ODOT contract 258017 bid tabulation
LAW-SR 217-02.53 (SLIDE REPAIR). Let by Ohio DOT on June 26, 2025, LAW. 5 bids received; low bid $444,747 by Allard Excavation LLC, -16% against the engineer's estimate of $528,000.
- Owner
- Ohio DOT
- Letting
- 26 JUN 2025
- Pay items
- 44
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Allard Excavation LLC | $444,747 | Low | -16% |
| 2 | Alan Stone Co Inc | $445,404 | 0.0% | -16% |
| 3 | Ohio-West Virginia Excavating Co | $519,284 | +17% | -2.0% |
| 4 | Craig Edward Susany Inc | $519,590 | +17% | -2.0% |
| 5 | Beaver Excavating Company | $544,986 | +23% | +3.0% |
Engineer's estimate: $528,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Allard Excavation LLC | 2. Alan Stone Co Inc | 3. Ohio-West Virginia Excavating Co | 4. Craig Edward Susany Inc | 5. Beaver Excavating Company |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $2,929.00 | $5,200.00 | $4,200.00 | $100.00 | $29,000 |
| 2 | Pavement removed (202E23000) | SY | 14 | $36.00 | $120.00 | $180.00 | $20.00 | $27.00 |
| 3 | Pavement removed, as per plan (202E23001) | SY | 356 | $23.00 | $35.00 | $22.00 | $20.00 | $26.39 |
| 4 | Pipe removed, 24" and under (202E35100) | FT | 43 | $10.00 | $9.00 | $44.00 | $20.00 | $7.00 |
| 5 | Guardrail removed (202E38000) | FT | 108 | $5.00 | $6.00 | $17.00 | $5.00 | $4.50 |
| 6 | Excavation (203E10000) | CY | 31 | $26.00 | $20.00 | $72.00 | $20.00 | $20.76 |
| 7 | Embankment (203E20000) | CY | 55 | $23.00 | $20.00 | $46.00 | $20.00 | $41.59 |
| 8 | Subgrade compaction (204E10000) | SY | 66 | $4.00 | $20.00 | $16.00 | $3.00 | $16.40 |
| 9 | Guardrail, type MGS (606E15050) | FT | 312.50 | $24.34 | $25.00 | $28.00 | $25.00 | $24.34 |
| 10 | Guardrail, type MGS with long posts (606E15100) | FT | 112.50 | $26.78 | $27.00 | $30.00 | $27.00 | $26.78 |
| 11 | Anchor assembly, MGS type E (606E26150) | EACH | 1 | $2,300.00 | $2,500.00 | $2,600.00 | $2,300.00 | $2,300.00 |
| 12 | Topsoil (659E00300) | CY | 41 | $26.00 | $20.00 | $101.00 | $50.00 | $104.02 |
| 13 | Seeding and mulching (659E10000) | SY | 373 | $3.00 | $4.00 | $10.00 | $8.00 | $9.00 |
| 14 | Commercial fertilizer (659E20000) | TON | 0.05 | $600.00 | $660.00 | $1,435.00 | $600.00 | $1,250.00 |
| 15 | Lime (659E31000) | ACRE | 0.08 | $500.00 | $940.00 | $170.00 | $50.00 | $150.00 |
| 16 | Water (659E35000) | MGAL | 2 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 17 | Erosion control (832E30000) | EACH | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 18 | Concrete masonry (602E20000) | CY | 0.33 | $2,593.00 | $3,300.00 | $5,200.00 | $2,000.00 | $2,000.00 |
| 19 | 18" conduit, type A (611E07200) | FT | 42 | $147.00 | $330.00 | $180.00 | $190.00 | $75.00 |
| 20 | Pavement planing, asphalt concrete (1.5") (254E01000) | SY | 361 | $5.35 | $25.00 | $6.00 | $6.00 | $6.50 |
| 21 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 44 | $400.00 | $330.00 | $450.00 | $490.00 | $479.00 |
| 22 | Aggregate base (304E20000) | CY | 8 | $179.00 | $260.00 | $258.00 | $200.00 | $85.00 |
| 23 | Tack coat (407E10000) | GAL | 101 | $2.50 | $5.00 | $2.00 | $2.50 | $3.00 |
| 24 | Stabilized crushed aggregate (411E10000) | CY | 30 | $97.00 | $160.00 | $125.00 | $200.00 | $95.00 |
| 25 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 46 | $415.00 | $360.00 | $450.00 | $505.00 | $497.00 |
| 26 | Removal of delineator (620E31200) | EACH | 2 | $46.00 | $30.00 | $30.00 | $10.00 | $13.10 |
| 27 | RPM (621E00100) | EACH | 5 | $550.00 | $650.00 | $600.00 | $550.00 | $550.00 |
| 28 | Raised pavement marker removed (621E54000) | EACH | 5 | $10.00 | $45.00 | $55.00 | $20.00 | $13.20 |
| 29 | Barrier reflector, type 3 (BI-directional) (626E00112) | EACH | 5 | $10.00 | $10.00 | $14.00 | $10.00 | $10.00 |
| 30 | Ground mounted support, no. 3 post (630E03100) | FT | 13.10 | $12.00 | $15.00 | $15.00 | $12.00 | $12.00 |
| 31 | Sign, flat sheet (630E80100) | SF | 8.60 | $28.00 | $35.00 | $60.00 | $28.00 | $28.00 |
| 32 | Removal of ground mounted sign and disposal (630E84900) | EACH | 2 | $29.00 | $65.00 | $400.00 | $10.00 | $16.90 |
| 33 | Removal of ground mounted post support and disposal (630E86002) | EACH | 1 | $29.00 | $75.00 | $700.00 | $15.00 | $130.00 |
| 34 | Edge line, 6", type 1 (642E00104) | MI | 0.12 | $8,550.00 | $10,000 | $9,800.00 | $9,000.00 | $8,550.00 |
| 35 | Center line, type 1 (642E00300) | MI | 0.06 | $16,550 | $19,000 | $18,000 | $17,000 | $16,550 |
| 36 | Unclassified excavation (503E21300) | LS | 1 | $1,266.00 | $1,100.00 | $2,000.00 | $1,000.00 | $12,000 |
| 37 | Steel piles, misc.: W12X53 steel beam, furnished, (507E00400) | FT | 1,670 | $49.00 | $50.00 | $49.00 | $59.00 | $45.00 |
| 38 | Concrete, misc.: precast reinforced concrete laggi (511E81300) | EACH | 1 | $2,627.00 | $3,400.00 | $4,400.00 | $4,000.00 | $3,300.00 |
| 39 | Drilled shafts, 36" diameter, above bedrock, as per plan (524E94703) | FT | 817 | $112.00 | $100.00 | $127.00 | $135.00 | $110.00 |
| 40 | Drilled shafts, 36" diameter, into bedrock, as per plan (524E94705) | FT | 645 | $125.00 | $110.00 | $110.00 | $135.00 | $135.00 |
| 41 | Drilled shafts, misc.: plug piles, 36" diameter, U (524E95000) | FT | 594 | $101.00 | $100.00 | $128.00 | $125.00 | $120.00 |
| 42 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $4,000.00 | $4,000.00 | $7,500.00 | $14,000 | $2,220.00 |
| 43 | Construction layout stakes and surveying (623E10000) | LS | 1 | $10,607 | $7,100.00 | $4,000.00 | $7,500.00 | $5,500.00 |
| 44 | Mobilization (624E10000) | LS | 1 | $21,500 | $21,000 | $51,200 | $20,000 | $70,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of June 26, 2025. Compiled by Mirage Metrics.