ODOT contract 260077 bid tabulation

BRO-CR 62-00.42 (BRIDGE REPLACEMENT (1 BRIDGE)). Let by Ohio DOT on February 19, 2026, BRO. 4 bids received; low bid $1,707,854 by Complete General Construction Company, -15% against the engineer's estimate of $2,015,000.

Owner
Ohio DOT
Letting
19 FEB 2026
Pay items
81
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Complete General Construction Company$1,707,854Low-15%
2Double Z Construction Company$1,917,464+12%-5.0%
3Sunesis Construction Co$1,998,834+17%-1.0%
4Prus Construction Company$2,249,492+32%+12%
ODOT contract 260077: bids by rank

Engineer's estimate: $2,015,000.

Bid tabulation

LinePay itemUnitQuantity1. Complete General Construction Company2. Double Z Construction Company3. Sunesis Construction Co4. Prus Construction Company
1Clearing and grubbing (201E11000)LS1$5,000.00$6,500.00$2,804.95$5,100.00
2Pavement removed (202E23000)SY190$50.00$38.00$36.40$39.00
3Guardrail removed (202E38000)FT154$2.00$2.00$25.45$11.40
4Mailbox removed (202E53100)EACH7$35.00$35.00$103.78$125.00
5Excavation (203E10000)CY250$55.00$60.00$25.81$25.50
6Embankment (203E20000)CY121$35.00$27.00$27.46$40.00
7Subgrade compaction (204E10000)SY1,082$9.00$8.00$3.71$2.15
8Guardrail, type MGS (606E15050)FT50$29.20$30.00$48.94$35.25
9Anchor assembly, type T (606E26500)EACH4$1,320.00$1,320.00$1,100.00$1,482.00
10MGS bridge terminal assembly, type 1 (606E35002)EACH2$2,450.00$2,450.00$2,100.00$2,622.00
11MGS bridge terminal assembly, type 1, as per plan (606E35003)EACH2$2,620.00$2,620.00$2,400.00$3,420.00
12Special - mailbox support system, single (690E50100)EACH7$220.00$225.00$125.00$650.00
13Topsoil (659E00300)CY70$25.00$65.00$89.28$100.00
14Seeding and mulching (659E10000)SY623$5.70$10.00$8.35$8.81
15Repair seeding and mulching (659E14000)SY31$5.70$19.75$5.70$22.00
16Commercial fertilizer (659E20000)TON0.08$1,250.00$500.00$1,250.00$570.00
17Lime (659E31000)ACRE0.13$150.00$75.00$150.00$825.00
18Water (659E35000)MGAL3$1.00$1.00$1.00$1.00
19Erosion control (832E30000)EACH5,000$1.00$1.00$1.00$1.00
206" unclassified pipe underdrains for springs (605E13402)FT50$6.00$17.00$15.62$28.00
21Aggregate drains (605E31100)FT137$50.00$22.00$9.00$16.50
22Aggregate drains for springs (605E32200)FT50$5.00$15.00$20.11$16.75
23Precast reinforced concrete outlet (611E99710)EACH2$350.00$375.00$486.62$735.00
24Pavement planing, asphalt concrete (3") (254E01000)SY590$14.25$10.00$14.25$19.00
25Asphalt concrete base, PG64-22, (449) (302E56000)CY22$325.00$550.00$325.00$655.50
26Aggregate base (304E20000)CY121$175.00$125.00$140.89$89.50
27Tack coat (407E10000)GAL103$4.10$5.00$4.10$5.50
28Stabilized crushed aggregate (411E10000)CY86$95.00$165.00$136.88$158.50
29Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000)CY65$345.00$395.00$345.00$584.00
30Asphalt concrete surface course, type 1, (449), (driveways) (441E70500)CY6$345.00$575.00$345.00$875.00
31Ground mounted support, no. 3 post (630E03100)FT13.50$40.00$15.50$15.50$20.00
32Sign, flat sheet (630E80100)SF14$20.00$16.00$16.00$25.00
33Removal of ground mounted sign and disposal (630E84900)EACH3$45.00$20.00$20.00$17.10
34Removal of ground mounted sign and reerection (630E85100)EACH1$15.00$45.00$45.00$114.00
35Removal of ground mounted post support and disposal (630E86002)EACH4$65.00$25.00$25.00$28.50
36Edge line, 4" (644E00100)MI0.20$11,340$11,340$11,340$11,400
37Center line (644E00300)MI0.10$22,680$22,680$22,680$11,400
38Detour signing (614E12420)LS1$5,000.00$6,000.00$3,100.00$3,500.00
39Water (616E10000)MGAL2$75.00$60.00$353.70$285.00
40Structure removed, over 20 foot span, as per plan (202E11003)LS1$80,000$65,000$53,610$230,000
41Wearing course removed (202E23500)SY348$20.00$15.00$8.88$35.00
42Granular material, type B (204E30010)CY41$150.00$95.00$148.14$165.00
43Geotextile fabric (204E50000)SY1,048$4.50$2.50$3.44$2.00
44Cofferdams and excavation bracing (503E11100)LS1$55,000$80,000$8,852.28$65,500
45Unclassified excavation (503E21300)LS1$25,000$75,000$48,827$35,325
46Epoxy coated steel reinforcement (509E10000)LB61,921$1.50$1.75$1.90$1.70
47Dowel holes with nonshrink, nonmetallic grout (510E10000)EACH12$175.00$45.00$52.55$60.00
48Class QC2 concrete with QC/QA, superstructure (511E33418)CY55$875.00$1,000.00$1,779.64$1,592.00
49Semi-integral diaphragm guide (511E33500)EACH2$5,500.00$4,600.00$3,917.20$5,500.00
50Class QC2 concrete with QC/QA, bridge deck (511E34446)CY140$1,200.00$1,765.00$2,151.90$1,600.00
51Class QC1 concrete with QC/QA, pier above footings (511E41012)CY22$2,250.00$2,200.00$3,288.86$2,550.00
52Class QC1 concrete with QC/QA, abutment including footing (511E43512)CY151$925.00$940.00$1,136.88$1,365.00
53Sealing of concrete surfaces (non-epoxy) (512E10050)SY414$12.50$12.50$12.50$18.75
54Type 2 waterproofing (512E33000)SY30$30.00$40.00$30.00$46.00
55Draped strand prestressed concrete bridge I-beam members, level 3, type 3 (515E15010)EACH4$30,000$32,000$37,932$38,500
56Draped strand prestressed concrete bridge I-beam members, level 3, type 3 (515E15010)EACH4$30,000$32,000$37,932$38,500
57Intermediate diaphragms (515E20000)EACH6$4,500.00$2,600.00$5,022.66$3,525.00
58Armorless preformed joint seal (516E10010)FT66$65.00$80.00$35.22$75.50
592" preformed expansion joint filler (516E13900)SF54$10.00$25.00$16.90$12.25
60Nylon reinforced neoprene sheeting (516E25000)SF327$26.50$15.00$16.65$5.00
61Elastomeric bearing with internal laminates and load plate (516E44100)EACH8$1,300.00$1,800.00$1,506.85$2,200.00
62Elastomeric bearing with internal laminates and load plate, as per plan (516E44101)EACH8$1,300.00$1,800.00$2,391.18$2,200.00
63Railing (twin steel tube) (517E70000)FT270$270.00$270.00$268.00$371.50
64Porous backfill with geotextile fabric (518E21200)CY67$125.00$155.00$151.34$130.00
65Special - steel drip strip (518E22300)FT313$15.50$22.00$32.93$15.00
666" perforated corrugated plastic pipe (518E40000)FT129$20.00$15.00$3.88$6.00
676" non-perforated corrugated plastic pipe, including specials, as per plan (518E40011)FT106$25.00$20.00$6.31$19.00
68Drilled shafts, 42" diameter, into bedrock (524E94804)FT130$750.00$840.00$452.13$715.00
69Drilled shafts, 48" diameter, above bedrock (524E94902)FT83$595.00$740.00$528.91$735.00
70Drilled shafts, 48" diameter above bedrock, as per plan (524E94903)FT29$595.00$870.00$417.78$500.00
71Reinforced concrete approach slabs with QC/QA (T=1 (526E25011)SY178$350.00$400.00$437.76$415.00
72Type C installation (526E90030)FT66$400.00$350.00$285.57$325.00
73Rock channel protection, type B with filter (601E32100)CY290$90.00$90.00$231.72$110.00
74Select granular backfill (840E23000)CY353$70.00$120.00$113.33$120.00
75Geogrid, type P1 (863E00100)SY1,782$3.50$6.00$9.30$4.35
76Thermal integrity profiling (tip) test (894E10000)EACH3$9,500.00$3,300.00$2,617.00$7,850.00
77Premium for contract performance bond and for payment bond (103E05000)LS1$11,000$11,500$11,154$8,000.00
78Maintaining traffic (614E11000)LS1$5,000.00$6,000.00$4,097.52$35,500
79Field office, type B (619E16010)MNTH4$1,500.00$2,800.00$2,322.50$1,800.00
80Construction layout stakes and surveying (623E10000)LS1$15,000$20,000$48,700$10,000
81Mobilization (624E10000)LS1$84,000$65,000$71,656$100,000
ODOT contract 260077: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of February 19, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy