ODOT contract 258017 bid tabulation

LAW-SR 217-02.53 (SLIDE REPAIR). Let by Ohio DOT on June 26, 2025, LAW. 5 bids received; low bid $444,747 by Allard Excavation LLC, -16% against the engineer's estimate of $528,000.

Owner
Ohio DOT
Letting
26 JUN 2025
Pay items
44
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Allard Excavation LLC$444,747Low-16%
2Alan Stone Co Inc$445,4040.0%-16%
3Ohio-West Virginia Excavating Co$519,284+17%-2.0%
4Craig Edward Susany Inc$519,590+17%-2.0%
5Beaver Excavating Company$544,986+23%+3.0%
ODOT contract 258017: bids by rank

Engineer's estimate: $528,000.

Bid tabulation

LinePay itemUnitQuantity1. Allard Excavation LLC2. Alan Stone Co Inc3. Ohio-West Virginia Excavating Co4. Craig Edward Susany Inc5. Beaver Excavating Company
1Clearing and grubbing (201E11000)LS1$2,929.00$5,200.00$4,200.00$100.00$29,000
2Pavement removed (202E23000)SY14$36.00$120.00$180.00$20.00$27.00
3Pavement removed, as per plan (202E23001)SY356$23.00$35.00$22.00$20.00$26.39
4Pipe removed, 24" and under (202E35100)FT43$10.00$9.00$44.00$20.00$7.00
5Guardrail removed (202E38000)FT108$5.00$6.00$17.00$5.00$4.50
6Excavation (203E10000)CY31$26.00$20.00$72.00$20.00$20.76
7Embankment (203E20000)CY55$23.00$20.00$46.00$20.00$41.59
8Subgrade compaction (204E10000)SY66$4.00$20.00$16.00$3.00$16.40
9Guardrail, type MGS (606E15050)FT312.50$24.34$25.00$28.00$25.00$24.34
10Guardrail, type MGS with long posts (606E15100)FT112.50$26.78$27.00$30.00$27.00$26.78
11Anchor assembly, MGS type E (606E26150)EACH1$2,300.00$2,500.00$2,600.00$2,300.00$2,300.00
12Topsoil (659E00300)CY41$26.00$20.00$101.00$50.00$104.02
13Seeding and mulching (659E10000)SY373$3.00$4.00$10.00$8.00$9.00
14Commercial fertilizer (659E20000)TON0.05$600.00$660.00$1,435.00$600.00$1,250.00
15Lime (659E31000)ACRE0.08$500.00$940.00$170.00$50.00$150.00
16Water (659E35000)MGAL2$1.00$1.00$1.00$1.00$1.00
17Erosion control (832E30000)EACH5,000$1.00$1.00$1.00$1.00$1.00
18Concrete masonry (602E20000)CY0.33$2,593.00$3,300.00$5,200.00$2,000.00$2,000.00
1918" conduit, type A (611E07200)FT42$147.00$330.00$180.00$190.00$75.00
20Pavement planing, asphalt concrete (1.5") (254E01000)SY361$5.35$25.00$6.00$6.00$6.50
21Asphalt concrete base, PG64-22, (449) (301E56000)CY44$400.00$330.00$450.00$490.00$479.00
22Aggregate base (304E20000)CY8$179.00$260.00$258.00$200.00$85.00
23Tack coat (407E10000)GAL101$2.50$5.00$2.00$2.50$3.00
24Stabilized crushed aggregate (411E10000)CY30$97.00$160.00$125.00$200.00$95.00
25Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000)CY46$415.00$360.00$450.00$505.00$497.00
26Removal of delineator (620E31200)EACH2$46.00$30.00$30.00$10.00$13.10
27RPM (621E00100)EACH5$550.00$650.00$600.00$550.00$550.00
28Raised pavement marker removed (621E54000)EACH5$10.00$45.00$55.00$20.00$13.20
29Barrier reflector, type 3 (BI-directional) (626E00112)EACH5$10.00$10.00$14.00$10.00$10.00
30Ground mounted support, no. 3 post (630E03100)FT13.10$12.00$15.00$15.00$12.00$12.00
31Sign, flat sheet (630E80100)SF8.60$28.00$35.00$60.00$28.00$28.00
32Removal of ground mounted sign and disposal (630E84900)EACH2$29.00$65.00$400.00$10.00$16.90
33Removal of ground mounted post support and disposal (630E86002)EACH1$29.00$75.00$700.00$15.00$130.00
34Edge line, 6", type 1 (642E00104)MI0.12$8,550.00$10,000$9,800.00$9,000.00$8,550.00
35Center line, type 1 (642E00300)MI0.06$16,550$19,000$18,000$17,000$16,550
36Unclassified excavation (503E21300)LS1$1,266.00$1,100.00$2,000.00$1,000.00$12,000
37Steel piles, misc.: W12X53 steel beam, furnished, (507E00400)FT1,670$49.00$50.00$49.00$59.00$45.00
38Concrete, misc.: precast reinforced concrete laggi (511E81300)EACH1$2,627.00$3,400.00$4,400.00$4,000.00$3,300.00
39Drilled shafts, 36" diameter, above bedrock, as per plan (524E94703)FT817$112.00$100.00$127.00$135.00$110.00
40Drilled shafts, 36" diameter, into bedrock, as per plan (524E94705)FT645$125.00$110.00$110.00$135.00$135.00
41Drilled shafts, misc.: plug piles, 36" diameter, U (524E95000)FT594$101.00$100.00$128.00$125.00$120.00
42Premium for contract performance bond and for payment bond (103E05000)LS1$4,000.00$4,000.00$7,500.00$14,000$2,220.00
43Construction layout stakes and surveying (623E10000)LS1$10,607$7,100.00$4,000.00$7,500.00$5,500.00
44Mobilization (624E10000)LS1$21,500$21,000$51,200$20,000$70,000
ODOT contract 258017: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of June 26, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy