ODOT contract 250571 bid tabulation

ROS-CR 550-17.12 (Safety) (INTERSECTION). Let by Ohio DOT on December 4, 2025, ROS. 7 bids received; low bid $496,847 by Complete General Construction Company, -4.6% against the engineer's estimate of $521,000.

Owner
Ohio DOT
Letting
04 DEC 2025
Pay items
76
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Complete General Construction Company$496,847Low-5.0%
2Shelly & Sands Inc$506,637+2.0%-3.0%
3Shelly Company$585,416+18%+12%
4Fillmore Construction$587,537+18%+13%
5Axis Civil Construction LLC$594,208+20%+14%
6D G M Inc$599,873+21%+15%
7Alan Stone Co Inc$692,268+39%+33%
ODOT contract 250571: bids by rank

Engineer's estimate: $521,000.

Bid tabulation

LinePay itemUnitQuantity1. Complete General Construction Company2. Shelly & Sands Inc3. Shelly Company4. Fillmore Construction5. Axis Civil Construction LLC6. D G M Inc
1Clearing and grubbing (201E11000)LS1$4,000.00$15,000$18,500$10,000$1,000.00$11,000
2Pavement removed (202E23000)SY495$28.00$21.00$26.50$10.00$20.00$12.00
3Monument assembly removed (202E60010)EACH2$445.00$209.00$550.00$500.00$275.00$200.00
4Fence removed (202E75000)FT280$4.40$8.00$8.50$10.00$5.00$5.00
5Removal misc.:rock (202E98100)EACH2$350.00$200.00$395.00$1,000.00$90.00$50.00
6Excavation (203E10000)CY496$60.00$42.00$61.25$30.00$45.00$35.00
7Embankment (203E20000)CY149$24.00$25.00$47.00$50.00$45.00$35.00
8Subgrade compaction (204E10000)SY1,451$5.00$9.00$2.25$5.00$3.00$4.00
9Excavation of subgrade (204E13000)CY409$12.00$53.00$43.50$30.00$45.00$35.00
10Granular material, type B (204E30010)CY409$65.00$75.00$63.75$100.00$95.00$100.00
11Proof rolling (204E45000)HR2$225.00$277.00$260.00$200.00$200.00$1,500.00
12Geotextile fabric (204E50000)SY701$5.00$0.75$1.95$5.00$2.00$2.50
13Fence, type CLT (607E23000)FT274$37.00$42.00$37.00$50.00$37.00$46.00
14Detectable warning (608E53020)SF68$45.00$58.00$50.00$50.00$85.00$35.00
15Monument assembly, type C (623E38500)EACH4$980.00$2,200.00$1,525.00$2,500.00$3,000.00$1,000.00
16Right-of-way monument, type B (623E40520)EACH2$1,000.00$800.00$455.00$1,500.00$600.00$400.00
17Tied concrete block mat with type 1 underlayment (601E21050)SY4$172.00$150.00$165.00$500.00$265.00$100.00
18Topsoil (659E00300)CY136$75.00$39.00$200.00$50.00$48.00$20.00
19Seeding and mulching (659E10000)SY1,226$2.80$2.80$3.60$2.00$2.80$3.50
20Repair seeding and mulching (659E14000)SY61.30$2.80$2.80$5.00$2.20$2.80$0.05
21Commercial fertilizer (659E20000)TON0.17$1,250.00$1,250.00$900.00$1,400.00$1,250.00$1,500.00
22Lime (659E31000)ACRE0.25$150.00$150.00$2.52$450.00$150.00$300.00
23Water (659E35000)MGAL7$1.00$1.00$2.50$100.00$1.00$1.00
24Erosion control (832E30000)EACH8,000$1.00$1.00$1.00$1.00$1.00$1.00
254" unclassified pipe underdrains (605E05200)FT200$25.00$21.00$26.00$25.00$16.50$15.00
264" conduit, type F (611E00406)FT100$52.00$33.00$27.00$50.00$16.50$15.00
27Precast reinforced concrete outlet (611E99710)EACH2$1,500.00$556.00$575.00$500.00$450.00$150.00
28Asphalt concrete base, PG64-22, (449) (301E56000)CY342$195.00$195.00$219.00$200.00$270.00$210.00
29Aggregate base (304E20000)CY263$125.00$130.00$80.75$100.00$135.00$120.00
30Tack coat (407E10000)GAL237$4.00$4.00$2.50$5.00$3.00$4.00
31Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000)CY121$325.00$325.00$369.00$250.00$295.00$335.00
32Curb, type 6 (609E26000)FT32$112.00$115.00$153.00$100.00$87.00$60.00
33Valve box adjusted to grade (638E10800)EACH2$460.00$875.00$405.00$500.00$500.00$300.00
34Valve box adjusted to grade, as per plan (638E10801)EACH1$460.00$1,100.00$405.00$1,000.00$500.00$300.00
35RPM (621E00100)EACH53$80.00$80.00$48.00$80.00$140.00$84.00
36Raised pavement marker removed (621E54000)EACH22$54.00$26.00$50.00$20.00$35.00$1.00
37Ground mounted support, no. 3 post (630E03100)FT197.50$18.35$19.00$20.00$20.00$20.00$21.00
38Sign post reflector (630E08600)EACH6$75.04$75.00$45.00$50.00$45.00$60.00
39Sign hanger assembly, span wire (630E79000)EACH1$347.12$348.00$525.00$700.00$525.00$725.00
40Sign, flat sheet (630E80100)SF27.50$22.12$23.00$22.00$30.00$22.00$30.00
41Removal of ground mounted sign and reerection (630E85100)EACH8$82.50$82.50$65.00$150.00$65.00$160.00
42Edge line, 6" (644E00104)MI0.28$5,800.00$5,800.00$5,800.00$7,280.00$7,280.00$7,500.00
43Center line (644E00300)MI0.34$7,000.00$7,000.00$7,000.00$10,450$10,450$11,000
44Channelizing line, 12" (644E00404)FT795$2.20$2.20$2.20$3.00$3.00$3.00
45Stop line (644E00500)FT73$9.00$9.00$9.00$8.50$8.50$9.00
46Crosswalk line, 12" (644E00620)FT193$8.00$8.00$8.00$4.20$4.20$5.00
47Transverse/diagonal line (644E00700)FT187$7.00$7.00$7.00$8.50$8.50$9.00
48Lane arrow (644E01300)EACH15$120.00$120.00$120.00$95.00$95.00$100.00
49Removal of pavement marking (644E30000)FT3,760$0.55$0.55$0.55$1.00$0.90$1.00
50Removal of pavement marking (644E30020)EACH2$50.00$50.00$50.00$145.00$145.00$200.00
51Pull box removed (625E31510)EACH4$250.00$250.00$250.00$525.00$525.00$550.00
52Vehicular signal head, misc.:backplate (632E04000)EACH8$675.00$675.00$675.00$850.00$850.00$875.00
53Vehicular signal head, (LED), 5-section, 12" lens, 1-way, polycarbonate (632E05086)EACH2$1,750.00$1,750.00$1,750.00$2,800.00$2,800.00$2,900.00
54Special - removal and replacement of signal hanger assembly and wire entrance cap (632E07600)EACH8$600.00$600.00$600.00$475.00$475.00$500.00
55Covering of vehicular signal head (632E25000)EACH2$45.00$45.00$45.00$50.00$50.00$55.00
56Tether wire, with accessories (632E30600)FT390$32.00$29.00$29.00$48.00$48.00$50.00
57Signal cable, 7 conductor, no. 14 AWG (632E40700)FT25$3.50$3.50$3.50$5.00$5.00$5.00
58Signal cable, 9 conductor, no. 14 AWG (632E40900)FT175$4.50$4.50$4.50$6.00$6.00$7.00
59Removal of miscellaneous traffic signal item (vehi (632E90020)EACH1$300.00$300.00$300.00$250.00$250.00$275.00
60Reuse of vehicular signal head (632E90200)EACH8$400.00$400.00$400.00$750.00$750.00$800.00
61Advance radar detection, as per plan (809E69001)EACH1$8,500.00$8,500.00$8,500.00$24,000$24,000$25,000
62Stop line radar detection, as per plan (809E69101)EACH1$8,500.00$8,500.00$8,500.00$43,000$43,000$45,000
63Law enforcement officer with patrol car for assistance (614E11110)HR40$85.00$105.00$80.00$150.00$75.00$70.00
64Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380)EACH4$2,720.00$2,150.00$1,929.64$2,000.00$2,800.00$2,250.00
65Barrier reflector, type 1 bidirectional (614E13310)EACH28$50.00$10.00$16.50$50.00$25.00$50.00
66Work zone center line, class I, 642 paint (614E21100)MI0.22$17,500$17,500$5,000.00$17,500$17,500$18,000
67Work zone edge line, class I, 4", 642 paint (614E22100)MI0.37$10,250$10,250$5,000.00$10,250$10,250$11,000
68Work zone channelizing line, class I, 8", 642 paint (614E23200)FT100$10.00$10.00$2.00$10.00$10.00$10.00
69Work zone stop line, class I, 642 paint (614E26200)FT60$14.00$14.00$6.00$14.00$14.00$15.00
70Work zone arrow, class I, 642 paint (614E30200)EACH2$500.00$500.00$70.00$500.00$500.00$550.00
71Water (616E10000)MGAL2$1,800.00$250.00$1.00$100.00$1.00$1.00
72Portable barrier, unanchored (622E41100)FT700$35.00$39.00$38.27$40.00$36.00$24.00
73Premium for contract performance bond and for payment bond (103E05000)LS1$3,000.00$3,000.00$5,000.00$15,000$3,500.00$30,000
74Maintaining traffic (614E11000)LS1$38,000$19,500$83,250$15,000$25,000$60,000
75Construction layout stakes and surveying (623E10000)LS1$7,000.00$17,000$10,000$15,000$10,000$8,000.00
76Mobilization (624E10000)LS1$25,000$25,000$35,000$48,500$35,000$20,000
ODOT contract 250571: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of December 4, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way