ODOT letting results, September 14, 2023

15 contracts let by Ohio DOT on September 14, 2023, $27,068,615 in low bids, a median of 4 bidders per contract. On the 15 with an engineer's estimate, the low bid came in under it 8 times; median low bid -4.0% against the estimate.

Owner
Ohio DOT
Contracts
15
Low bids, total
$27,068,615
Data through
12 NOV 2026

Contracts let that day

ContractProjectCountyBidsLow bidderLow bidSecond bidGapAgainst estimateSource
230450LIC-SR 16/SR 79-20.26/12.46 (FOUR LANE RESURFACING)LIC2Shelly Company$6,388,998$7,411,837+16%+6.0%ODOT
230446D05-Guardrail FY2024 (GUARDRAIL REBUILDING)District 52M P Dory Co$2,879,253$3,064,935+6.0%-23%ODOT
230444COL-SR 164/SR 644-15.72/03.96 (TWO LANE RESURFACING)COL3Shelly Company$2,752,206$2,760,9430.0%+14%ODOT
230451MOT-BH-FY24 (BRIDGE REPAIR)MOT6BCC Ohio Inc$2,590,157$2,844,821+10%+23%ODOT
230447FRA-IR 70-20.29 (Courtright Rd.) (BRIDGE REPAIR)FRA5Ruhlin Company$2,543,664$2,601,942+2.0%-23%ODOT
230445CRA-OVERLAY VAR (TWO LANE RESURFACING)CRA2Kokosing Construction Company Inc$2,491,167$2,535,562+2.0%+4.0%ODOT
230448GRE-US 42-11.26 (TWO LANE RESURFACING)GRE2John R Jurgensen Company$1,800,093$2,241,200+25%+17%ODOT
230438SUM-IR 271-01.51 (BRIDGE REPAIR)SUM5Ruhlin Company$1,731,081$1,879,815+9.0%-9.0%ODOT
230456MAH-LG FY2024 (LIGHTING)MAH4Cornerstone Electric Inc$1,353,662$1,771,500+31%-18%ODOT
230443BEL-US 40-27.30 (CULVERT REPLACEMENT)BEL4Shelly & Sands Inc$818,020$963,275+18%+20%ODOT
230442ALL-SR 115-01.11 (SLIDE REPAIR)ALL6Allied Construction, LLC$600,000$698,104+16%-4.0%ODOT
234021CLI-/GRE Culvert Repair FY2024 (CULVERT REPLACEMENT)CLI4BCC Ohio Inc$392,926$507,372+29%-18%ODOT
230454WOO-SR 795-03.26 Intrsect Upgrade (SIGNALIZATION)WOO4Miller Cable Company$341,200$347,965+2.0%+2.0%ODOT
230455D03-PR FY2024 (B) (PRUNING/OR TREE/BRUSH REMOVAL)District 34Ecotree Services LLC$217,525$224,450+3.0%-7.0%ODOT
230452MRG-CR Guardrail FY 2024 (GUARDRAIL REBUILDING)MRG4Cuyahoga Fence LLC$168,661$168,9690.0%-16%ODOT
ODOT contracts let on September 14, 2023, largest low bid first

Gap is the second bid over the low bid. Where a contract shows fewer bids than ODOT received, the others did not match their published totals and are left out.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy