ODOT contract 260206 bid tabulation
MAR-SR 746-09.05 (BRIDGE REPAIR). Let by Ohio DOT on April 23, 2026, MAR. 3 bids received; low bid $1,340,165 by Double Z Construction Company, +12% against the engineer's estimate of $1,200,000.
- Owner
- Ohio DOT
- Letting
- 23 APR 2026
- Pay items
- 75
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Double Z Construction Company | $1,340,165 | Low | +12% |
| 2 | Complete General Construction Company | $1,372,124 | +2.0% | +14% |
| 3 | Shelly & Sands Inc | $1,540,870 | +15% | +28% |
Engineer's estimate: $1,200,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Double Z Construction Company | 2. Complete General Construction Company | 3. Shelly & Sands Inc |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $5,000.00 | $5,000.00 | $10,000 |
| 2 | Pavement removed (202E23000) | SY | 237.23 | $45.00 | $21.00 | $30.00 |
| 3 | Guardrail removed (202E38000) | FT | 200 | $8.00 | $2.00 | $4.00 |
| 4 | Bridge terminal assembly removed (202E47000) | EACH | 4 | $80.00 | $350.00 | $160.00 |
| 5 | Excavation (203E10000) | CY | 85 | $80.00 | $30.00 | $50.00 |
| 6 | Embankment (203E20000) | CY | 178 | $30.00 | $50.00 | $25.00 |
| 7 | Subgrade compaction (204E10000) | SY | 260 | $10.00 | $4.00 | $12.00 |
| 8 | Proof rolling (204E45000) | HR | 1 | $180.00 | $130.00 | $300.00 |
| 9 | Guardrail, type MGS with long posts (606E15100) | FT | 200 | $27.60 | $27.60 | $27.00 |
| 10 | MGS bridge terminal assembly, type 1 (606E35002) | EACH | 4 | $2,520.00 | $2,520.00 | $2,700.00 |
| 11 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 8 | $200.00 | $165.00 | $250.00 |
| 12 | Topsoil (659E00300) | CY | 56.61 | $85.00 | $45.00 | $100.00 |
| 13 | Seeding and mulching (659E10000) | SY | 510 | $10.00 | $6.50 | $15.00 |
| 14 | Repair seeding and mulching (659E14000) | SY | 26 | $4.80 | $1.50 | $1.00 |
| 15 | Inter-seeding (659E15000) | SY | 26 | $4.80 | $0.10 | $1.00 |
| 16 | Commercial fertilizer (659E20000) | TON | 0.07 | $750.00 | $750.00 | $1,000.00 |
| 17 | Lime (659E31000) | ACRE | 0.11 | $10.00 | $90.00 | $175.00 |
| 18 | Water (659E35000) | MGAL | 2 | $1.00 | $0.50 | $1.00 |
| 19 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 | $1.00 |
| 20 | 6" unclassified pipe underdrains (605E13300) | FT | 20 | $10.00 | $25.00 | $55.00 |
| 21 | Aggregate drains (605E31100) | FT | 50 | $20.00 | $25.00 | $50.00 |
| 22 | 6" conduit, type F (611E01500) | FT | 20 | $10.00 | $60.00 | $35.00 |
| 23 | Precast reinforced concrete outlet (611E99710) | EACH | 1 | $450.00 | $300.00 | $500.00 |
| 24 | Pavement planing, asphalt concrete, variable depth (254E01000) | SY | 118 | $22.00 | $22.00 | $60.00 |
| 25 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 81 | $240.00 | $290.00 | $600.00 |
| 26 | Aggregate base (304E20000) | CY | 104 | $105.00 | $140.00 | $200.00 |
| 27 | Non-tracking tack coat (407E20000) | GAL | 60 | $4.25 | $4.25 | $3.50 |
| 28 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 45 | $300.00 | $325.00 | $900.00 |
| 29 | Compacted aggregate (617E10100) | CY | 25 | $120.00 | $210.00 | $115.00 |
| 30 | Barrier reflector, type 5, bidirectional (626E00116) | EACH | 16 | $12.00 | $12.00 | $20.00 |
| 31 | Ground mounted support, no. 3 post (630E03100) | FT | 75 | $22.40 | $22.40 | $24.00 |
| 32 | Sign post reflector (630E08600) | EACH | 2 | $45.00 | $45.00 | $53.00 |
| 33 | Sign, flat sheet (630E80100) | SF | 18 | $25.00 | $25.00 | $27.00 |
| 34 | Removal of ground mounted sign and disposal (630E84900) | EACH | 6 | $15.00 | $15.00 | $54.00 |
| 35 | Edge line, 4" (644E00100) | MI | 0.04 | $12,780 | $12,780 | $14,000 |
| 36 | Center line (644E00300) | MI | 0.01 | $24,500 | $24,500 | $26,000 |
| 37 | Edge line, 4" (646E10000) | MI | 0.09 | $12,780 | $12,780 | $13,700 |
| 38 | Center line (646E10200) | MI | 0.05 | $24,500 | $24,500 | $24,500 |
| 39 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 40 | $70.00 | $95.00 | $110.00 |
| 40 | Detour signing (614E12420) | LS | 1 | $10,000 | $7,000.00 | $7,500.00 |
| 41 | Water (616E10000) | MGAL | 5 | $35.00 | $150.00 | $200.00 |
| 42 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $250,000 | $345,000 | $264,600 |
| 43 | Approach slab removed (202E22900) | SY | 79 | $70.00 | $70.00 | $100.00 |
| 44 | Wearing course removed (202E23500) | SY | 620 | $15.00 | $14.00 | $15.00 |
| 45 | Unclassified excavation, as per plan (503E21301) | LS | 1 | $20,000 | $24,000 | $30,000 |
| 46 | Galvanized steel reinforcement (509E26000) | LB | 6,228 | $2.50 | $2.25 | $2.99 |
| 47 | No. 4 deformed GFRP reinforcement (509E30020) | FT | 9,790 | $1.45 | $1.42 | $1.50 |
| 48 | No. 5 deformed GFRP reinforcement (509E30030) | FT | 36,350 | $1.60 | $1.60 | $1.50 |
| 49 | No. 6 GFRP deformed bars (509E30040) | FT | 1,735 | $1.80 | $1.86 | $1.70 |
| 50 | No. 8 deformed GFRP reinforcement (509E30060) | FT | 254 | $2.60 | $3.35 | $4.00 |
| 51 | Dowel holes with nonshrink, nonmetallic grout (510E10000) | EACH | 168 | $30.00 | $20.00 | $35.00 |
| 52 | Semi-integral diaphragm guide (511E33500) | EACH | 2 | $5,000.00 | $4,500.00 | $7,000.00 |
| 53 | Class QC2 concrete with QC/QA, bridge deck (511E34446) | CY | 203 | $1,350.00 | $1,300.00 | $1,350.00 |
| 54 | Class QC1 concrete, abutment (511E45710) | CY | 16 | $1,700.00 | $1,500.00 | $3,300.00 |
| 55 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 136 | $54.00 | $35.25 | $38.00 |
| 56 | Structural steel members, level 1, as per plan (513E10221) | LB | 648 | $46.00 | $43.75 | $57.50 |
| 57 | Welded stud shear connectors (513E20000) | EACH | 15 | $53.25 | $53.25 | $57.00 |
| 58 | Structural steel, misc.: drilled holes (513E95030) | EACH | 30 | $86.00 | $86.00 | $86.00 |
| 59 | Field painting, misc.: coating of beam ends (514E27700) | SF | 315 | $198.00 | $175.00 | $179.00 |
| 60 | 2" preformed expansion joint filler (516E13900) | SF | 43 | $16.00 | $17.00 | $4.00 |
| 61 | Semi-integral abutment expansion joint seal (516E14020) | FT | 97 | $40.00 | $48.00 | $51.00 |
| 62 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44101) | EACH | 10 | $3,200.00 | $1,110.00 | $1,232.00 |
| 63 | Refurbish bearing device, as per plan (516E45305) | EACH | 10 | $3,500.00 | $2,500.00 | $4,200.00 |
| 64 | Jacking and temporary support of superstructure, as per plan (516E47001) | LS | 1 | $45,000 | $34,000 | $41,000 |
| 65 | Railing (twin steel tube) (517E70000) | FT | 358 | $260.00 | $246.00 | $200.00 |
| 66 | Porous backfill with geotextile fabric (518E21200) | CY | 38 | $140.00 | $120.00 | $160.00 |
| 67 | Special - steel drip strip (518E22300) | FT | 412 | $20.00 | $20.00 | $18.00 |
| 68 | Reinforced concrete approach slabs (T=13") (526E15000) | SY | 125 | $550.00 | $480.00 | $650.00 |
| 69 | Type A installation (526E90010) | FT | 65 | $340.00 | $300.00 | $400.00 |
| 70 | Structure grounding system (625E33000) | EACH | 1 | $13,776 | $16,000 | $38,600 |
| 71 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $10,000 | $10,000 | $10,000 |
| 72 | Maintaining traffic (614E11000) | LS | 1 | $4,500.00 | $4,500.00 | $25,000 |
| 73 | Field office, type B (619E16010) | MNTH | 3 | $2,000.00 | $5,000.00 | $6,500.00 |
| 74 | Construction layout stakes and surveying (623E10000) | LS | 1 | $15,000 | $16,000 | $20,000 |
| 75 | Mobilization (624E10000) | LS | 1 | $50,000 | $60,000 | $75,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 23, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.