS | 1 | $53,997 | $50,000 | $57,000 | $40,000 |
| 100 | Dynamic load testing (523E20000) | EACH | 1 | $5,862.26 | $3,800.00 | $5,275.00 | $4,200.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of August 14, 2025. Compiled by Mirage Metrics.