ODOT contract 260449 bid tabulation
HEN-US 6/CR 424 Infields TP (PARKING AREAS). Let by Ohio DOT on October 1, 2026, HEN. 2 bids received; low bid $3,154,858 by E S Wagner - Vernon Nagel Joint Venture, -1.8% against the engineer's estimate of $3,214,000.
- Owner
- Ohio DOT
- Letting
- 01 OCT 2026
- Pay items
- 94
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | E S Wagner - Vernon Nagel Joint Venture | $3,154,858 | Low | -2.0% |
| 2 | Great Lakes Construction Co | $3,696,619 | +17% | +15% |
Engineer's estimate: $3,214,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. E S Wagner - Vernon Nagel Joint Venture | 2. Great Lakes Construction Co |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $84,000 | $350.00 |
| 2 | Pavement removed (202E23000) | SY | 86 | $31.69 | $39.00 |
| 3 | Guardrail removed (202E38000) | FT | 137.50 | $2.40 | $2.40 |
| 4 | Anchor assembly removed, type E (202E42010) | EACH | 1 | $165.00 | $165.00 |
| 5 | Bridge terminal assembly removed (202E47000) | EACH | 1 | $100.00 | $100.00 |
| 6 | Excavation (203E10000) | CY | 721 | $57.00 | $23.00 |
| 7 | Embankment (203E20000) | CY | 19,955 | $10.00 | $28.75 |
| 8 | Subgrade compaction (204E10000) | SY | 17,525 | $1.80 | $1.70 |
| 9 | Excavation of subgrade (204E13000) | CY | 562 | $57.00 | $25.00 |
| 10 | Granular material, type C (204E30020) | CY | 562 | $63.00 | $58.00 |
| 11 | Proof rolling (204E45000) | HR | 6 | $184.00 | $250.00 |
| 12 | Geotextile fabric (204E50000) | SY | 1,687 | $2.50 | $4.00 |
| 13 | Ditch cleanout (209E10000) | FT | 453 | $20.00 | $4.50 |
| 14 | Reshaping under guardrail (209E15000) | STA | 1 | $125.00 | $125.00 |
| 15 | Guardrail, type MGS (606E15050) | FT | 25 | $58.00 | $58.00 |
| 16 | Anchor assembly, MGS type E (606E26150) | EACH | 1 | $3,320.00 | $3,320.00 |
| 17 | MGS bridge terminal assembly, type 1 (606E35002) | EACH | 1 | $3,460.00 | $3,460.00 |
| 18 | Fence, misc.:wooden slat fence (607E98000) | FT | 38 | $267.50 | $267.50 |
| 19 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $1,850.00 | $2,500.00 |
| 20 | Post construction survey monument verification and report (623E51000) | LS | 1 | $1,850.00 | $2,500.00 |
| 21 | Special - bollard (690E50600) | EACH | 5 | $940.00 | $940.00 |
| 22 | Inspection and compaction testing of unbound materials (878E25000) | LS | 1 | $61,093 | $56,000 |
| 23 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 14 | $125.00 | $165.00 |
| 24 | Rock channel protection, type C with filter (601E32200) | CY | 1 | $200.00 | $300.00 |
| 25 | Rock channel protection, type D with aggregate filter (601E32310) | CY | 17 | $160.00 | $215.00 |
| 26 | Soil analysis test (659E00100) | EACH | 2 | $40.00 | $60.00 |
| 27 | Topsoil (659E00300) | CY | 1,170 | $21.00 | $26.00 |
| 28 | Seeding and mulching, class 6 (659E00590) | SY | 7,106 | $2.00 | $3.40 |
| 29 | Seeding and mulching (659E10000) | SY | 3,330 | $1.00 | $1.80 |
| 30 | Commercial fertilizer (659E20000) | TON | 0.97 | $700.00 | $850.00 |
| 31 | Lime (659E31000) | ACRE | 1.49 | $0.50 | $35.00 |
| 32 | Water (659E35000) | MGAL | 40 | $15.00 | $1.00 |
| 33 | Sodding staked (660E25000) | SY | 153 | $14.00 | $15.50 |
| 34 | Slope erosion protection (670E00500) | SY | 8,440 | $1.60 | $1.80 |
| 35 | Storm water pollution prevention plan (832E15000) | LS | 1 | $2,900.00 | $1,000.00 |
| 36 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $10,440 | $9,000.00 |
| 37 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $13,200 | $12,000 |
| 38 | Erosion control (832E30000) | EACH | 34,537 | $1.00 | $1.00 |
| 39 | Concrete masonry (602E20000) | CY | 0.27 | $3,200.00 | $2,700.00 |
| 40 | 6" unclassified pipe underdrains (605E13300) | FT | 121 | $22.00 | $17.00 |
| 41 | 6" base pipe underdrains (605E14000) | FT | 6,968 | $15.66 | $17.00 |
| 42 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 485 | $25.00 | $18.50 |
| 43 | 12" conduit, type B (611E04400) | FT | 224 | $101.00 | $130.00 |
| 44 | 15" conduit, type C (611E06100) | FT | 133 | $101.00 | $130.00 |
| 45 | Catch basin, no. 3 (611E98150) | EACH | 5 | $5,200.00 | $7,500.00 |
| 46 | Catch basin, no. 2-3 (611E98510) | EACH | 1 | $3,200.00 | $5,250.00 |
| 47 | Precast reinforced concrete outlet (611E99710) | EACH | 7 | $375.00 | $450.00 |
| 48 | Aggregate base (304E20000) | CY | 3,938 | $60.57 | $65.00 |
| 49 | 8" non-reinforced concrete pavement, class QC 1P (452E12010) | SY | 16,897 | $82.98 | $92.25 |
| 50 | Curb, type 7 (609E28000) | FT | 1,979 | $20.17 | $37.00 |
| 51 | 4" concrete traffic island (609E50000) | SY | 207 | $74.93 | $42.00 |
| 52 | 4" concrete median (609E70000) | SY | 77 | $92.41 | $48.00 |
| 53 | Curb, misc.:curb, type 7 turnout (609E98100) | EACH | 7 | $1,090.87 | $1,600.00 |
| 54 | 4" conduit, type E (611E00400) | FT | 60 | $10.61 | $10.50 |
| 55 | Connection, fused pull apart (625E00450) | EACH | 10 | $207.16 | $203.00 |
| 56 | Connection, unfused permanent (625E00480) | EACH | 9 | $207.16 | $203.00 |
| 57 | Light tower, misc.: light tower BBBB45 (625E13500) | EACH | 5 | $21,489 | $21,058 |
| 58 | Light tower foundation, misc.:36" X 10' deep (625E15700) | EACH | 5 | $5,600.44 | $5,488.00 |
| 59 | No. 2 AWG 2400 volt distribution cable (625E23300) | FT | 4,245 | $6.84 | $6.70 |
| 60 | Conduit, 3", 725.051 (625E25504) | FT | 1,375 | $8.27 | $8.10 |
| 61 | Luminaire, high mast, solid state (LED), as per plan (625E26263) | EACH | 20 | $1,908.31 | $1,870.00 |
| 62 | Trench, 24" deep (625E29002) | FT | 1,375 | $10.00 | $9.80 |
| 63 | Pull box, 725.08, 24" (625E30706) | EACH | 3 | $1,787.89 | $1,752.00 |
| 64 | Ground rod (625E32000) | EACH | 10 | $530.65 | $520.00 |
| 65 | Power service, as per plan (625E34001) | EACH | 1 | $4,923.85 | $4,825.00 |
| 66 | Control center cabinet, complete (625E34450) | EACH | 1 | $7,251.59 | $7,106.00 |
| 67 | Underground warning marking tape (625E36010) | FT | 1,375 | $2.76 | $2.70 |
| 68 | Arc flash calculations and label, lighting control (625E76000) | EACH | 1 | $2,809.91 | $2,753.50 |
| 69 | Barrier reflector, type 2, bidirectional (626E00110) | EACH | 2 | $15.00 | $15.00 |
| 70 | Ground mounted support, no. 3 post (630E03100) | FT | 244 | $16.00 | $13.50 |
| 71 | Ground mounted structural beam support, W8X18 (630E07000) | FT | 100 | $75.00 | $58.15 |
| 72 | Breakaway structural beam connection (630E09000) | EACH | 4 | $820.00 | $850.00 |
| 73 | Sign support assembly, pole mounted (630E79500) | EACH | 6 | $265.00 | $190.00 |
| 74 | Sign support assembly, bridge mounted, type 2 (630E79604) | EACH | 1 | $2,780.00 | $2,750.00 |
| 75 | Sign, flat sheet (630E80100) | SF | 181 | $21.00 | $16.85 |
| 76 | Sign, ground mounted extrusheet (630E80200) | SF | 220 | $27.00 | $26.85 |
| 77 | Ground mounted structural beam support foundation (630E84500) | EACH | 4 | $1,525.00 | $1,200.00 |
| 78 | Removal of ground mounted sign and disposal (630E84900) | EACH | 8 | $15.00 | $21.00 |
| 79 | Removal of ground mounted post support and disposal (630E86002) | EACH | 4 | $20.00 | $26.50 |
| 80 | Parking lot stall marking (646E20200) | FT | 7,354 | $3.10 | $2.10 |
| 81 | Lane arrow (646E20300) | EACH | 5 | $220.00 | $210.00 |
| 82 | Special - work zone traffic signal (614E11300) | EACH | 2 | $8,434.79 | $20,700 |
| 83 | Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384) | EACH | 2 | $2,620.00 | $2,280.44 |
| 84 | Barrier reflector, type 1 BI-directional (614E13310) | EACH | 10 | $10.00 | $12.89 |
| 85 | Object marker, two way (614E13360) | EACH | 9 | $18.00 | $23.84 |
| 86 | Work zone center line, class I (614E21000) | MI | 0.06 | $7,500.00 | $7,800.00 |
| 87 | Work zone edge line, class I, 6" (614E22010) | MI | 0.13 | $3,500.00 | $7,800.00 |
| 88 | Work zone stop line, class I (614E26000) | FT | 40 | $5.00 | $5.00 |
| 89 | Water (616E10000) | MGAL | 46 | $100.00 | $50.00 |
| 90 | Portable barrier, unanchored (622E41100) | FT | 430 | $18.40 | $53.00 |
| 91 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $14,187 | $26,000 |
| 92 | Maintaining traffic (614E11000) | LS | 1 | $38,942 | $45,000 |
| 93 | Construction layout stakes and surveying (623E10000) | LS | 1 | $30,000 | $23,000 |
| 94 | Mobilization (624E10000) | LS | 1 | $157,243 | $184,500 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 1, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.