ODOT contract 254014 bid tabulation
D05-CUL FY2025 (A) (CULVERT REPLACEMENT). Let by Ohio DOT on April 24, 2025, District 5. 2 bids received; low bid $934,416 by Axis Civil Construction LLC, -7.9% against the engineer's estimate of $1,015,000.
- Owner
- Ohio DOT
- Letting
- 24 APR 2025
- Pay items
- 75
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Axis Civil Construction LLC | $934,416 | Low | -8.0% |
| 2 | Crawford Construction Company Inc | $1,073,363 | +15% | +6.0% |
Engineer's estimate: $1,015,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Axis Civil Construction LLC | 2. Crawford Construction Company Inc |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $15,000 | $12,000 |
| 2 | Headwall removed (202E20010) | EACH | 6 | $750.00 | $800.00 |
| 3 | Pavement removed (202E23000) | SY | 479 | $21.00 | $24.00 |
| 4 | Pipe removed, 24" and under (202E35100) | FT | 97 | $28.00 | $12.00 |
| 5 | Pipe removed, over 24" diameter (202E35200) | FT | 232 | $90.00 | $79.00 |
| 6 | Guardrail removed (202E38000) | FT | 387.50 | $6.50 | $19.00 |
| 7 | Anchor assembly removed, type A (202E42000) | EACH | 7 | $480.00 | $422.00 |
| 8 | Anchor assembly removed, type T (202E42040) | EACH | 1 | $480.00 | $480.00 |
| 9 | Mailbox removed (202E53100) | EACH | 2 | $150.00 | $200.00 |
| 10 | Catch basin removed (202E58100) | EACH | 1 | $750.00 | $400.00 |
| 11 | Fence removed (202E75000) | FT | 100 | $6.00 | $8.00 |
| 12 | Excavation (203E10000) | CY | 207 | $35.00 | $59.00 |
| 13 | Embankment (203E20000) | CY | 601 | $35.00 | $35.00 |
| 14 | Subgrade compaction (204E10000) | SY | 647 | $4.00 | $4.00 |
| 15 | Guardrail, type MGS (606E15050) | FT | 612.50 | $22.00 | $26.00 |
| 16 | Guardrail, type MGS with long posts (606E15100) | FT | 187.50 | $25.00 | $27.00 |
| 17 | Guardrail, type MGS, long-span (606E17360) | FT | 87.50 | $28.00 | $27.00 |
| 18 | Anchor assembly, MGS type A (606E25550) | EACH | 1 | $1,750.00 | $1,900.00 |
| 19 | Anchor assembly, MGS type E (MASH 2016) (606E26150) | EACH | 4 | $2,500.00 | $3,000.00 |
| 20 | Anchor assembly, MGS type T (606E26550) | EACH | 4 | $1,200.00 | $1,600.00 |
| 21 | Fence, type 47 (607E15000) | FT | 100 | $25.00 | $48.00 |
| 22 | Fence, snow (607E30000) | FT | 430 | $4.50 | $9.00 |
| 23 | Right-of-way monument, type B (623E40520) | EACH | 9 | $350.00 | $450.00 |
| 24 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $1,600.00 | $4,000.00 |
| 25 | Post construction survey monument verification and report (623E51000) | LS | 1 | $1,600.00 | $4,000.00 |
| 26 | Special - mailbox support system, single (690E50100) | EACH | 2 | $350.00 | $300.00 |
| 27 | Riprap, type D (601E11000) | SY | 21 | $250.00 | $380.00 |
| 28 | Rock channel protection, type A with filter (601E32000) | CY | 38 | $128.00 | $195.00 |
| 29 | Rock channel protection, type B with filter (601E32100) | CY | 56 | $138.00 | $200.00 |
| 30 | Seeding and mulching, class 2 (659E00510) | SY | 3,242 | $1.75 | $4.55 |
| 31 | Commercial fertilizer (659E20000) | TON | 0.44 | $1,500.00 | $1,160.00 |
| 32 | Lime (659E31000) | ACRE | 0.67 | $200.00 | $270.00 |
| 33 | Water (659E35000) | MGAL | 18 | $1.00 | $1.30 |
| 34 | Erosion control (832E30000) | EACH | 20,000 | $1.00 | $1.00 |
| 35 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $27,000 | $35,000 |
| 36 | Concrete masonry (602E20000) | CY | 20.60 | $2,200.00 | $2,000.00 |
| 37 | 12" conduit, type D (611E04900) | FT | 46 | $55.00 | $87.00 |
| 38 | 15" conduit, type D (611E06400) | FT | 52 | $65.00 | $90.00 |
| 39 | 72" conduit, type A, 706.02 or (611E26000) | FT | 92 | $850.00 | $1,000.00 |
| 40 | 68" X 106" conduit, type A, 706.04 (611E53600) | FT | 78 | $1,450.00 | $1,500.00 |
| 41 | 77" X 121" conduit, type A, 706.04 (611E53800) | FT | 66 | $1,960.00 | $2,000.00 |
| 42 | Catch basin, no. 2-2B (611E98470) | EACH | 1 | $3,100.00 | $2,700.00 |
| 43 | Conduit renewal using spray applied structural liner, round conduit (833E10000) | FT | 230 | $408.00 | $450.00 |
| 44 | Full depth pavement sawing (252E01500) | FT | 198 | $6.00 | $11.00 |
| 45 | Pavement planing, asphalt concrete (1.25") (254E01000) | SY | 60 | $65.00 | $37.00 |
| 46 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 93 | $400.00 | $700.00 |
| 47 | Aggregate base (304E20000) | CY | 128 | $145.00 | $200.00 |
| 48 | Non-tracking tack coat (407E20000) | GAL | 44 | $6.00 | $11.60 |
| 49 | Prime coat, as per plan (408E10001) | GAL | 207 | $12.00 | $12.00 |
| 50 | Asphalt concrete surface course, type 1, (449), PG70-22M (441E70100) | CY | 22 | $680.00 | $685.00 |
| 51 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 24 | $500.00 | $675.00 |
| 52 | Asphalt concrete surface course, type 1, (449), (driveways) (441E70500) | CY | 3 | $680.00 | $580.00 |
| 53 | Compacted aggregate (617E10100) | CY | 115 | $145.00 | $137.00 |
| 54 | RPM (621E00100) | EACH | 3 | $1,500.00 | $2,034.00 |
| 55 | Raised pavement marker removed (621E54000) | EACH | 3 | $65.00 | $60.00 |
| 56 | Barrier reflector, type 2 (bidirectional) (626E00110) | EACH | 23 | $12.00 | $15.00 |
| 57 | Ground mounted support, no. 3 post, as per plan (630E03101) | FT | 28 | $20.00 | $53.00 |
| 58 | Sign post reflector (630E08600) | EACH | 2 | $45.00 | $62.00 |
| 59 | Sign, flat sheet (630E80100) | SF | 19.25 | $25.00 | $56.00 |
| 60 | Removal of ground mounted sign and disposal (630E84900) | EACH | 4 | $15.00 | $60.00 |
| 61 | Removal of ground mounted post support and disposal (630E86002) | EACH | 3 | $15.00 | $60.00 |
| 62 | Edge line, 6", type 1 (642E00104) | MI | 0.03 | $52,250 | $116,000 |
| 63 | Center line, type 1 (642E00300) | MI | 0.02 | $75,500 | $116,000 |
| 64 | Stop line, type 1 (642E00500) | FT | 19 | $12.00 | $4.70 |
| 65 | Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384) | EACH | 2 | $2,650.00 | $3,300.00 |
| 66 | Detour signing (614E12420) | LS | 1 | $10,000 | $11,600 |
| 67 | Barrier reflector, type 1 (bidirectional) (614E13310) | EACH | 6 | $25.00 | $14.00 |
| 68 | Object marker, two way (614E13360) | EACH | 5 | $39.00 | $14.00 |
| 69 | Portable changeable message sign, as per plan (614E18601) | SNMT | 8 | $900.00 | $1,044.00 |
| 70 | Water (616E10000) | MGAL | 10 | $1.00 | $2.90 |
| 71 | Portable barrier, unanchored (622E41100) | FT | 240 | $31.00 | $150.00 |
| 72 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $8,500.00 | $12,300 |
| 73 | Maintaining traffic (614E11000) | LS | 1 | $18,000 | $13,920 |
| 74 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $18,000 | $16,800 |
| 75 | Mobilization (624E10000) | LS | 1 | $60,000 | $50,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 24, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.