ODOT letting results, July 13, 2023
11 contracts let by Ohio DOT on July 13, 2023, $20,854,572 in low bids, a median of 2 bidders per contract. On the 11 with an engineer's estimate, the low bid came in under it 3 times; median low bid +4.0% against the estimate.
- Owner
- Ohio DOT
- Contracts
- 11
- Low bids, total
- $20,854,572
- Data through
- 12 NOV 2026
Contracts let that day
| Contract | Project | County | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 230386 | WOO-IR 75-26.02 Resurf (FOUR LANE RESURFACING) | WOO | 3 | Gerken Paving Inc | $6,250,054 | $6,580,146 | +5.0% | 0.0% | ODOT |
| 230385 | PIK-SR 32-00.00/09.92 (FOUR LANE RESURFACING) | PIK | 2 | Shelly & Sands Inc | $4,384,115 | $4,525,553 | +3.0% | +4.0% | ODOT |
| 238005 | HEN-SR 110-00.30 Resurfacing (FOUR LANE RESURFACING) | HEN | 1 | Gerken Paving Inc | $3,956,531 | -2.0% | ODOT | ||
| 230383 | MOT-SR 4-00.00 (TWO LANE RESURFACING) | MOT | 2 | Barrett Paving Materials Inc | $1,092,101 | $1,196,471 | +10% | +5.0% | ODOT |
| 230382 | GRE-Yellow Spgs Multi-Modal FY23 (SIDEWALK) | GRE | 3 | R B Jergens Contractors Inc | $962,731 | $1,096,891 | +14% | +1.0% | ODOT |
| 230393 | ROS-US 35-24.19 (BRIDGE REPAIR) | ROS | 3 | Complete General Construction Company | $870,210 | $895,290 | +3.0% | -19% | ODOT |
| 230384 | NOB-IR 77-11.97 (CULVERT REPLACEMENT) | NOB | 4 of 5 | $867,571 | $889,230 | +2.0% | +14% | ODOT | |
| 230381 | D01-TSG-FY2024 (SIGNALIZATION) | District 1 | 3 | Perram Electric Inc | $771,900 | $826,750 | +7.0% | +5.0% | ODOT |
| 230390 | D07-TSG MAINT FY24 (SIGNALIZATION) | District 7 | 1 | Capital Electric Line Builders Inc | $638,442 | -7.0% | ODOT | ||
| 230380 | COL-SR 14T-00.00 (CHIP SEAL) | COL | 2 | Melway Paving Co Inc | $621,814 | $655,679 | +5.0% | +9.0% | ODOT |
| 230391 | D12-CS FY2024 (CRACK SEALING) | District 12 | 2 | Scodeller Construction Inc | $439,104 | $978,894 | +123% | +6.0% | ODOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than ODOT received, the others did not match their published totals and are left out.