ODOT contract 250380 bid tabulation
LAK-SR 283-14.34 Deck (BRIDGE REPAIR). Let by Ohio DOT on August 14, 2025, LAK. 5 bids received; low bid $4,709,801 by J D Williamson Construction Co Inc, +7.9% against the engineer's estimate of $4,366,000.
- Owner
- Ohio DOT
- Letting
- 14 AUG 2025
- Pay items
- 138
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | J D Williamson Construction Co Inc | $4,709,801 | Low | +8.0% |
| 2 | Ruhlin Company | $4,980,763 | +6.0% | +14% |
| 3 | Ohio Concrete Maintenance LLC | $5,369,274 | +14% | +23% |
| 4 | Union Industrial Contractors Inc | $5,705,568 | +21% | +31% |
| 5 | Catts Construction Inc | $6,140,052 | +30% | +41% |
Engineer's estimate: $4,366,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. J D Williamson Construction Co Inc | 2. Ruhlin Company | 3. Ohio Concrete Maintenance LLC | 4. Union Industrial Contractors Inc | 5. Catts Construction Inc |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $10,000 | $60,000 | $8,000.00 | $5,000.00 | $1,800.00 |
| 2 | Pavement removed (202E23000) | SY | 2,371 | $22.50 | $28.00 | $26.00 | $30.00 | $27.00 |
| 3 | Concrete median removed (202E30600) | SY | 92 | $32.00 | $55.00 | $45.00 | $150.00 | $78.00 |
| 4 | Curb removed (202E32000) | FT | 1,140 | $8.00 | $7.30 | $7.00 | $15.00 | $13.00 |
| 5 | Guardrail removed (202E38000) | FT | 963 | $2.00 | $3.50 | $2.50 | $2.00 | $3.00 |
| 6 | Removal misc.:underdrains (202E98200) | FT | 135 | $9.50 | $14.00 | $10.00 | $15.00 | $7.00 |
| 7 | Excavation (203E10000) | CY | 653 | $26.50 | $40.00 | $45.00 | $95.00 | $23.50 |
| 8 | Embankment (203E20000) | CY | 422 | $21.00 | $45.00 | $52.00 | $120.00 | $69.00 |
| 9 | Subgrade compaction (204E10000) | SY | 3,540 | $5.00 | $3.50 | $3.00 | $5.00 | $1.00 |
| 10 | Proof rolling (204E45000) | HR | 2 | $350.00 | $650.00 | $500.00 | $150.00 | $285.00 |
| 11 | Linear grading, as per plan (209E60201) | STA | 5 | $275.00 | $2,000.00 | $100.00 | $500.00 | $240.00 |
| 12 | Guardrail, type MGS (606E15050) | FT | 388 | $25.50 | $22.00 | $26.00 | $25.00 | $26.00 |
| 13 | Anchor assembly, type T (606E26500) | EACH | 5 | $1,550.00 | $1,100.00 | $1,600.00 | $1,500.00 | $1,320.00 |
| 14 | MGS bridge terminal assembly, type 1 (606E35002) | EACH | 2 | $3,150.00 | $2,450.00 | $3,200.00 | $3,000.00 | $2,940.00 |
| 15 | MGS bridge terminal assembly, type 2 (606E35102) | EACH | 2 | $635.00 | $650.00 | $650.00 | $600.00 | $780.00 |
| 16 | Impact attenuator, type 2 (bidirectional) (speed 5 (606E60028) | EACH | 2 | $31,500 | $30,000 | $32,000 | $30,000 | $35,401 |
| 17 | Curb, type 4-C (609E24510) | FT | 72 | $30.00 | $52.50 | $35.00 | $100.00 | $50.00 |
| 18 | Curb, type 6 (609E26000) | FT | 455 | $30.00 | $41.50 | $35.00 | $50.00 | $30.00 |
| 19 | Concrete barrier, single slope, type B (622E10060) | FT | 236 | $210.00 | $355.00 | $200.00 | $240.00 | $372.00 |
| 20 | Barrier reflector, type 1 (bidirectional) (626E00102) | EACH | 8 | $12.50 | $13.00 | $15.00 | $15.00 | $15.50 |
| 21 | Barrier reflector, type 1 (one-way) (626E00102) | EACH | 5 | $14.00 | $13.00 | $15.00 | $15.00 | $15.50 |
| 22 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 10 | $300.00 | $310.00 | $220.00 | $150.00 | $725.00 |
| 23 | Tied concrete block mat with type 2 underlayment (601E21060) | SY | 124 | $100.00 | $200.00 | $120.00 | $125.00 | $366.00 |
| 24 | Soil analysis test (659E00100) | EACH | 2 | $150.00 | $100.00 | $400.00 | $200.00 | $360.00 |
| 25 | Topsoil (659E00300) | CY | 123 | $80.00 | $50.00 | $80.00 | $125.00 | $70.00 |
| 26 | Seeding and mulching, class 2 (659E00510) | SY | 1,011 | $3.00 | $5.50 | $3.00 | $5.00 | $2.00 |
| 27 | Repair seeding and mulching (659E14000) | SY | 51 | $0.50 | $12.00 | $6.00 | $2.00 | $1.00 |
| 28 | Inter-seeding (659E15000) | SY | 51 | $0.25 | $12.00 | $5.00 | $0.10 | $1.00 |
| 29 | Commercial fertilizer (659E20000) | TON | 0.14 | $1,000.00 | $700.00 | $1,500.00 | $0.14 | $984.00 |
| 30 | Lime (659E31000) | ACRE | 0.21 | $30.00 | $100.00 | $1,000.00 | $50.00 | $431.00 |
| 31 | Water (659E35000) | MGAL | 6 | $2.00 | $10.00 | $10.00 | $5.00 | $1.00 |
| 32 | Ditch erosion protection mat, type F (670E00760) | SY | 85 | $5.00 | $3.60 | $75.00 | $10.00 | $27.00 |
| 33 | Storm water pollution prevention plan (832E15000) | LS | 1 | $6,000.00 | $2,500.00 | $5,000.00 | $2,000.00 | $15,000 |
| 34 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $20,000 | $14,500 | $18,000 | $18,000 | $26,000 |
| 35 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $10,000 | $10,000 | $20,000 | $12,000 | $12,100 |
| 36 | Erosion control (832E30000) | EACH | 13,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 37 | 6" shallow pipe underdrains (605E11100) | FT | 748 | $15.00 | $35.50 | $26.00 | $30.00 | $16.50 |
| 38 | 6" unclassified pipe underdrains (605E13300) | FT | 50 | $17.00 | $37.50 | $40.00 | $50.00 | $27.00 |
| 39 | 6" conduit, type F (611E01500) | FT | 305 | $20.00 | $66.00 | $30.00 | $40.00 | $25.00 |
| 40 | Catch basin, no. 8A without apron (611E98444) | EACH | 1 | $6,000.00 | $8,100.00 | $8,000.00 | $12,000 | $6,205.00 |
| 41 | Precast reinforced concrete outlet (611E99710) | EACH | 6 | $360.00 | $790.00 | $600.00 | $550.00 | $615.00 |
| 42 | Pavement planing, asphalt concrete (T=1.5") (254E01000) | SY | 9,922 | $3.00 | $3.00 | $2.00 | $3.00 | $5.00 |
| 43 | Asphalt concrete base, PG64-22, (449) (302E56000) | CY | 455 | $255.00 | $245.00 | $300.00 | $245.00 | $336.00 |
| 44 | Aggregate base (304E20000) | CY | 578 | $75.00 | $130.00 | $125.00 | $150.00 | $140.00 |
| 45 | 9" concrete base, class QC 1P (305E13010) | SY | 651 | $105.00 | $100.00 | $205.00 | $135.00 | $91.00 |
| 46 | Non-tracking tack coat (407E20000) | GAL | 908 | $5.00 | $5.00 | $4.00 | $5.00 | $3.00 |
| 47 | Asphalt concrete surface course, type 1, (449), as per plan (441E70101) | CY | 149 | $310.00 | $300.00 | $375.00 | $300.00 | $727.00 |
| 48 | Asphalt concrete intermediate course, type 1, (449), (under guardrail), as per plan (441E70801) | CY | 33 | $780.00 | $750.00 | $600.00 | $750.00 | $925.00 |
| 49 | Asphalt concrete surface course, 12.5 MM, type A (449), as per plan (442E22101) | CY | 436 | $305.00 | $295.00 | $400.00 | $295.00 | $433.00 |
| 50 | Asphalt concrete intermediate course, 12.5 MM, type A (449) (442E22300) | CY | 37 | $260.00 | $250.00 | $450.00 | $250.00 | $553.00 |
| 51 | 10" non-reinforced concrete pavement, class QC 1P (452E14010) | SY | 544 | $150.00 | $180.00 | $210.00 | $165.00 | $113.00 |
| 52 | RPM (621E00100) | EACH | 33 | $60.00 | $60.00 | $175.00 | $155.00 | $72.00 |
| 53 | Raised pavement marker removed (621E54000) | EACH | 33 | $15.00 | $10.50 | $75.00 | $100.00 | $60.04 |
| 54 | Signing, misc.:overpass name installation (630E97700) | EACH | 2 | $1,475.00 | $1,085.00 | $1,650.00 | $1,100.00 | $600.00 |
| 55 | Edge line, 4" (644E00100) | MI | 0.39 | $5,000.00 | $5,000.00 | $6,000.00 | $5,000.00 | $4,536.00 |
| 56 | Edge line, 6" (644E00104) | MI | 1.34 | $5,000.00 | $4,750.00 | $5,500.00 | $4,750.00 | $6,330.00 |
| 57 | Lane line, 6" (644E00204) | MI | 0.73 | $3,000.00 | $2,850.00 | $3,200.00 | $2,850.00 | $3,162.00 |
| 58 | Center line (644E00300) | MI | 0.32 | $8,500.00 | $8,300.00 | $9,000.00 | $8,300.00 | $8,268.00 |
| 59 | Channelizing line, 8" (644E00400) | FT | 280 | $3.00 | $2.90 | $3.50 | $2.90 | $7.50 |
| 60 | Channelizing line, 12" (644E00404) | FT | 369 | $3.40 | $3.25 | $4.00 | $3.25 | $8.00 |
| 61 | Stop line (644E00500) | FT | 65 | $10.00 | $10.00 | $11.00 | $10.00 | $13.00 |
| 62 | Crosswalk line, 12" (644E00620) | FT | 88 | $10.00 | $10.00 | $11.00 | $10.00 | $12.00 |
| 63 | Transverse/diagonal line (644E00700) | FT | 84 | $12.00 | $11.75 | $13.00 | $11.75 | $12.00 |
| 64 | Lane arrow (644E01300) | EACH | 2 | $150.00 | $150.00 | $175.00 | $150.00 | $294.00 |
| 65 | Wrong way arrow (644E01360) | EACH | 2 | $250.00 | $240.00 | $265.00 | $240.00 | $480.00 |
| 66 | Edge line, 4" (646E10000) | MI | 0.12 | $25,500 | $24,300 | $27,000 | $24,300 | $11,500 |
| 67 | Edge line, 6" (646E10010) | MI | 0.09 | $35,000 | $33,500 | $38,000 | $33,500 | $15,550 |
| 68 | Center line (646E10200) | MI | 0.12 | $22,000 | $21,000 | $23,500 | $21,000 | $19,620 |
| 69 | Channelizing line, 8" (646E10300) | FT | 580 | $2.75 | $2.65 | $3.00 | $2.65 | $4.00 |
| 70 | Stop line (646E10400) | FT | 17 | $25.00 | $25.00 | $30.00 | $25.00 | $34.00 |
| 71 | Lane arrow (646E20300) | EACH | 8 | $200.00 | $190.00 | $210.00 | $197.00 | $360.00 |
| 72 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 100 | $78.00 | $115.00 | $125.00 | $80.00 | $108.08 |
| 73 | Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384) | EACH | 8 | $2,800.00 | $3,500.00 | $2,900.00 | $2,700.00 | $2,350.00 |
| 74 | Replacement sign (614E12500) | EACH | 5 | $250.00 | $170.00 | $200.00 | $170.00 | $287.00 |
| 75 | Work zone raised pavement marker, as per plan (614E12801) | EACH | 546 | $6.65 | $12.00 | $14.00 | $12.00 | $12.01 |
| 76 | Barrier reflector, type 1 BI-directional (614E13310) | EACH | 50 | $13.75 | $20.00 | $22.00 | $20.00 | $15.00 |
| 77 | Barrier reflector, type 2 BI-directional (614E13312) | EACH | 12 | $13.35 | $30.00 | $33.00 | $30.00 | $15.00 |
| 78 | Object marker, two way (614E13360) | EACH | 62 | $20.00 | $35.00 | $39.00 | $35.00 | $23.50 |
| 79 | Portable changeable message sign, as per plan (614E18601) | SNMT | 8 | $1,100.00 | $1,050.00 | $1,200.00 | $1,000.00 | $1,374.00 |
| 80 | Work zone lane line, class I, 6", 807 paint (614E20056) | MI | 0.25 | $1,000.00 | $7,250.00 | $8,000.00 | $7,250.00 | $1,141.00 |
| 81 | Work zone center line, class I (614E21000) | MI | 0.43 | $4,400.00 | $4,320.00 | $5,100.00 | $4,320.00 | $5,052.00 |
| 82 | Work zone edge line, class I, 4" (614E22000) | MI | 0.83 | $2,400.00 | $3,650.00 | $4,100.00 | $3,630.00 | $2,765.00 |
| 83 | Work zone edge line, class I, 6" (614E22010) | MI | 0.14 | $3,400.00 | $11,500 | $12,500 | $11,365 | $3,906.00 |
| 84 | Work zone edge line, class I, 6", 807 paint (614E22056) | MI | 0.45 | $5,350.00 | $7,250.00 | $8,000.00 | $7,255.00 | $6,115.00 |
| 85 | Work zone channelizing line, class I, 12" (614E23010) | FT | 1,100 | $1.40 | $0.65 | $0.85 | $0.65 | $1.50 |
| 86 | Work zone stop line, class I (614E26000) | FT | 32 | $7.80 | $21.50 | $24.00 | $22.00 | $9.01 |
| 87 | Pavement for maintaining traffic, class A (615E20000) | SY | 67 | $65.00 | $245.00 | $220.00 | $350.00 | $150.00 |
| 88 | Pavement for maintaining traffic, class A, as per plan (615E20001) | SY | 253 | $85.00 | $130.00 | $180.00 | $225.00 | $130.00 |
| 89 | Water (616E10000) | MGAL | 2 | $5.00 | $40.00 | $100.00 | $50.00 | $103.00 |
| 90 | Portable barrier, unanchored (622E41100) | FT | 289 | $8.00 | $30.50 | $35.00 | $70.00 | $21.00 |
| 91 | Portable barrier, anchored (622E41110) | FT | 1,966 | $10.00 | $40.00 | $35.00 | $80.00 | $45.00 |
| 92 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $520,000 | $305,000 | $380,000 | $600,000 | $217,000 |
| 93 | Approach slab removed (202E22900) | SY | 365 | $66.00 | $49.00 | $55.00 | $150.00 | $50.00 |
| 94 | Wearing course removed (202E23500) | SY | 365 | $12.50 | $8.22 | $25.00 | $15.00 | $9.00 |
| 95 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $20,000 | $25,000 | $30,000 | $150,000 | $53,500 |
| 96 | Unclassified excavation (503E21100) | CY | 201 | $340.00 | $505.00 | $300.00 | $300.00 | $425.00 |
| 97 | Epoxy coated steel reinforcement (509E10000) | LB | 166,098 | $1.55 | $1.93 | $1.80 | $1.60 | $2.00 |
| 98 | Galvanized steel reinforcement (509E26000) | LB | 939 | $2.50 | $4.70 | $3.50 | $2.00 | $4.00 |
| 99 | No. 4 deformed GFRP reinforcement (509E30020) | FT | 7,013 | $1.85 | $2.24 | $2.40 | $1.50 | $2.25 |
| 100 | Dowel holes with nonshrink, nonmetallic grout, as per plan (510E10001) | EACH | 912 | $35.00 | $29.00 | $30.00 | $35.00 | $28.00 |
| 101 | Class QC2 concrete with QC/QA, bridge deck (511E34446) | CY | 429 | $900.00 | $1,050.00 | $1,270.00 | $1,200.00 | $1,541.00 |
| 102 | Class QC2 concrete with QC/QA, bridge deck (parapet) (511E34450) | CY | 72 | $975.00 | $985.00 | $1,800.00 | $1,300.00 | $2,046.00 |
| 103 | Class QC1 concrete with QC/QA, pier (511E43212) | CY | 36 | $2,000.00 | $3,000.00 | $3,500.00 | $3,000.00 | $4,615.00 |
| 104 | Class QC1 concrete with QC/QA, abutment (511E45712) | CY | 118 | $850.00 | $1,050.00 | $1,800.00 | $1,500.00 | $1,840.00 |
| 105 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 1,353 | $25.00 | $32.50 | $40.00 | $65.00 | $39.00 |
| 106 | Concrete repair by epoxy injection (512E10600) | FT | 21 | $200.00 | $185.00 | $100.00 | $150.00 | $222.00 |
| 107 | Type 2 waterproofing (512E33000) | SY | 87 | $25.00 | $35.50 | $48.00 | $100.00 | $30.00 |
| 108 | Structural steel members, level UF, as per plan (513E10201) | LB | 26,700 | $11.00 | $5.00 | $12.50 | $9.00 | $16.00 |
| 109 | Welded stud shear connectors (513E20000) | EACH | 7,914 | $4.45 | $4.25 | $13.00 | $5.00 | $5.00 |
| 110 | Surface preparation of existing structural steel (514E00050) | SF | 18,750 | $11.00 | $11.50 | $15.00 | $11.50 | $12.01 |
| 111 | Field painting of existing structural steel, prime coat (514E00056) | SF | 18,750 | $6.00 | $3.00 | $2.75 | $3.00 | $7.00 |
| 112 | Field painting structural steel, intermediate coat (514E00060) | SF | 19,300 | $4.00 | $3.00 | $2.25 | $3.00 | $4.50 |
| 113 | Field painting structural steel, finish coat (514E00066) | SF | 19,300 | $3.50 | $3.00 | $2.25 | $3.00 | $4.00 |
| 114 | Grinding fins, tears, slivers on existing structural steel (514E00504) | MNHR | 31 | $150.00 | $100.00 | $225.00 | $100.00 | $180.00 |
| 115 | Final inspection repair (514E10000) | EACH | 11 | $200.00 | $400.00 | $325.00 | $400.00 | $240.00 |
| 116 | Armorless preformed joint seal (516E10010) | FT | 186 | $50.00 | $60.00 | $72.00 | $50.00 | $129.00 |
| 117 | Structural expansion joint including elastomeric strip seal (516E11210) | FT | 187 | $775.00 | $840.00 | $800.00 | $950.00 | $1,054.00 |
| 118 | 2" preformed expansion joint filler (516E13900) | SF | 112 | $9.00 | $12.00 | $20.00 | $25.00 | $5.00 |
| 119 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44101) | EACH | 24 | $1,100.00 | $2,000.00 | $1,700.00 | $1,600.00 | $1,524.00 |
| 120 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44201) | EACH | 16 | $1,580.00 | $2,100.00 | $1,900.00 | $1,400.00 | $1,730.00 |
| 121 | Jacking and temporary support of superstructure, as per plan (516E47001) | LS | 1 | $130,000 | $75,000 | $135,000 | $110,000 | $198,000 |
| 122 | Porous backfill with geotextile fabric (518E21200) | CY | 225 | $125.00 | $130.00 | $120.00 | $125.00 | $111.00 |
| 123 | 6" perforated corrugated plastic pipe (518E40000) | FT | 240 | $24.00 | $20.00 | $20.00 | $25.00 | $12.00 |
| 124 | 6" non-perforated corrugated plastic pipe, including specials (518E40010) | FT | 80 | $24.00 | $22.00 | $30.00 | $30.00 | $30.00 |
| 125 | Special - composite fiber wrap system (519E00100) | SF | 3,100 | $30.00 | $44.00 | $30.00 | $30.00 | $53.00 |
| 126 | Patching concrete structure, as per plan (519E11101) | SF | 106 | $145.00 | $165.00 | $150.00 | $175.00 | $128.00 |
| 127 | Reinforced concrete approach slabs with QC/QA (T=1 (526E25010) | SY | 361 | $420.00 | $450.00 | $445.00 | $600.00 | $405.00 |
| 128 | Type C installation (526E90030) | FT | 180 | $150.00 | $265.00 | $215.00 | $300.00 | $175.00 |
| 129 | Special - form liner (530E13000) | SF | 944 | $12.00 | $18.00 | $25.00 | $40.00 | $10.00 |
| 130 | Vandal protection fence, 6' straight, coated fabric (607E39900) | FT | 450 | $110.00 | $135.00 | $113.00 | $125.00 | $140.00 |
| 131 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $46,000 | $38,000 | $53,000 | $35,000 | $63,867 |
| 132 | Maintaining traffic (614E11000) | LS | 1 | $120,000 | $195,000 | $95,000 | $100,000 | $103,500 |
| 133 | Field office, type B, as per plan (619E16011) | MNTH | 12 | $2,500.00 | $3,200.00 | $2,200.00 | $2,500.00 | $2,400.00 |
| 134 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $50,000 | $63,500 | $20,000 | $50,000 | $48,000 |
| 135 | Mobilization (624E10000) | LS | 1 | $235,000 | $249,038 | $115,000 | $200,000 | $398,000 |
| 200 | CPM progress schedule short duration projects (108E30000) | LS | 1 | $5,000.00 | $500.00 | $10,000 | $25,000 | $6,000.00 |
| 201 | Special - asbestos abatement(aluminum pads) (690E70100) | SF | 40 | $75.00 | $80.00 | $250.00 | $100.00 | $1,000.00 |
| 202 | Roads for maintaining traffic (615E10000) | LS | 1 | $10,000 | $25,000 | $20,000 | $10,000 | $7,500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of August 14, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.