ODOT contract 250527 bid tabulation
JEF-SR 213-18.09 (SLIDE REPAIR). Let by Ohio DOT on November 13, 2025, JEF. 3 bids received; low bid $917,531 by Buds Inc, +5.5% against the engineer's estimate of $870,000.
- Owner
- Ohio DOT
- Letting
- 13 NOV 2025
- Pay items
- 64
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Buds Inc | $917,531 | Low | +5.0% |
| 2 | Alan Stone Co Inc | $1,146,188 | +25% | +32% |
| 3 | Craig Edward Susany Inc | $1,216,146 | +33% | +40% |
Engineer's estimate: $870,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Buds Inc | 2. Alan Stone Co Inc | 3. Craig Edward Susany Inc |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $100,000 | $120,000 | $119,000 |
| 2 | Pavement removed (202E23000) | SY | 143 | $35.00 | $45.00 | $50.00 |
| 3 | Concrete barrier removed, as per plan (202E30701) | FT | 280 | $18.00 | $30.00 | $25.00 |
| 4 | Pipe removed, 24" and under (202E35100) | FT | 26 | $25.00 | $8.00 | $50.00 |
| 5 | Guardrail removed (202E38000) | FT | 140 | $5.00 | $3.00 | $5.00 |
| 6 | Excavation (203E10000) | CY | 49 | $65.00 | $50.00 | $125.00 |
| 7 | Embankment (203E20000) | CY | 63 | $65.00 | $45.00 | $125.00 |
| 8 | Subgrade compaction (204E10000) | SY | 329 | $5.00 | $6.50 | $3.00 |
| 9 | Pre-blast condition survey (208E10000) | LS | 1 | $5,000.00 | $14,000 | $10,000 |
| 10 | Guardrail, type MGS (606E15050) | FT | 137.50 | $35.00 | $40.00 | $45.00 |
| 11 | Anchor assembly, MGS type E(MASH 2016) (606E26150) | EACH | 2 | $2,900.00 | $3,500.00 | $2,500.00 |
| 12 | MGS bridge terminal assembly, type 1 (606E35002) | EACH | 2 | $2,700.00 | $3,600.00 | $2,200.00 |
| 13 | Concrete barrier, single slope, type D, as per plan (622E10161) | FT | 180 | $400.00 | $470.00 | $333.00 |
| 14 | Barrier transition, as per plan (622E10201) | EACH | 2 | $5,000.00 | $9,600.00 | $9,000.00 |
| 15 | Concrete barrier end section, type D, as per plan (622E25001) | EACH | 2 | $5,000.00 | $15,000 | $6,000.00 |
| 16 | Scaling (862E00500) | HR | 60 | $600.00 | $830.00 | $1,100.00 |
| 17 | Slope drape, as per plan (862E00601) | SY | 1,594 | $180.00 | $205.00 | $235.00 |
| 18 | Excavation (862E00610) | CY | 444 | $40.00 | $75.00 | $125.00 |
| 19 | Trim blasting (862E00700) | SF | 500 | $120.00 | $180.00 | $200.00 |
| 20 | Soil analysis test (659E00100) | EACH | 2 | $300.00 | $190.00 | $10.00 |
| 21 | Topsoil (659E00300) | CY | 29 | $20.00 | $190.00 | $125.00 |
| 22 | Seeding and mulching (659E10000) | SY | 260 | $25.00 | $6.00 | $10.00 |
| 23 | Repair seeding and mulching (659E14000) | SY | 13 | $0.10 | $3.00 | $10.00 |
| 24 | Commercial fertilizer (659E20000) | TON | 0.04 | $1,300.00 | $710.00 | $1,000.00 |
| 25 | Lime (659E31000) | ACRE | 0.05 | $150.00 | $1,000.00 | $600.00 |
| 26 | Water (659E35000) | MGAL | 5 | $1.00 | $130.00 | $1.00 |
| 27 | Erosion control mat, type G (671E15060) | SY | 434 | $5.00 | $60.00 | $100.00 |
| 28 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 | $1.00 |
| 29 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 22 | $630.00 | $570.00 | $600.00 |
| 30 | Aggregate base (304E20000) | CY | 61 | $200.00 | $180.00 | $150.00 |
| 31 | Tack coat (407E10000) | GAL | 18 | $4.00 | $5.00 | $10.00 |
| 32 | Prime coat, as per plan (408E10001) | GAL | 44 | $30.00 | $5.00 | $72.00 |
| 33 | Asphalt concrete surface course, type 1, (449), PG70-22M (441E70100) | CY | 4 | $1,000.00 | $1,800.00 | $2,100.00 |
| 34 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 5 | $800.00 | $1,500.00 | $1,200.00 |
| 35 | Curb, type 4-C (609E24510) | FT | 38 | $126.00 | $70.00 | $100.00 |
| 36 | RPM (621E00100) | EACH | 8 | $400.00 | $510.00 | $400.00 |
| 37 | Raised pavement marker removed (621E54000) | EACH | 8 | $10.00 | $15.00 | $25.00 |
| 38 | Barrier reflector, type 1 (bidirectional) (626E00102) | EACH | 5 | $10.00 | $15.00 | $10.00 |
| 39 | Barrier reflector, type 2 (bidirectional) (626E00110) | EACH | 6 | $13.00 | $20.00 | $12.00 |
| 40 | Ground mounted support, no. 2 post (630E02100) | FT | 69 | $25.00 | $25.00 | $14.00 |
| 41 | Sign post reflector (630E08600) | EACH | 11 | $55.00 | $55.00 | $30.00 |
| 42 | Removal of ground mounted sign and reerection (630E85100) | EACH | 11 | $160.00 | $85.00 | $50.00 |
| 43 | Removal of ground mounted post support and disposal (630E86002) | EACH | 6 | $30.00 | $20.00 | $15.00 |
| 44 | Edge line, 6" (646E10010) | MI | 0.10 | $20.00 | $31,000 | $45,000 |
| 45 | Center line (646E10200) | MI | 0.05 | $15,000 | $49,000 | $60,000 |
| 46 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 40 | $85.00 | $110.00 | $125.00 |
| 47 | Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384) | EACH | 2 | $2,500.00 | $3,800.00 | $3,000.00 |
| 48 | Work zone lighting system (614E12740) | EACH | 2 | $15,000 | $2,500.00 | $20,000 |
| 49 | Asphalt concrete for maintaining traffic (614E13000) | CY | 20 | $180.00 | $480.00 | $1,000.00 |
| 50 | Barrier reflector, type 1 (bidirectional) (614E13310) | EACH | 8 | $15.00 | $60.00 | $40.00 |
| 51 | Barrier reflector, type 2 (bidirectional) (614E13312) | EACH | 4 | $15.00 | $65.00 | $60.00 |
| 52 | Object marker, two way (614E13360) | EACH | 12 | $20.00 | $50.00 | $40.00 |
| 53 | Work zone center line, class I, 642 paint (614E21100) | MI | 0.18 | $6,000.00 | $4,700.00 | $4,500.00 |
| 54 | Work zone center line, class I, 740.06, type I (614E21200) | MI | 0.18 | $15,000 | $18,000 | $16,000 |
| 55 | Work zone edge line, class I, 6", 642 paint (614E22110) | MI | 0.22 | $5,000.00 | $3,800.00 | $4,000.00 |
| 56 | Work zone edge line, class I, 6", 740.06, type I (614E22210) | MI | 0.22 | $9,000.00 | $13,000 | $11,000 |
| 57 | Work zone stop line, class I, 740.06, type I (614E26400) | FT | 22 | $20.00 | $15.00 | $15.00 |
| 58 | Water (616E10000) | MGAL | 25 | $0.50 | $0.10 | $1.00 |
| 59 | Portable barrier, unanchored (622E41100) | FT | 340 | $30.00 | $40.00 | $45.00 |
| 60 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $20,000 | $13,000 | $40,000 |
| 61 | Maintaining traffic (614E11000) | LS | 1 | $25,000 | $105,000 | $40,000 |
| 62 | Field office, type B (619E16010) | MNTH | 4 | $250.00 | $1,500.00 | $3,000.00 |
| 63 | Construction layout stakes and surveying (623E10000) | LS | 1 | $28,000 | $15,000 | $20,000 |
| 64 | Mobilization (624E10000) | LS | 1 | $90,000 | $57,500 | $40,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of November 13, 2025. Compiled by Mirage Metrics.