ODOT contract 260185 bid tabulation
WAS-SR 26-03.75 (INTERSECTION). Let by Ohio DOT on April 9, 2026, WAS. 3 bids received; low bid $934,443 by Shelly & Sands Inc, +8.7% against the engineer's estimate of $860,000.
- Owner
- Ohio DOT
- Letting
- 09 APR 2026
- Pay items
- 74
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly & Sands Inc | $934,443 | Low | +9.0% |
| 2 | Ohio-West Virginia Excavating Co | $977,288 | +5.0% | +14% |
| 3 | Alan Stone Co Inc | $1,057,552 | +13% | +23% |
Engineer's estimate: $860,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly & Sands Inc | 2. Ohio-West Virginia Excavating Co | 3. Alan Stone Co Inc |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $10,000 | $6,000.00 | $10,000 |
| 2 | Pavement removed (202E23000) | SY | 2,197 | $12.00 | $18.11 | $15.00 |
| 3 | Fence removed (202E75000) | FT | 732 | $5.00 | $4.26 | $4.00 |
| 4 | Fence removed for reuse (202E75200) | FT | 216 | $5.00 | $4.87 | $15.00 |
| 5 | Gate removed for reuse (202E75254) | EACH | 1 | $750.00 | $316.24 | $1,500.00 |
| 6 | Excavation (203E10000) | CY | 874 | $25.00 | $40.27 | $35.00 |
| 7 | Embankment (203E20000) | CY | 2,358 | $35.00 | $41.50 | $25.00 |
| 8 | Subgrade compaction (204E10000) | SY | 2,677 | $3.25 | $0.82 | $4.50 |
| 9 | Guardrail, type MGS (606E15050) | FT | 412.50 | $24.00 | $27.25 | $25.00 |
| 10 | Anchor assembly, MGS type E (NCHRP 350/MASH 2016) (606E26150) | EACH | 2 | $2,700.00 | $3,430.01 | $2,700.00 |
| 11 | Fence, type 47 (607E15000) | FT | 448 | $25.00 | $29.68 | $30.00 |
| 12 | Fence rebuilt, type 47 (607E16000) | FT | 261 | $20.00 | $26.52 | $20.00 |
| 13 | Fence, misc.:temporary fence (607E98000) | FT | 215 | $20.00 | $27.00 | $20.00 |
| 14 | Curb, type 7 (609E28000) | FT | 122 | $86.00 | $103.20 | $65.00 |
| 15 | Topsoil (659E00300) | CY | 331 | $25.00 | $45.93 | $10.00 |
| 16 | Seeding and mulching (659E10000) | SY | 2,493 | $1.50 | $1.64 | $2.50 |
| 17 | Repair seeding and mulching (659E14000) | SY | 126 | $1.50 | $1.64 | $5.00 |
| 18 | Inter-seeding (659E15000) | SY | 126 | $1.50 | $1.64 | $3.00 |
| 19 | Commercial fertilizer (659E20000) | TON | 0.36 | $1,250.00 | $1,520.42 | $620.00 |
| 20 | Lime (659E31000) | ACRE | 0.53 | $150.00 | $182.45 | $890.00 |
| 21 | Water (659E35000) | MGAL | 15 | $1.00 | $1.22 | $110.00 |
| 22 | Slope erosion protection (670E00500) | SY | 479 | $2.00 | $2.43 | $3.00 |
| 23 | Ditch erosion protection mat, type C (670E00730) | SY | 18 | $2.50 | $3.04 | $20.00 |
| 24 | Storm water pollution prevention plan (832E15000) | LS | 1 | $3,100.00 | $2,432.63 | $3,300.00 |
| 25 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $8,000.00 | $7,297.89 | $12,000 |
| 26 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $5,250.00 | $6,271.12 | $5,800.00 |
| 27 | Erosion control (832E30000) | EACH | 10,000 | $1.00 | $1.00 | $1.00 |
| 28 | Rock channel protection, type B with filter (601E32100) | CY | 12 | $185.00 | $180.91 | $190.00 |
| 29 | Rock channel protection, type C with filter (601E32200) | CY | 61 | $160.00 | $166.41 | $110.00 |
| 30 | Concrete masonry (602E20000) | CY | 2 | $3,175.00 | $4,858.98 | $3,900.00 |
| 31 | Aggregate drains (605E31100) | FT | 236 | $20.00 | $44.21 | $30.00 |
| 32 | 6" conduit, type B (611E00900) | FT | 50 | $22.50 | $48.83 | $15.00 |
| 33 | 6" conduit, type E (611E01400) | FT | 50 | $22.00 | $48.83 | $15.00 |
| 34 | 6" conduit, type F (611E01500) | FT | 50 | $22.00 | $38.38 | $15.00 |
| 35 | 12" conduit, type A (611E04200) | FT | 6 | $194.00 | $130.29 | $240.00 |
| 36 | 12" conduit, type B (611E04400) | FT | 201 | $114.00 | $106.02 | $140.00 |
| 37 | 15" conduit, type A (611E05700) | FT | 50 | $150.00 | $189.95 | $160.00 |
| 38 | 43" X 68" conduit, type A, 706.04 (611E53100) | FT | 68 | $620.00 | $790.26 | $730.00 |
| 39 | Catch basin, no. 3A (611E98180) | EACH | 1 | $4,000.00 | $4,753.93 | $5,700.00 |
| 40 | Catch basin, no. 2-2B (611E98470) | EACH | 1 | $3,300.00 | $3,918.32 | $3,400.00 |
| 41 | Pavement planing, asphalt concrete (variable, 1 1/ (254E01000) | SY | 1,111 | $9.00 | $15.03 | $20.00 |
| 42 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 427 | $265.00 | $262.00 | $290.00 |
| 43 | Aggregate base (304E20000) | CY | 449 | $115.00 | $136.96 | $130.00 |
| 44 | Tack coat (407E10000) | GAL | 371 | $3.50 | $6.08 | $5.00 |
| 45 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 256 | $315.00 | $279.50 | $310.00 |
| 46 | RPM (621E00100) | EACH | 21 | $150.00 | $182.45 | $170.00 |
| 47 | Raised pavement marker removed (621E54000) | EACH | 20 | $14.00 | $54.17 | $20.00 |
| 48 | Ground mounted support, no. 3 post (630E03100) | FT | 265 | $25.00 | $30.41 | $30.00 |
| 49 | Sign post reflector (630E08600) | EACH | 16 | $52.00 | $72.98 | $60.00 |
| 50 | Sign, flat sheet (630E80100) | SF | 54 | $25.00 | $38.92 | $30.00 |
| 51 | Removal of ground mounted sign and disposal (630E84900) | EACH | 11 | $25.00 | $91.22 | $30.00 |
| 52 | Removal of ground mounted sign and reerection (630E85100) | EACH | 19 | $150.00 | $115.55 | $170.00 |
| 53 | Removal of ground mounted post support and disposal (630E86002) | EACH | 21 | $25.00 | $48.65 | $30.00 |
| 54 | Edge line, 6", type 1 (642E00104) | MI | 0.58 | $1,375.00 | $1,672.43 | $4,400.00 |
| 55 | Center line, type 1 (642E00300) | MI | 0.19 | $3,225.00 | $3,922.63 | $8,100.00 |
| 56 | Stop line (644E00500) | FT | 52 | $16.50 | $20.07 | $45.00 |
| 57 | Dotted line, 6" (644E01510) | FT | 230 | $6.00 | $6.99 | $9.50 |
| 58 | Special - work zone traffic signal (614E11300) | EACH | 2 | $32,000 | $22,564 | $1,000.00 |
| 59 | Increased barrier delineation (614E11630) | FT | 1,540 | $0.75 | $1.40 | $1.50 |
| 60 | Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384) | EACH | 6 | $2,200.00 | $3,054.33 | $2,400.00 |
| 61 | Work zone lighting system (614E12740) | EACH | 1 | $11,000 | $6,550.75 | $4,000.00 |
| 62 | Barrier reflector, type 1, (bidirectional) (614E13310) | EACH | 31 | $12.00 | $34.06 | $30.00 |
| 63 | Portable changeable message sign (614E18600) | SNMT | 12 | $1,750.00 | $2,128.55 | $1,900.00 |
| 64 | Work zone center line, class I (614E21000) | MI | 0.30 | $12,925 | $15,721 | $14,000 |
| 65 | Work zone edge line, class I, 6", 740.06, type I (614E22210) | MI | 0.92 | $8,850.00 | $10,764 | $9,800.00 |
| 66 | Work zone stop line, class I, 740.06, type I (614E26400) | FT | 55 | $12.00 | $14.60 | $15.00 |
| 67 | Pavement for maintaining traffic, class B (615E25000) | SY | 375 | $110.00 | $104.39 | $180.00 |
| 68 | Water (616E10000) | MGAL | 10 | $140.00 | $12.16 | $0.10 |
| 69 | Portable barrier, unanchored (622E41100) | FT | 1,540 | $21.00 | $25.02 | $25.00 |
| 70 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $5,221.90 | $11,378 | $10,000 |
| 71 | Maintaining traffic (614E11000) | LS | 1 | $20,000 | $12,406 | $120,000 |
| 72 | Construction layout stakes and surveying (623E10000) | LS | 1 | $25,000 | $5,838.31 | $35,000 |
| 73 | Mobilization (624E10000) | LS | 1 | $59,731 | $42,750 | $45,000 |
| 100 | Object marker, two way (614E13360) | EACH | 31 | $22.00 | $36.49 | $35.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 9, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.